Lisle v. Anderson

1916 OK 92, 159 P. 278, 61 Okla. 68, 1916 Okla. LEXIS 807
CourtSupreme Court of Oklahoma
DecidedJanuary 24, 1916
Docket4785
StatusPublished
Cited by62 cases

This text of 1916 OK 92 (Lisle v. Anderson) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lisle v. Anderson, 1916 OK 92, 159 P. 278, 61 Okla. 68, 1916 Okla. LEXIS 807 (Okla. 1916).

Opinion

Opinion by

BROWN, C.

The plaintiffs in error will be hereinafter called the defendants, and the defendants in error will be hereinafter called the plaintiff, in accord with their respective titles in the trial court.

The school district at Mountain View, Okla., on the 14th day of July. 1909, entered into two contracts, one for the construction of a school building and one for the installation of a heating and ventilating system in said building. The defendants had the contract for the construction of said building, and were to furnish all material and do all the work necessary to a complete structure in accordance with certain plans and specifications, save the installation of said heating and ventilating system. Lewis & Kitchens had the contract to install the •heating and ventilating system, in accordance with certain plans and specifications. It was required by the plans and specifications for the building- that a certain tank, which was a part of the heating and ventilating system to he installed by the said Lewis & Kitchens, was to be supported by the joists in the attic of the said building, and these joists were to be furnished and placed in said building by the defendants, and the defendants knew that the same were to be used as a support for said tank. The joists were made of pine lumber, size 2x6 and 12 or 14 feet in length, and were placed 16 inches apart from center to center, and extended north and south from one wall to another. Said joists were of size and length, and placed the distance apart, as called for by the plans and specifications. The plaintiff was superintendent for Lewis & Kitchens, and had charge of installing the heating and ventilating system. After the defendants had finished their work in the attic where this tank was to be placed, hut before they liad fully completed the building and delivered it to the owner, the plaintiff went into the attic to place the tank, and, while placing the tank upon said joists, one of the joists broke, and the plaintiff fell some 12 or 15 feet and was considerably injured. The evidence tended to show that said joists broke by reason of being windsliaken or worm-eaten. Plaintiff brought this action against defendants to recover damages for the personal injuries received by the fall, basing his petition upon the above facts, with the allegation as to negligence as follows :

« * Defendants were careless and negligent in putting in place and maintaining said weak, rotten, and defective joist, when they knew, or by the exercise of ordinary care could have known, of its condition; and when they knew the purpose said joist was intended to serve; and when they knew it would be necessary for this plaintiff and other workmen, while in and about their work, to walk over and upon and stand Tip-on this and other joists: and when they knew that plaintiff and other workmen intended to work upon and about said joists: and when they knew, or by the exercise of *70 reasonable care could have known that said joist was liable to break and injure this plaintiff or other workmen.”

The plaintiff recovered judgment against the defendants for $3,000. Defendants filed a motion for a new trial, and same was overruled and exceptions allowed, and the case is brought here to have the action of the trial court reviewed. We deem it unnecessary, at this time, to make a fuller statement of facts, as same will more fully appear, where they are necessary to be stated, in the discussion of the various assignments of error to be considered by the court.

The first point urged by the defendants calls for a determination of the trial court’s action in overruling a demurrer to the petition, a demurrer to the evidence, and refusing to direct a verdict in favor of the defendants.

The defendants claim that they owed the plaintiff no duty at the time he was injured, and that therefore there can be no liability. It is a familiar proposition that in every case involving actionable negligence, there are, of necessity, three constituent elements, to its existence: First, the existence of a duty on the part of the person complained against to protect the complainant from the injury of which he complains; second, the failure of the defendant to perform that duty; third, injury to the plaintiff resulting from such failure of the defendant. And it is only when these elements are brought together unitedly that actionable negligence is constituted. The. absence of an affirmative showing of any one of these essential elements renders the petition bad, or the evidence insufficient. Loehring v. Westlake Const. Co., 118 Mo. App. 163, 94 S. W. 747; Faurot v. Oklahoma Wholesale Gro. Co., 21 Okla. 104, 95 Pac. 463, 17 L. R. A. (N. S.) 136; Faris v. Hoberg, 134 Ind. 269, 33 U. E. 1028, 39 Am. St. Rep. 261; Texas Co. v. Collins. 42 Okla. 374, 141 Pac. 783: C., R. I. & P. R. Co. v. McIntire. 29 Okla. 797, 119 Pac. 1008; St. L. & S. F. R. Co. v. Lee, 37 Okla. 545, 132 Pac. 1072, 46 L. R. A. (N. S.) 357.

With these principles in mind we shall examine the, facts of the case. The plaintiff was not in the employ of the defendants; there was no privity of contract existing. Therefore the relation of master and servant did not obtain. But the. defendants had a contract with the school board tp erect a building complete save the heating and ventilating system; the company for whom the plaintiff was working k,ad the contract with the school board for installing the heating and ventilating system. Both contractors were carrying out the terms of their contracts at the same time; the defendants were doing the general construction work, and the plaintiff, for liis company, was installing the heating and ventilating system. The defendants, by the terms of their contract, were to furnish and place the joists in the attic, upon which the plaintiff’s company was to place the tank. It was not only necessary that the joists be furnished and installed in order that the defendants might complete the building, but it was also necessary that they be furnished and installed in order that the tank of the heating and ventilating system be supported, and the defendants knew that this was one of the purposes for which the joists were to be used. Now did they owe the plaintiff any duty in the selection of the joists? In the case of Delvin v. Smith, 89 N. Y. 470, 42 Am. Rep. 311, the defendant, who was a scaffold builder, was employed by a painter to construct a scaffold, and he defectively constructed it, and it gave way and killed a person who was in the employ of the painter, and the Supreme Court of New York held the defendant liable. In the case of Loehring v. Westlake Const. Co., supra, the court had under consideration a proposition that involved the same principle that we have in the instant, case, and the court in the course of the opinion said :

“* « * jj. ¡s now wep settled, in the law of negligence applicable to cases of this nature, that there are duties owing, the violation of which will constitute actionable negligence, in instances other than those arising out of privity of contract, and many such arising outside of the relation of master and servant, etc. The principle finds application in that class of cases where the injured party is rightfully on the premises, and is injured by the negligence of another irnder such circumstances as could reasonably have been foreseen, been contemplated, and the probable injury averted by ordinary care on the part of the person whose act caused the injury.”

The Supreme Court of Illinois, in the case of Flanagan v. Wills Bros.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Proe v. Diamond Homes
2025 OK CIV APP 18 (Court of Civil Appeals of Oklahoma, 2025)
SNOW v. TRAVELCENTERS OF AMERICA
527 P.3d 741 (Court of Civil Appeals of Oklahoma, 2022)
J.W. v. INDEPENDENT SCHOOL DISTRICT NO. 10 of DEWEY COUNTY
2021 OK CIV APP 34 (Court of Civil Appeals of Oklahoma, 2021)
McGehee v. Southwest Electronic Energy
908 F.3d 619 (Tenth Circuit, 2018)
Brewer v. Murray
2012 OK CIV APP 109 (Court of Civil Appeals of Oklahoma, 2012)
Lowery v. Echostar Satellite Corp.
2007 OK 38 (Supreme Court of Oklahoma, 2007)
Cleveland v. Dyn-A-Mite Pest Control, Inc.
2002 OK CIV APP 95 (Court of Civil Appeals of Oklahoma, 2002)
St. Paul Fire & Marine Insurance Co. v. Getty Oil Co.
782 P.2d 915 (Supreme Court of Oklahoma, 1989)
Woodis v. Oklahoma Gas & Electric Co.
1985 OK 62 (Supreme Court of Oklahoma, 1985)
Points v. Oklahoma Publishing Co.
1983 OK 62 (Supreme Court of Oklahoma, 1983)
Keel v. Titan Construction Corp.
1981 OK 148 (Supreme Court of Oklahoma, 1981)
Rose v. Sapulpa Rural Water Co.
1981 OK 85 (Supreme Court of Oklahoma, 1981)
Peter Kiewit Sons' Co. v. Grimme
1970 OK 75 (Supreme Court of Oklahoma, 1970)
Nye v. Cox
1968 OK 50 (Supreme Court of Oklahoma, 1968)
Foster v. Harding
1967 OK 46 (Supreme Court of Oklahoma, 1967)
Henryetta Construction Co. v. Harris
408 P.2d 522 (Supreme Court of Oklahoma, 1965)
J & K CONSTRUCTION COMPANY v. Molton
390 P.2d 68 (Supreme Court of Colorado, 1964)
Colarossi v. Anderson Concrete Corp.
175 Ohio St. (N.S.) 321 (Ohio Supreme Court, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
1916 OK 92, 159 P. 278, 61 Okla. 68, 1916 Okla. LEXIS 807, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lisle-v-anderson-okla-1916.