Zurn Engineers v. STATE OF CALIF., DEPT. WATER RES

69 Cal. App. 3d 798, 138 Cal. Rptr. 478, 1977 Cal. App. LEXIS 1467
CourtCalifornia Court of Appeal
DecidedMay 17, 1977
DocketCiv. 48784
StatusPublished
Cited by10 cases

This text of 69 Cal. App. 3d 798 (Zurn Engineers v. STATE OF CALIF., DEPT. WATER RES) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zurn Engineers v. STATE OF CALIF., DEPT. WATER RES, 69 Cal. App. 3d 798, 138 Cal. Rptr. 478, 1977 Cal. App. LEXIS 1467 (Cal. Ct. App. 1977).

Opinion

*802 Opinion

LORING, J. *

Plaintiff-respondent Zura Engineers, a California corporation, formerly known as Pascal & Ludwig, Inc. (Contractor) recovered judgment after a nonjury trial against defendant-appellant State of California, acting by and through its Department of Water Resources (State), in the aggregate sum of $896,245.89 with interest at 7 percent per annum from December 21, 1967, on four causes of action which arose out of the alleged breach of a contract for the construction of the Grizzly Valley Dam (Dam) in Plumas County, California. 1 Contractor’s complaint as amended alleged 12 causes of action for “extra” work aggregating $1,238,275.31. The contract contained provisions authorizing the State Engineer, or his designated representative, 2 to decide disputes including claims for extra compensation between Contractor and State and making his decision “Final and conclusive unless it is fraudulent or capricious or arbitrary or so grossly erroneous as necessarily to imply bad faith. Contractor filed 27 claims for extra compensation on which it was awarded $127,297.68. The trial court, disregarding the decision of the Engineer, tried the case de novo; that is, the court received original evidence bearing upon the Contractor’s claims for extras and made findings that State had made certain representations to Contractor which were untrue which caused damage to Contractor, and rendered judgment accordingly in favor of Contractor on the first four causes of action. The trial court rendered judgment in favor of State on the last eight causes of action. State appeals from the judgment in favor of Contractor on the first four causes of action but Contractor does not appeal from the judgment in favor of State on the last eight causes of action. We will, therefore, affirm the judgment in favor of State on the eight causes of action and treat the case as if it originally contained only the four causes of action on which this appeal is based.

Preliminary Facts

Commencing at least as early as 1954, State began to formulate plans for the construction of Dam. Periodically topographic surveys and maps *803 and geologic studies were made of the proposed site and some rotary core drilling was performed. By June of 1964, plans and specifications were prepared and the project was let for public bidding at unit prices for 66 different items of work. Many of the 66 items of work were for a specific quantity measured in terms of cubic feet, linear feet, pounds, tons or barrels. At the end of the 66 items, State included the following caveat: “The foregoing quantities are approximate only, being given as a basis for the comparison of bids and the Department of Water Resources does not, expressly or by implication, agree that the actual amount of work will correspond therewith, but reserves the right to increase or decrease the amount of any class or portion of the work, or to omit portions of the work, as may be deemed necessary or advisable by the Engineer.”

Contractor was the low bidder at an aggregate price of $1,833,131 based on State’s quantity estimates. The project included a 700-foot, 36-inch diameter outlet conduit constructed of steel pipe embedded in concrete under the embankment with upstream intake tower and downstream control valves (which was designed to allow drainage of water from the reservoir) and a concrete overflow chute-type spillway to accommodate any excess flow of water. The embankment of the Dam was composed of a core of impervious earth (Zone 1 material) against which gravel was banked upstream (Zone 2 material), against which sand and gravel were banked at a uniform width, both upstream and downstream (Zone 4 material), against which was banked a rock shell of larger rocks, both upstream and downstream (Zone 3 material). The base of the Dam was approximately 250 feet wide sloping to a crest 30 feet wide. Zone 1, 2 and 3 material was tapered from bottom to top. Each zone of material was to be laid and compacted concurrently. The upstream slope of the embankment was at a ratio of 2.5:1 and the downstream slope of the embankment at a ratio of 2:1. The project also included the construction of a road over the crest of the Dam and the relocation of certain roads around the reservoir. The reservoir area had to be grubbed and cleared. The plans included a map of the damsite and borrow pit locations for the excavation or quarrying of Zones 1, 2, 3 and 4 material.

State contemplated that the damsite area would be cleared of overburden and decomposed rock and excavated to a point where “moderately weathered” rock was reached, both for the outlet conduit and the foundation for the Dam embankment. State had used its *804 preliminary topographic surveys (both aerial and on the ground) and geologic studies including cored rotary drillings, auger holes and backhoe trenches for the purpose of preparing its design studies and plans and specifications. The drawings attached to the specifications included a map designating the location of the auger holes, cored rotary drilling holes and back hoe trenchings. The request for bids advised all prospective bidders that the surveys, geologic studies and reports and core samples were available for inspection on request at the Sacramento office. State calculated that the desired type of subsurface would be reached after a certain amount of excavation and computed its estimated quantities for various items of work accordingly. However, the desired type of subsurface was not reached after excavation within State’s estimates. For example, State calculated that the project would require the removal of 33,000 yards of material in order to place the embankment of the Dam, whereas 64,724 cubic yards of material were ultimately excavated; State estimated 5,400 yards of material would have to be removed in order to build the outlet conduit whereas 7,709 cubic yards were ultimately removed; State estimated the project would require 160,000 cubic yards of excavation for roadways whereas 190,498 cubic yards were ultimately removed. State estimated that 700 cubic yards of specially compacted material would be required whereas 2,129 cubic yards were ultimately required. Because of the increase in the quantities of the various items of work, State ultimately paid Contractor $2,269,382.05 based on actual quantities multiplied by the unit bid prices and approved change orders.

The contract required Contractor to complete the project by November 15. 1966, and contained a liquidated damage clause of $500 per day for each day that completion was delayed. Contractor was notified to begin work on October 20, 1964. Under the contract, Contractor was authorized to arrange its schedule of work in any sequence which it desired in order to complete the work on schedule. Contractor completed the work on September 29, 1967. State extended the completion date from time to time for various periods for various reasons.

The contract provided that if the work to be performed was unclear, the Contractor should apply to the State Engineer for clarification, 3 and *805 the Engineer’s decision would be final.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pittsburg Unified School District v. S.J. Amoroso Construction Co.
232 Cal. App. 4th 808 (California Court of Appeal, 2014)
MCI Constructors, Inc. v. Hazen and Sawyer, PC
401 F. Supp. 2d 504 (M.D. North Carolina, 2005)
Clark v. City of Hermosa Beach
48 Cal. App. 4th 1152 (California Court of Appeal, 1996)
Budwin v. American Psychological Assn.
24 Cal. App. 4th 875 (California Court of Appeal, 1994)
Luck v. Southern Pacific Transportation Co.
218 Cal. App. 3d 1 (California Court of Appeal, 1990)
A.C. Shaw Construction, Inc. v. Washoe County
784 P.2d 9 (Nevada Supreme Court, 1989)
Yellen v. Board of Medical Quality Assurance
174 Cal. App. 3d 1040 (California Court of Appeal, 1985)
Pascal & Ludwig, Inc. v. State Ex Rel. Deparment of Water Resources
127 Cal. App. 3d 178 (California Court of Appeal, 1981)
Vale v. Union Bank
88 Cal. App. 3d 330 (California Court of Appeal, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
69 Cal. App. 3d 798, 138 Cal. Rptr. 478, 1977 Cal. App. LEXIS 1467, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zurn-engineers-v-state-of-calif-dept-water-res-calctapp-1977.