(1)The department may use a design-build contract for
a transportation project if the design work for such project must be performed
before a potential bidder can develop a price or cost proposal for such project and
if the chief engineer of the engineering, design, and construction division
determines that using a design-build contract is appropriate. The chief engineer
shall consider the following factors in making a determination pursuant to this
subsection (1):
(a)The extent to which the transportation project requirements are
adequately defined;
(b)The time constraints for completing the transportation project;
(c)The capability and experience of potential design-build firms;
(d)The suitability of the transportation project to a design-build contract;
and
(e)The cap
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
Source: L. 99: Entire part added, p. 258, � 1, effective April 9.
Nearby Sections
15
§ 43-1-1001
Urban mass transportation grants§ 43-1-1002
Rules and regulations§ 43-1-101
Legislative declaration§ 43-1-102
Definitions§ 43-1-103
Department created - executive director§ 43-1-107
Duties of deputy director§ 43-1-109
Chief engineer§ 43-1-1101
Legislative declaration§ 43-1-1102
Definitions§ 43-1-1103
Transportation planning§ 43-1-1104
Transportation advisory committeeCite This Page — Counsel Stack
Bluebook (online)
Colorado § 43-1-1404, Counsel Stack Legal Research, https://law.counselstack.com/statute/co/43/43-1-1404.