§ 32-11-617 — Extra work authorized - payment
Extra work may arise in
connection with any project mentioned in this article and not particularly provided
for in the plans, specifications, estimates, bids and contracts; and such extra work
shall be performed by the contractor at the direction of the engineer at cost of
labor and materials and overhead including superintendence as set forth in the
plans, specifications, or construction contract, such amount to be included in the
assessment for the project (but not exceeding in the aggregate the estimated
maximum special benefits to any tract so assessed) or to be paid out of the general
or other funds of the district available therefor, in the discretion of the board.
Free access — add to your briefcase to read the full text and ask questions with AI
Colorado § 32-11-617 (Extra work authorized - payment) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
Source: L. 69: p. 793, � 130. C.R.S. 1963: � 89-21-130.
Nearby Sections
15
§ 32-1-1001
Common powers - definitions§ 32-1-1003
Health service districts - additional powers§ 32-1-1009
Regional tourism projects§ 32-1-101
Short title§ 32-1-102
Legislative declaration§ 32-1-103
Definitions§ 32-1-104.8
Information statement regarding taxes and debt§ 32-1-106
Repetitioning of elections - time limits§ 32-1-107
Service area of special districts§ 32-1-108
Correction of faulty notices§ 32-1-109
Early hearings