Zap's Electrical, LLC v. Monarch Construction, LLC

CourtDistrict Court, D. Nevada
DecidedApril 18, 2024
Docket3:19-cv-00603
StatusUnknown

This text of Zap's Electrical, LLC v. Monarch Construction, LLC (Zap's Electrical, LLC v. Monarch Construction, LLC) is published on Counsel Stack Legal Research, covering District Court, D. Nevada primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zap's Electrical, LLC v. Monarch Construction, LLC, (D. Nev. 2024).

Opinion

1 UNITED STATES DISTRICT COURT 2 DISTRICT OF NEVADA 3 * * *

4 ZAP’S ELECTRICAL, LLC, Case No. 3:19-CV-00603-CLB

5 Plaintiff, ORDER GRANTING PLAINTIFF’S MOTION FOR ATTORNEY’S FEES AND 6 v. MOTION TO AMEND JUDGMENT TO INCLUDE INTEREST 7 MONARCH CONSTRUCTION, LLC, [ECF Nos. 148, 153] 8 Defendant.

9 10 This case involves an action filed by Plaintiff Zap’s Electrical, LLC (“Zap’s”) against 11 Defendant Monarch Construction (“Monarch”). Currently pending before the Court are 12 two motions filed by Zap’s. First, Zap’s filed a motion for attorney’s fees, (ECF No. 148.) 13 Monarch responded, (ECF No. 149), and Zap’s replied. (ECF No. 152.) Second, Zap’s 14 filed a motion to amend the judgment to include interest. (ECF No. 153.) Monarch 15 responded, (ECF No. 154), and Zap’s replied. (ECF No. 155.) For the reasons stated 16 below, the Court grants Zap’s motion for attorney’s fees and motion to amend the 17 judgment to include interest. 18 I. FACTUAL BACKGROUND1 19 This dispute stems from alleged contracts between Zap’s and Monarch related to 20 construction work which occurred when Zap’s was not a licensed contractor in the state 21 of Nevada. Initially, Zap’s contracted with Monarch to perform electrical work on projects 22 at the Circus Circus Hotel and Casino and El Dorado Hotel and Casino for general 23 contractor Digney York. Shortly after beginning the work, the Nevada contractor’s board 24 shut down the construction and fined the parties because Zap’s was not a licensed 25 contractor. Following the shutdown by the contractor’s board, construction restarted and 26 was completed. Ultimately, the parties disagreed over how the money earned from the El 27 1 The background facts provided are based on facts stipulated to by the parties and 1 Dorado project should be distributed. 2 In its complaint, Zap’s alleged three claims for relief: (1) breach of contract; (2) 3 promissory estoppel; and (3) unjust enrichment. (ECF No. 22.) As to the first claim, Zap’s 4 alleged Monarch breached a contract between the parties by refusing to pay Zap’s the 5 full amount upon completion of the construction project. (Id. at 3.) Next, Zap’s alleged it 6 is entitled to recoup the reasonable amount of benefits obtained by Monarch based on 7 promissory estoppel because of Zap’s detrimental reliance on Monarch’s promise to pay 8 for work completed. (Id. at 4.) Finally, Zap’s alleged Monarch inequitably retained the 9 payment for completing the project and Zap’s is entitled to recoup the reasonable amount 10 of benefits obtained by Monarch based on the doctrine of unjust enrichment. 11 Thereafter, Monarch filed its answer and asserted counterclaims against Zap’s for: 12 (1) breach of contract; (2) unjust enrichment; (3) promissory estoppel; and (4) conversion. 13 (ECF Nos. 8, 15.) Monarch’s first counterclaim alleged Zap’s breached a contract 14 between the parties by failing to pay Monarch after Monarch performed under the 15 contract. (Id. at 4-5.) Monarch’s second counterclaim alleged Zap’s received benefits 16 which were due to Monarch and which Monarch is entitled to recover to prevent unjust 17 enrichment of Zap’s. (Id. at 5-6.) Next, Monarch alleged it was entitled to a portion of the 18 proceeds from the construction work in connection with the work performed by both 19 parties under the theory of promissory estoppel. (Id. at 6-7.) Finally, Monarch alleged 20 Zap’s was not entitled to any of the proceeds from the construction work and therefore, 21 by keeping the funds, converted the proceeds to the exclusion of Monarch. (Id.) 22 On September 9, 2021, the district court entered an order ruling on the parties’ 23 competing motions for summary judgment and Zap’s motion to strike. (ECF No. 68.) In 24 the order, the district court granted Zap’s motion to strike Monarch’s motion for summary 25 judgment as it was filed “nearly three weeks after the deadline.” (Id.) As to the merits of 26 Zap’s motion for summary judgment, the district court determined there was genuine 27 issue of material fact existed with respect to whether a contract existed. (Id. at 8-9.) The 1 contract was illegal pursuant to NRS 624.320 because Zap’s was not a licensed 2 contractor in the state of Nevada at the time the agreement was formed. (Id.) Although 3 Zap’s conceded the contract between the parties was illegal, Zap’s argued two exceptions 4 applied through which Zap’s could still recover under the terms of the contract: substantial 5 compliance and the Magill test. (Id.) The district court determined that neither exception 6 applied and therefore denied Zap’s motion for summary judgment. (Id.) 7 After the case was set for trial, Monarch filed a document entitled a “Memorandum” 8 in support of its statement of the case. (ECF No. 110.) In this memorandum, Monarch 9 raised – for the first time – the issue of whether the district court’s order related to 10 Monarch’s motion for summary judgment was binding as law of the case and precluded 11 Zap’s claims from being presented to the jury. (Id.) Accordingly, the Court ordered the 12 parties to submit supplemental briefing on the issues raised by Monarch’s memorandum 13 in order to determine what, if any, claims could proceed to trial. (ECF No. 119.) 14 Specifically, the Court ordered to the parties to brief: 15 (1) Whether the district court’s order, (ECF No. 68), is law of the case, and, if so, whether the factual findings in that order are binding; and 16 (2) Whether, despite those decisions appearing to be legal decisions, such 17 decisions can be presented to the jury. 18 (Id.) At the hearing where the Court ordered this briefing, Monarch argued its counterclaim 19 for breach of contract was based on a separate, second contract between the parties. 20 (Id.) 21 After full briefing, the Court first found that because the district court’s order, (ECF 22 No. 68), was a denial of summary judgment for the plaintiff, the order did not bind the 23 Court as the law of the case. (ECF No. 123 at 7 (citing Fred Segal, LLC v. CormackHill, 24 LP, 821 F. Appx 783, 786 (9th Cir. 2020).) Next, the Court determined that there were 25 questions of fact for a jury and therefore Zap’s claims should proceed to trial. (Id. at 7-8.) 26 Regardless of whether Zap’s claims were precluded by the district court’s order, (ECF 27 No. 68), the Court specifically noted that because Monarch affirmatively represented that 1 its counterclaims are based on a separate contract, those claims would also have to 2 proceed to trial. (Id. at 8 (citing ECF No. 119).) The Court therefore concluded that as a 3 matter of judicial economy, proceeding as to both Zap’s claims and Monarch’s 4 counterclaims in the same trial was prudent because a trial on any alleged separate 5 contract would involve the same parties and much, if not all, of the same evidence and 6 testimony which would be used to try Zap’s claims. (Id.) 7 The jury trial began on February 12, 2024. (ECF No. 138.) After Monarch rested 8 its case but before the case was submitted to the jury, Zap’s made a Rule 50 motion on 9 all of Monarch’s counterclaims. (ECF No. 150 at 147.) The Court granted Zap’s motion 10 as to Monarch’s counterclaims of breach of contract and promissory estoppel based on 11 Monarch’s concession that these claims should be dismissed. (Id. at 151, 158.) At the 12 conclusion of the trial, on February 14, 2024, the jury returned a verdict in favor of Zap’s. 13 (ECF No. 145.) The jury found in favor of Zap’s. Specifically, the jury found that although 14 Monarch did not breach its contract with Zap’s, Zap’s could recover under the theories of 15 unjust enrichment and promissory estoppel. (Id.) Moreover, the jury rejected each of 16 Monarch’s counterclaims for unjust enrichment and conversion. (Id.) 17 On February 27, 2024, Zap’s filed a motion for attorney’s fees. (ECF No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hensley v. Eckerhart
461 U.S. 424 (Supreme Court, 1983)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
City of Burlington v. Dague
505 U.S. 557 (Supreme Court, 1992)
Martin Gonzalez, Sr. v. City of Maywood
729 F.3d 1196 (Ninth Circuit, 2013)
Semenza v. Caughlin Crafted Homes
901 P.2d 684 (Nevada Supreme Court, 1995)
Chowdhry v. NLVH, INC.
851 P.2d 459 (Nevada Supreme Court, 1993)
Johnson v. Johnson
851 P.2d 4 (Wyoming Supreme Court, 1993)
Bergmann v. Boyce
856 P.2d 560 (Nevada Supreme Court, 1993)
Diamond Full Fashioned Hosiery Co. v. Leader
20 F. Supp. 467 (E.D. Pennsylvania, 1937)
First Interstate Bank of Nevada v. Green
694 P.2d 496 (Nevada Supreme Court, 1985)
Camacho v. Bridgeport Financial, Inc.
523 F.3d 973 (Ninth Circuit, 2008)
Women's Federal S & L Ass'n v. Nevada Nat. Bank
623 F. Supp. 469 (D. Nevada, 1985)
Haley v. DIST. CT.
273 P.3d 855 (Nevada Supreme Court, 2012)
Valley Electric Ass'n v. Overfield
106 P.3d 1198 (Nevada Supreme Court, 2005)
Rivero v. Rivero
216 P.3d 213 (Nevada Supreme Court, 2009)
Brunzell v. Golden Gate National Bank
455 P.2d 31 (Nevada Supreme Court, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
Zap's Electrical, LLC v. Monarch Construction, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zaps-electrical-llc-v-monarch-construction-llc-nvd-2024.