Clemens v. Benzinger

211 A.D. 586, 207 N.Y.S. 539, 1925 N.Y. App. Div. LEXIS 10655
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJanuary 14, 1925
StatusPublished
Cited by10 cases

This text of 211 A.D. 586 (Clemens v. Benzinger) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clemens v. Benzinger, 211 A.D. 586, 207 N.Y.S. 539, 1925 N.Y. App. Div. LEXIS 10655 (N.Y. Ct. App. 1925).

Opinions

Hubbs, P. J.:

The death of the plaintiff’s intestate occurred during the construction of a new grand stand at the Buffalo base ball grounds. A steel column which had been hoisted into place and on which men were still working to attach beams or struts fell and in falling struck plaintiff’s intestate, another workman but not engaged in working on this column, and caused him injuries from which he died.

At the time of his death deceased was in the employ of the Bancroft-Jones Corporation which had a contract with the owners of the grounds to furnish and erect all structural steel upon the stand. The defendants Benzinger also had a contract with the owners to furnish all materials and do all work for the construction and completion of the stand except furnishing and erecting the structural steel.

Both these contracts provided that the work should be done according to drawings and specifications prepared by the defendant Osborne Engineering Corporation, which as supervising engineer had complete charge of construction.

The grand stand was built of concrete with steel columns supporting steel trusses for the roof. These columns were in the shape of H-beams, twenty feet in height with a base plate eight inches by eighteen inches in dimension in which there were holes to permit the anchor bolts, to pass through. The columns weighed [588]*588about 610 pounds. The plans provided for two anchor bolts for each column to be set by the defendants Benzinger when the concrete for the floor was poured, the bolts to be imbedded in the concrete to a depth of about thirty inches and the threaded end to project four inches above the surface of the concrete floor. The columns were placed erect in position by a derrick, being let down over the anchor bolts which then passed through the openings in the base plates intended for them. Then nuts were screwed down onto the bolts. The columns were then left standing without any bracing, being held in place by the anchor bolts. Workers would climb up the columns and the adjoining ones and by the means of blocks attached at the tops pull up the cross struts and cross beams and when raised to the proper height, fasten them in place, thus tying the columns together. The general plan furnished by the defendant Osborne Engineering Corporation to the Bancroft-Jones Corporation did not specify the type of anchor bolts, except as to the size and length. The Bancroft-Jones Corporation, however, prepared detailed plans which received the approval of the defendant Osborne Engineering Corporation and these plans showed anchor bolts with an L or lug of about two inches in length running at right angles to the main shaft of the bolt at its lower end. The Bancroft-Jones Corporation’s contract required that company to furnish the anchor bolts to the defendants Benzinger and the Benzingers’ contract required them to put these bolts in place at the time the concrete was poured for the floors. The anchor bolts actually furnished by the Bancroft-Jones Corporation were in accord with the description of them in the detailed plans. When the defendants Benzinger came to pour the concrete floor they imbedded the anchor bolts for the first and fourth of each group of four columns but omitted those for the two intervening ones. A number of weeks elapsed and the cement floor had become completely hardened before the Bancroft-Jones Corporation started erecting the columns. The superintendent of that company, then discovering the omission of the bolts, called the.situation to the attention of the superintendent of the defendant Osborne Engineering Corporation. The superintendent of the Osborne Engineering Corporation in turn directed the defendants Benzinger to drill holes in the concrete, to cut off part of the L or lug from the bolts leaving only as much of it as would pass down into the drilled holes, then to drive the bolts into the holes drilled in the cement and fill the holes with grouting around the bolts. This plan was followed and the work on this was commenced three -or four days before the ■accident. - About one-half to • five-eighths -of an inch of the lug was left upon the bolts and-the bolts were driven [589]*589in and grouted in the holes by pouring in sand and cement in equal parts. The bolts for the coliman which fell and caused the death of plaintiff’s intestate were put in place in this manner on the day before the accident. The fall of the column pulled the anchor bolts at the base of the fallen column up about six inches and bent them over. After the accident green or only partially hardened cement was apparent at the top of the holes. The cement poured into the drilled holes would not harden fully in less than three weeks although it would appear hard at the surface very quickly and like the rest of the cement floor. There was evidence from which the jury could have found that bolts furnished with an expansive end at the bottom either by a wedge in a split end or other similar device would have supported the columns without regard to the grouting as would the bolts actually used even with the lugs cut off, had the cement been allowed to harden completely.

There was also evidence to the effect that the Bancroft-Jones Corporation when erecting the column did not know that the bolts which were used in the drilled holes were not split end or expansion bolts. Under these circumstances questions of fact for the jury were presented as to the negligence of both the defendant Osborne Engineering Corporation and of the defendants Ben-zinger. As to the latter, negligence could be predicated upon the failure to use split end or expansion bolts, or if such bolts were not used upon the failure to notify the steel erector of the kind actually used. The jury might well say that the fact that the steel erector was already engaged in erecting some of the columns at the very time the bolts were being grouted in, made it obviously necessary for the defendants Benzinger in the exercise of due care to use such bolts as would enable the erector to proceed in the usual way without delay or give such notification that the steel erector might modify the method of doing the work so as to insure safety to the workmen. In the latter case guys and other supports could have been used to secure stability without reliance upon the anchor bolts for support while the grouting was still unhardened. There was proof that the mode of erecting employed by the Bancroft-Jones Corporation, with reliance upon the anchor bolts for support of the columns, was an ordinary and usual method for the prosecution of such work. i$!

The jury, to be sure, might have found that the Bancroft-Jones Corporation was negligent in relying on the strength of the anchor bolts as a support when the wet condition of the cement and the dangers therefrom ought to have been known to that company and put it on inquiry as to the condition at the lower end of the bolts. But such negligence on the part of the Bancroft-Jones [590]*590Corporation does not necessarily break the chain of legal causation, for the jury might say that such omission even though negligent was one that the defendants Benzinger, acting as reasonable men, dealing with a dangerous situation, should have foreseen. (Rosebrock v. General Electric Co., 236 N. Y. 227.) On the other hand, if the Bancroft-Jones Corporation knew the condition and acted in negligent disregard of the dangers of which it was fully advised, the chain of causation was broken. Whether that company did or did not so act was a question of fact.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mudgett v. Marshall
574 A.2d 867 (Supreme Judicial Court of Maine, 1990)
Hughes v. Nussbaumer
140 A.D.2d 988 (Appellate Division of the Supreme Court of New York, 1988)
Varga v. Parker
136 A.D.2d 932 (Appellate Division of the Supreme Court of New York, 1988)
Cutlip v. Lucky Stores, Inc.
325 A.2d 432 (Court of Special Appeals of Maryland, 1974)
Mauldin v. Sheffer
150 S.E.2d 150 (Court of Appeals of Georgia, 1966)
Cosgriff Neon Company v. Mattheus
371 P.2d 819 (Nevada Supreme Court, 1962)
Olsen v. Chase Manhattan Bank
10 A.D.2d 539 (Appellate Division of the Supreme Court of New York, 1960)
Roush v. Johnson
80 S.E.2d 857 (West Virginia Supreme Court, 1954)
Zimmer v. Brandon
278 N.W. 502 (Nebraska Supreme Court, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
211 A.D. 586, 207 N.Y.S. 539, 1925 N.Y. App. Div. LEXIS 10655, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clemens-v-benzinger-nyappdiv-1925.