This text of Indiana § 13-18-27-18 (Limitation on authority of MS4 community to order construction project to stop) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 13-18-27-18 (2026).

Text

(a)If:
(1)an MS4 community has made a conclusive favorable determination concerning a construction plan; and
(2)work on the construction project has begun; the MS4 community may not order work on the construction project to stop on the grounds that the erosion and sediment control measures included in the construction plan are not adequate unless the project site owner is notified in writing of the inadequacies that the MS4 community perceives in the erosion and sediment control measures and the perceived inadequacies are not resolved within seventy-two (72) hours after the project site owner receives the written notice.
(b)This section does not prohibit an MS4 community from ordering work on a construction project to stop if the project site owner is creating a public health hazard or

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

As added by P.L.248-2019, SEC.14.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Indiana § 13-18-27-18, Counsel Stack Legal Research, https://law.counselstack.com/statute/in/13-18-27-18.