Zahn v. Allen

CourtCourt of Appeals of South Carolina
DecidedApril 19, 2004
Docket2004-UP-261
StatusUnpublished

This text of Zahn v. Allen (Zahn v. Allen) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zahn v. Allen, (S.C. Ct. App. 2004).

Opinion

THIS OPINION HAS NO PRECEDENTIAL VALUE.  IT SHOULD NOT BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 239(d)(2), SCACR.

THE STATE OF SOUTH CAROLINA
In The Court of Appeals

Paul Zahn, individually and d/b/a Zahn Construction Company,        Respondent,

v.

Sadie Allen and Abbeville Savings & Loan,        Defendants,

Of Whom Sadie Allen is the        Appellant.


Appeal From Abbeville County
Joseph J. Watson, Circuit Court Judge


Unpublished Opinion No. 2004-UP-261
Submitted March 8, 2004 – Filed April 19, 2004


AFFIRMED


Hemphill P. Pride II, of Columbia, for Appellant. 

Edward S. McCallum, III, of Greenwood, and James B. Richardson, Jr., of Columbia, for Respondent.

PER CURIAM:  In this action to foreclose a mechanic’s lien, the trial court awarded homebuilder Paul Zahn a $43,848.73 judgment against homeowner Sadie Allen.  Allen appeals, arguing the trial court erred in:  (1) finding the mechanic’s lien was timely filed; (2) ruling she was liable under the contract; and (3) awarding attorney’s fees to Zahn.  We affirm. [1]

BACKGROUND

The parties contracted for Zahn to build Allen a house.  The house was based on a design the parties modified to accommodate Allen’s needs including handicapped features for her mother.  It is undisputed Zahn made mistakes in constructing the home.  He also failed to deliver it in a timely fashion.  After Zahn informed Allen the home was complete and demanded payment, Allen refused to pay the remainder due under the contract until the home could be independently inspected.  In response to a complaint filed by Allen, an inspector with the South Carolina Department of Labor, Licensing, and Regulation inspected the home, finding a number of construction deficiencies.  Zahn repaired the items noted in the report and approximately a month later filed a mechanic’s lien and this action.  Allen answered, asserting several affirmative defenses and a breach of contract counterclaim.  Zahn completed additional repairs after the filing of pleadings.  However, problems continued with the home. 

Following a bench trial, the trial court issued an order finding Zahn timely filed the mechanic’s lien and awarding him $43,848.73.  This amount reflected two setoffs to Allen, one for the interest she lost during the time between scheduled delivery and actual completion and another for repair costs to correct an error in the foyer’s construction.  The court also held Zahn was entitled to legal fees and costs it later determined to be $14,610.08. 

DISCUSSION

I.     Filing of the Mechanic’s Lien

Allen argues the trial court erred in concluding Zahn timely filed his mechanic’s lien.  We disagree.

“An action to foreclose a mechanic’s lien is a law case in South Carolina.”  Keeney’s Metal Roofing, Inc. v. Palmieri, 345 S.C. 550, 553, 548 S.E.2d 900, 901 (Ct. App. 2001).  In an action at law tried without a jury, the appellate court’s standard of review extends only to the correction of errors of law.  Barnacle Broad. v. Baker Broad., 343 S.C. 140, 146, 538 S.E.2d 672, 675 (Ct. App. 2000), cert. dismissed, 348 S.C. 11, 558 S.E.2d 516 (2002).  Therefore, the trial court’s factual findings will not be disturbed on appeal unless the record discloses there is no evidence reasonably supporting the court’s findings.  Id.

Mechanics’ liens [2] serve to secure payment for a “person to whom a debt is due for labor performed or furnished or for materials furnished and actually used in the erection . . . of a building or structure . . . by virtue of an agreement with, or by consent of, the owner of the building or structure.”  S.C. Code Ann. § 29-5-10(a) (Supp. 2003).

For a person to be entitled to enforce a mechanic’s lien, he must file within ninety days of furnishing labor or materials for the building or structure.  S.C. Code Ann. § 29-5-90 (providing a mechanic’s lien “shall be dissolved” unless the person holding the lien serves and files the lien within ninety days of providing labor or materials); see also Preferred Sav. & Loan Ass’n, Inc. v. Royal Garden Resort, Inc., 301 S.C. 1, 4, 389 S.E.2d 853, 854 (1990) (stating when a person files a mechanic’s lien, he is essentially asserting work has been performed in the ninety days prior to filing for which he is entitled to a lien). 

The court found for Zahn’s lien to be timely, he must have performed work sometime between March 28 and June 26, 2000, the date he filed the lien.  Zahn sent Allen a letter on May 31, 2000 stating the problems outlined in LLR’s April 6 report had been remedied.  Based on this letter and the testimony adduced at trial, the court found Zahn performed work within the ninety-day period.  Thus the trial court properly found Zahn timely filed his lien.

Allen also argues S.C. Code Ann. § 29-5-250 (1991) precludes Zahn from asserting a mechanic’s lien under the facts of this case.  However, because Allen raises this issue for the first time on appeal, it is not preserved.  See Wilder Corp. v. Wilke, 330 S.C. 71, 76, 497 S.E.2d 731, 733 (1998) (finding an issue must be raised to and ruled on by the trial court to be preserved for appeal).

II.     Enforceability of Mechanic’s Lien

Allen also contends the trial court erred in finding an enforceable mechanic’s lien because it should have found Allen was not liable under the contract.  The contract provides for final payment to be made “at the time of completion.”  Allen asserts because numerous problems arose during construction, the house was never completed, and thus, the final payment never became due.  We disagree. 

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blumberg v. Nealco, Inc.
427 S.E.2d 659 (Supreme Court of South Carolina, 1993)
Jackson v. Speed
486 S.E.2d 750 (Supreme Court of South Carolina, 1997)
Brasington Tile Co., Inc. v. Worley
491 S.E.2d 244 (Supreme Court of South Carolina, 1997)
UTILITIES CONST. CO., INC. v. Wilson
468 S.E.2d 1 (Court of Appeals of South Carolina, 1996)
PREFERRED SAVINGS & LOAN ASSOCIATION, INC. v. Royal Garden Resort, Inc.
389 S.E.2d 853 (Supreme Court of South Carolina, 1990)
Wilder Corp. v. Wilke
497 S.E.2d 731 (Supreme Court of South Carolina, 1998)
Keeney's Metal Roofing, Inc. v. Palmieri
548 S.E.2d 900 (Court of Appeals of South Carolina, 2001)
Barnacle Broadcasting, Inc. v. Baker Broadcasting, Inc.
538 S.E.2d 672 (Court of Appeals of South Carolina, 2000)
Barnacle Broadcasting, Inc. v. Baker Broadcasting, Inc.
558 S.E.2d 516 (Supreme Court of South Carolina, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
Zahn v. Allen, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zahn-v-allen-scctapp-2004.