Zimmer v. Village of Willowbrook

610 N.E.2d 709, 242 Ill. App. 3d 437, 182 Ill. Dec. 840, 1993 Ill. App. LEXIS 311
CourtAppellate Court of Illinois
DecidedMarch 12, 1993
Docket2-92-0053
StatusPublished
Cited by56 cases

This text of 610 N.E.2d 709 (Zimmer v. Village of Willowbrook) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zimmer v. Village of Willowbrook, 610 N.E.2d 709, 242 Ill. App. 3d 437, 182 Ill. Dec. 840, 1993 Ill. App. LEXIS 311 (Ill. Ct. App. 1993).

Opinion

JUSTICE QUETSCH

delivered the opinion of the court:

Plaintiffs, Rodney and Phyllis Zimmer (the Zimmers) and Thaddeus and Grace Olech (the Olechs), sued defendant the Village of Willowbrook (WiUowbrook) for flooding damages allegedly resulting from Willowbrook’s installation and enlargement of certain culverts near plaintiffs’ property. Plaintiffs also sued defendant Cecil Allen (AUen) for flooding damages allegedly resulting from a pond, culverts and drains which Allen constructed on his property. Plaintiffs further sought a mandatory injunction requiring Allen to remove the pond, culverts and drains from his land. The trial court granted Willowbrook’s motion to dismiss pursuant to section 2 — 619 of the Code of Civil Procedure (111. Rev. Stat. 1991, ch. 110, par. 2 — 619), finding that plaintiffs’ cause of action was time barred by section 8 — 101 of the Local Governmental and Governmental Employees Tort Immunity Act (Tort Immunity Act) (111. Rev. Stat. 1991, ch. 85, par. 8 — 101). The trial court granted Allen’s motion for summary judgment, finding that plaintiff’s legal cause of action against Allen was time barred by section 13 — 205 of the Code of Civil Procedure (111. Rev. Stat. 1991, ch. 110, par. 13 — 205), and that laches barred plaintiffs’ claim for equitable relief. Pursuant to Supreme Court Rule 304(a), the court made an express written finding that there was no just reason to delay enforcement or appeal. (134 111. 2d R. 304(a).) Plaintiffs appeal.

The issues raised on plaintiffs’ appeal from the trial court’s granting of Willowbrook’s section 2 — 619 motion to dismiss are: (1) whether the limitations period set forth under section 8 — 101 of the Tort Immunity Act or section 13 — 214(a) of the Code of Civil Procedure (111. Rev. Stat. 1991, ch. 110, par. 13 — 214(a)) applies in the action against Willowbrook; and (2) when the applicable limitations period begins to run. The issues raised on plaintiffs’ appeal from the trial court’s granting of Allen’s motion for summary judgment are: (1) whether the limitations period set forth under section 13 — 214(a) or section 13 — 205 applies in the action against Allen; (2) when the applicable limitations period begins to run; (3) whether laches bars plaintiffs’ action seeking equitable relief from the flooding of their property; and (4) whether Allen must own property adjacent to the Olechs in order to be held liable to the Olechs for negligent trespass.

I

We first consider plaintiffs’ claim against Willowbrook. Plaintiffs filed their first complaint against Willowbrook on August 8, 1989, and their second amended complaint on January 11, 1991. Plaintiffs own properties near Bentley Avenue and 65th Street, and they allege that Willowbrook enlarged one culvert on Bentley Avenue and installed one culvert on 65th Street “to allow storm water from no less than 80 culverts and 35 sump pumps to pass water onto the Zimmer property and the property of the other plaintiffs.” Plaintiffs complained that Willowbrook’s actions unreasonably altered and increased the volume and rate of the flow of water onto plaintiffs’ land. In affidavits filed in response to Willowbrook’s section 2 — 619 motion to dismiss, the Zimmers claimed that their property was flooded in the spring of 1987, the spring of 1990, and from the beginning of 1991 until the middle of June 1991. The Olechs claimed that their property was flooded in the spring of 1987,1990, and 1991.

In its motion to dismiss, Willowbrook asserted that plaintiffs’ action was time barred by section 8 — 101. Section 8 — 101 states:

“No civil action may be commenced in any court against a local entity or any of its employees for any injury unless it is commenced within one year from the date that the injury was received or the cause of action accrued.” 111. Rev. Stat. 1991, ch. 85, par. 8 — 101.

Willowbrook argued that plaintiffs’ cause of action accrued when Willowbrook replaced the culverts in 1981. Willowbrook contended that this case was factually analogous to Firestone v. Fritz (1983), 119 Ill. App. 3d 685. In Firestone, the defendant Fritz constructed a retaining wall and placed fill on his property. Approximately 20 years later, Fritz replaced the retaining wall with a new wall. The Firestones alleged that the retaining wall and fill caused surface water to drain onto their property in unnatural quantities, destroying their garage. The court held that any cause of action accrued upon the completion of the original retaining wall. The court stated:

“Whether, in Illinois, separate causes of action accrue at each successive injury by an unnatural overflow requires a further analysis of the cause of the overflow. When a structure is placed on dominant land which unreasonably increases the flow onto the servient land, a cause of action may accrue upon the completion of the structure if it is a permanent structure which is necessarily injurious by reason of its construction. [Citation.] If, however, the structure is not apparently injurious, but may be used in a way which may or may not result in injury, the cause of action does not accrue until the use of the structure causes injury. [Citations.] The fact that flooding may be uncertain in time, duration and extent does not prevent an improvement, which displays obvious potential to cause an unnatural overflow upon completion, from constituting an immediate, permanent injury. [Citations.]” Firestone, 119 Ill. App. 3d at 687-88.

The trial court agreed that the principles set forth in Firestone governed this case and that plaintiffs’ cause of action accrued at the time the replacement culverts were installed in 1981. The court decided that the one-year limitations period of section 8 — 101 applied. Plaintiffs therefore had until 1982 to bring their cause of action. Plaintiffs did not file their action against Willowbrook until August 1989. The trial court granted Willowbrook’s motion to dismiss.

Plaintiffs argue that section 13 — 214(a) is the applicable statute of limitations. Section 13 — 214 states in relevant part:

“As used in this Section ‘person’ means any individual, any business or legal entity, or any body politic.
(a) Actions based upon tort, contract or otherwise against any person for an act or omission of such person in the design, planning, supervision, observation or management of construction, or construction of an improvement to real property shall be commenced within 4 years from the time the person bringing an action, or his or her privity, knew or should reasonably have known of such act or omission.” (111. Rev. Stat. 1991, ch. 110, par. 13 — 214(a).)

Plaintiffs contend that a question of fact exists as to when they should have reasonably known of Willowbrook’s act or omission and therefore the trial court should not have granted Willowbrook’s motion for summary judgment.

The law in Illinois is well established that where there are two statutory provisions, one general and the other specific, the particular provision prevails. (Bowes v. City of Chicago (1954), 3 Ill. 2d 175, 205.) This is especially true where the specific provision was enacted more recently. (Bowes, 3 Ill.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Giese v. Boyce
2024 IL App (3d) 240116-U (Appellate Court of Illinois, 2024)
City of Evanston v. Texaco, Inc.
19 F. Supp. 3d 817 (N.D. Illinois, 2014)
Ambrosia Land Investments, LLC v. Peabody Coal Co.
521 F.3d 778 (Seventh Circuit, 2008)
Paszkowski v. Metropolitan Water Reclamation District
820 N.E.2d 401 (Illinois Supreme Court, 2004)
Paszkowski v. METRO. WATER RECLAMATION
820 N.E.2d 401 (Illinois Supreme Court, 2004)
Hager v. Il In One Contractors, Inc. Vacated on 7/29/05
342 Ill. App. 3d 1082 (Appellate Court of Illinois, 2003)
Hager v. II in One Contractors, Inc.
797 N.E.2d 167 (Appellate Court of Illinois, 2003)
Paszkowski v. Metropolitan Water Reclamation District of Greater Chicago
338 Ill. App. 3d 781 (Appellate Court of Illinois, 2003)
Paszkowski v. METROPOLITAN WATER REC. DIST.
789 N.E.2d 342 (Appellate Court of Illinois, 2003)
Beetle v. Wal-Mart Associates, Inc.
326 Ill. App. 3d 528 (Appellate Court of Illinois, 2001)
Greb v. Forest Preserve District
Appellate Court of Illinois, 2001
Greb v. Forest Preserve Dist. of Cook Cty.
752 N.E.2d 519 (Appellate Court of Illinois, 2001)
Roark v. Macoupin Creek Drainage District
Appellate Court of Illinois, 2000
Peddinghaus v. Peddinghaus
733 N.E.2d 797 (Appellate Court of Illinois, 2000)
Tosado v. Miller
720 N.E.2d 1075 (Illinois Supreme Court, 1999)
Bank of Ravenswood v. City of Chicago
717 N.E.2d 478 (Appellate Court of Illinois, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
610 N.E.2d 709, 242 Ill. App. 3d 437, 182 Ill. Dec. 840, 1993 Ill. App. LEXIS 311, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zimmer-v-village-of-willowbrook-illappct-1993.