Zap's Electrical, LLC v. Monarch Construction, LLC

District Court, D. Nevada·Decided October 20, 2023·No. 3:19-cv-00603·Unknown

Opinion

1 UNITED STATES DISTRICT COURT 2 DISTRICT OF NEVADA 3 * * *

4 ZAP’S ELECTRICAL, LLC, Case No. 3:19-CV-00603-CLB

5 Plaintiff, ORDER RE: COURT’S AUGUST 9, 2023 ORDER 6 v. [ECF No. 119] 7 MONARCH CONSTRUCTION,

8 Defendant.

9 10 This case involves an action filed by Plaintiff Zap’s Electrical, LLC (“Zap’s”) against 11 Defendant Monarch Construction (“Monarch”) and counterclaims asserted by Monarch 12 against Zap’s. Currently pending before the Court is briefing regarding whether a previous 13 order entered by the district court is binding as law of the case and whether there were 14 questions of fact for the jury. (ECF No. 119). For the reasons stated below, the Court finds 15 that the case should proceed to trial on Zap’s claims and Monarch’s counterclaims. 16 I. PROCEDURAL HISTORY 17 On July 31, 2019, Zap’s filed the instant lawsuit against Monarch. (ECF No. 1.) 18 Zap’s claims arise from an alleged contract between Zap’s and Monarch related to 19 construction work which occurred when Zap’s was not a licensed contractor in the state 20 of Nevada. (Id.) After the case was transferred to the unofficial northern division of the 21 District of Nevada, District Court Judge Robert C. Jones was assigned as the presiding 22 judge with the undersigned magistrate judge assigned to oversee pretrial matters. (ECF 23 No. 22.) In its complaint, Zap’s alleged three claims for relief: (1) breach of contract; (2) 24 promissory estoppel; and (3) unjust enrichment. (Id. at 3-5.) As to the first claim, Zap’s 25 alleges Monarch breached a contract between the parties by refusing to pay Zap’s the 26 full amount upon completion of the construction project. (Id. at 3.) Next, Zap’s alleges it 27 is entitled to recoup the reasonable amount of benefits obtained by Monarch based on 1 for work completed. (Id. at 4.) Finally, Zap’s alleges Monarch inequitably retained the 2 payment for completing the project and Zap’s is entitled to recoup the reasonable amount 3 of benefits obtained by Monarch based on the doctrine of unjust enrichment. 4 On August 26, 2019, Monarch filed their answer and asserted counterclaims 5 against Zap’s alleging: (1) breach of contract; (2) unjust enrichment; (3) promissory 6 estoppel; and (4) conversion. (ECF Nos. 8, 15.) Monarch’s first counterclaim alleges 7 Zap’s breached a contract between the parties by failing to pay Monarch after Monarch 8 performed under the contract. (Id. at 4-5.) Monarch’s second counterclaim alleges Zap’s 9 received benefits which were due to Monarch and which Monarch is entitled to recover to 10 prevent Zap’s unjust enrichment of Zap’s. (Id. at 5-6.) Next, Monarch alleges promissory 11 estoppel entitles Monarch to a portion of the proceeds from the construction work in 12 connection with the work performed by both parties. (Id. at 6-7.) Finally, Monarch alleges 13 Zap’s was not entitled to any of the proceeds from the construction work and therefore, 14 by keeping the funds, converted the proceeds to the exclusion of Monarch. (Id.) 15 In October of 2019, the Court entered an initial scheduling order and discovery 16 plan. (ECF No. 24.) Following numerous amendments to the scheduling order, the 17 deadline to file dispositive motions was set for December 9, 2020. (ECF No. 58.) 18 Accordingly, Zap’s filed its motion for summary judgment on December 9, 2020. (ECF 19 No. 59.) On December 30, 2020, Monarch filed its motion for summary judgment. (ECF 20 No. 63.) In response to Monarch’s motion, Zap’s filed a motion to strike Monarch’s motion 21 as untimely. (ECF No. 65.) 22 On September 9, 2021, the district court entered an order ruling on the parties’ 23 competing motions for summary judgment and Zap’s motion to strike. (ECF No. 68.) In 24 the order, the district court granted Zap’s motion to strike Monarch’s motion for summary 25 judgment as it was filed “nearly three weeks after the deadline.” (Id.) The district court 26 then turned to the merits of Zap’s motion for summary judgment. First, the district court 27 considered whether Zap’s had shown that there “was–and still is–an enforceable 1 sufficient to show that a reasonable juror would find the parties agreed to the terms of the 2 alleged agreement and therefore denied summary judgment after concluding a genuine 3 issue of material fact existed with respect to this issue. (Id. at 8-9.) 4 Following this determination, the district court considered Monarch’s argument that 5 even if a contract did exist, the contract was illegal pursuant to NRS 624.320 because 6 Zap’s was not a licensed contractor in the state of Nevada at the time the agreement was 7 formed. (Id.) Although Zap’s conceded the contract between the parties was illegal, Zap’s 8 argued two exceptions applied through which Zap’s could still recover under the terms of 9 the contract: substantial compliance and the Magill test. (Id.) 10 The district court addressed these exceptions in turn. With respect to the 11 substantial compliance exception, to fit within this exception, the party must have 12 “substantially complied” with Nevada’s contractor licensing statutes. Eagle Rock 13 Contracting, LLC v. National Security Technologies, LLC, No. 2:14-cv-01278-GMN-NJK, 14 2017 WL 372977, at *3 (D. Nev. Jan. 25, 2017). The district court concluded that Zap’s 15 had failed to substantially comply with the statute. The district court noted that, in contrast 16 to other cases where this exception applied, Zap’s did not have any licenses in Nevada, 17 did not own the constructed properties, and did not function as a passive financier. (ECF 18 No. 68 at 10.) In sum, the district court found “no case applying Nevada law has extended 19 the substantial compliance doctrine as far as [Zap’s sought] to stretch it.” (Id.) 20 Next, the district court considered whether Zap’s could enforce the alleged contract 21 under the Magill test. In Magill v. Lewis, the Nevada Supreme Court found that an illegal 22 contract could still be enforceable where the following four-factor test weighs in favor of 23 such enforcement: 24 [1] the public cannot be protected because the transaction has been completed, [2] where no serious moral turpitude is involved, [3] where the 25 defendant is the one guilty of the greatest moral fault and [4] where to apply 26 the rule will be to permit the defendant to be unjustly enriched at the expense of the plaintiff, the rule should not be applied. 27 333 P.2d 717 (Nev. 1958). In reviewing the factors, the district court held that “the general 1 rule–that an illegal contract is unenforceable–should not be altered here.” (ECF No. 68 at 2 11.) In explaining why the exception would not apply, the district court stated its 3 conclusion as to each factor but did not elaborate on the reasoning for its conclusions 4 save for a brief discussion of the fourth factor. (Id.) 5 Finally, the district court noted neither the substantial compliance nor the Magill 6 exception can apply where the violations of the licensing statute where “blatant, 7 substantial, and repeated.” (Id. (citing Loomis v. Lange Fin. Corp., 865 P.2d 1161, 1165 8 (Nev. 1993).) The district court found that “while [Zap’s] may have innocently began 9 working on the Projects thinking that its application for license and partnering with 10 licensed contractors was sufficient, that cannot be true after [the Nevada State 11 Contractor’s Board (“NSCB”)] informed them of violations” and Zap’s continued to work 12 on the project. (Id.) Therefore, the district court concluded neither exception could apply 13 to work performed after NSCB’s notice and denied Zap’s motion for summary judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Zap's Electrical, LLC v. Monarch Construction, LLC, (D. Nev. 2023).

Zap's Electrical, LLC v. Monarch Construction, LLC (Zap's Electrical, LLC v. Monarch Construction, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Russell Earl Shouse v. Karl H. Ljunggren
792 F.2d 902 (Ninth Circuit, 1986)
Loomis v. Lange Financial Corp.
865 P.2d 1161 (Nevada Supreme Court, 1993)
Magill v. Lewis
333 P.2d 717 (Nevada Supreme Court, 1958)
Leasepartners Corp. v. Robert L. Brooks Trust
942 P.2d 182 (Nevada Supreme Court, 1997)
Whitemaine v. Aniskovich
183 P.3d 137 (Nevada Supreme Court, 2008)
Unionamerica Mortgage & Equity Trust v. McDonald
626 P.2d 1272 (Nevada Supreme Court, 1981)
Cion Peralta v. T. Dillard
744 F.3d 1076 (Ninth Circuit, 2014)