§ 13-18-27-16 — Time limit for review authority's preliminary determination of whether construction plan is substantially complete

Indiana·Art. 18 WATER POLLUTION CONTROL·Ch. 27 Erosion and Sediment Control in Construction Projects
(a)A review authority to which a construction plan is submitted must make a preliminary determination whether the construction plan is substantially complete before the end of:
(1)the tenth working day after the day on which the construction plan is submitted to the review authority, in the case of a small or very small construction activity site; or
(2)the fourteenth working day after the day on which the construction plan is submitted to the review authority, in the case of a large construction activity site.
(b)If a review authority to which a construction plan is submitted under subsection (a):
(1)makes a preliminary determination that the construction plan is substantially complete; and
(2)notifies the project site owner of its favorable preliminary determination; before the end

Free access — add to your briefcase to read the full text and ask questions with AI

Indiana § 13-18-27-16 (Time limit for review authority's preliminary determination of whether construction plan is substantially complete) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

As added by P.L.248-2019, SEC.14.

Nearby Sections

15
View on official source ↗