Zimmer v. Brandon

278 N.W. 502, 134 Neb. 311, 1938 Neb. LEXIS 43
CourtNebraska Supreme Court
DecidedMarch 18, 1938
DocketNo. 30048
StatusPublished
Cited by40 cases

This text of 278 N.W. 502 (Zimmer v. Brandon) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zimmer v. Brandon, 278 N.W. 502, 134 Neb. 311, 1938 Neb. LEXIS 43 (Neb. 1938).

Opinion

William A. Day, . District Judge.

This is an appeal from an order of the district court for Lancaster county, -Nebraska, directing the jury to return a verdict for the defendants in an action for personal injuries sustained by the plaintiff on account of the alleged negligence of the defendants.

An examination of the record reveals that this is. an action for personal injuries alleged to have been- sustained by the plaintiff, which he suffered when a wrought-iron upright pole, approximately 24 feet in height, on which he was working, toppled over, throwing him to the ground. The defendant, • the Lincoln Hatchery, the plaintiff’s employer (which is made one of the defendants by reason of having paid compensation' insurance), had employed the defendants James IT. Brandon and Arva V. 'Hartsón to do certain plumbing and .pipe-fitting work in connection with the construction of a gasoline filling station. -The defend[313]*313ant, the Lincoln Hatchery, also employed the plaintiff to assist in the general construction work • of the filling station. During the course of construction, and on the day that the plaintiff was injured, the defendants Brandon and Hartson had been instructed by the Lincoln Hatchery to join together, by means of a coupling, two pieces of. three-inch wrought-iron pipe. The shorter piece was about 3 feet in length, and the longer piece was 24 feet in length. The defendants were advised that the pipe, when so joined, was to be erected in an upright position, to which braces and brackets were to be attached, as well as lighting fixtures, and that a baked-enamel sign, weighing some 70 pounds, was to be suspended from the brackets. Braces, brackets and the enamel sign were lying beside the pipe at the time the defendant Brandon and Hartson were directed to work. The defendants were instructed to re-thread the longer piece of pipe, the threads of' which had been painted. They joined the two pieces of pipe together and then helped.the plaintiff and the electrician, who was working about the place, raise the pole so joined to an upright position, and place the end to which the short piece was attached into a hole which had already been prepared in a concrete island in the filling station drive. After the pole had been placed in position, as described, the electrician then placed a ladder against the pole so erected, and spent the remainder of the morning working at the top of the pole, wiring the electrical fixtures attached to the bracket; all of which, together with the braces, had been attached to the pole before it was erected in its upright position. During all the time that the electrician was so working, the defendants were in plain sight of him, as they were working in close proximity to him in completing the installation of the gasoline pumps.

At lunch time, while the electrician and the defendants had gone to lunch, the plaintiff, making use of the electrician’s ladder, which had been left erected against the upright pole, prepared to attach the diamond-shaped baked-enamel sign to the bracket. -He ascended the pole and at[314]*314tached to- the center of- the bracket a single block- with a rope through it, and 'returned to the ground and then attached the rope to a corner of the sign and pulled it up into position. He then had' his boy hold thé rope while he again ascended the- ladder and hooked ■ the sign on the hook nearest the pole, then reached out to attach the sign to the hook farthest from the pole, at which time the upright pole fell, hurling him to the ground, and as a result of the fall he sustained certain injuries which are permanent in their nature.

Inspection of the pole after it had fallen to the ground revealed that the long upright pole had separated' from the coupling, which was about a foot above the ground, causing the long piece to fall its entire length of 24 feet. Further examination disclosed that neither the pole nor the coupling had been broken; that the coupling-had not split or widened; that neither the threads on the long pole nor on the coupling were stripped, and from the brightness of the exposed threads, it was evident that only two or three threads of the long pole and the coupling had been engaged or screwed together. The evidence of expert witnesses on behalf of the plaintiff reveals that the standard practice in joining such pipes, as in this case, required that the pipe threads be screwed or entered into the coupling so that not less than ten full threads were engaged, and that engaging only two or three threads of the pipe into the coupling would be decidedly below all recognized and standard practice, and would not be considered satisfactory or suitable work. Testimony further reveals that had the pole been properly assembled it would have withstood the weight and force directed against it at the time of the plaintiff’s fall, and in fact it would have withstood from six to eight times the actual load applied.

The plumbing firm of Brandon and Hartson, in undertaking to assemble this upright pipe by joining the two pieces with a coupling, owed a duty to this plaintiff, and any other person rightfully on the premises, to perform the work in a proper and workmanlike manner, and with[315]*315out negligence -on their part. As plumbers they are charged with knowledge of what a proper and workmanlike assembly of the upright pole in question would be, and knowledge of the manner in which the pole was assembled was exclusively theirs, as they did the work. They were told for what purpose the pipe was intended to be used, and they knew or ought to have known, or saw or ought to have seen, the purpose for which the pole was being used, and the manner in which the sign and the electrical attachments thereto were being put in position. The electrician placed a ladder against the pole and climbed up it,-within close proximity to where they were working on other work about the premises, and to say that they did not see him using the ladder in this manner,' although there is no direct proof that they did see him, would be to draw an unwarranted .inference. The testimony reveals that no warning was given to the electrician not to place the ladder against the pole and climb thereon, or that the pole was not properly united and would not sustain his weight and that of the ladder, or that it would be dangerous to climb thereon.

The defendants Brandon and Hartson, by attempting to-assemble this upright pole, assumed a duty of assembling it- in a good and workmanlike manner, and if a reasonable and prudent person under like circumstances, after having seen the use to -vyhich the pole was to be put, could reasonably have anticipated that some person would climb the pole in order to attach the sign thereto by means of a ladder, and put his weight upon the pole, then the defendants are liable for any injury that may have been sustained by any person rightfully upon the premises, as a direct and proximate result of their negligence, and in this case their negligence consisted of the improper and unworkmanlike manner of assembling the two pieces of pipe. Thus, it is to be seen that the rule is: “Whenever the circumstances attending a situation are such that an ordinarily prudent person could reasonably apprehend that, as the natural and probable consequences of his act, an[316]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McGill Restoration v. Lion Place Condo. Assn.
309 Neb. 202 (Nebraska Supreme Court, 2021)
Topil v. Hub Hall Co.
430 N.W.2d 306 (Nebraska Supreme Court, 1988)
Schild v. Schild
125 N.W.2d 900 (Nebraska Supreme Court, 1964)
Hilzer v. Farmers Irrigation District
56 N.W.2d 457 (Nebraska Supreme Court, 1953)
Scarborough v. Aeroservice, Inc.
53 N.W.2d 902 (Nebraska Supreme Court, 1952)
Kuska v. Nichols Construction Co.
48 N.W.2d 682 (Nebraska Supreme Court, 1951)
Krepcik v. Interstate Transit Lines
40 N.W.2d 252 (Nebraska Supreme Court, 1949)
Surface v. Safeway Stores, Inc.
169 F.2d 937 (Eighth Circuit, 1948)
Frazier v. Anderson
11 N.W.2d 764 (Nebraska Supreme Court, 1943)
McNaught v. New York Life Insurance
9 N.W.2d 160 (Nebraska Supreme Court, 1943)
McClelland v. Interstate Transit Lines
6 N.W.2d 384 (Nebraska Supreme Court, 1942)
Swinford v. Finck
299 N.W. 227 (Nebraska Supreme Court, 1941)
Edwards v. York
283 N.W. 851 (Nebraska Supreme Court, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
278 N.W. 502, 134 Neb. 311, 1938 Neb. LEXIS 43, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zimmer-v-brandon-neb-1938.