Brasington Tile Co., Inc. v. Worley

491 S.E.2d 244, 327 S.C. 280, 1997 S.C. LEXIS 174
CourtSupreme Court of South Carolina
DecidedSeptember 2, 1997
Docket24683
StatusPublished
Cited by6 cases

This text of 491 S.E.2d 244 (Brasington Tile Co., Inc. v. Worley) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brasington Tile Co., Inc. v. Worley, 491 S.E.2d 244, 327 S.C. 280, 1997 S.C. LEXIS 174 (S.C. 1997).

Opinion

TOAL, Justice:

In this action to recover on a mechanic’s lien, Appellant Brasington Tile Company (“Contractor”) appeals the special referee’s determination that Respondent Worley (“Owner”) was the prevailing party in the litigation and was, therefore, entitled to attorneys’ fees. We affirm.

Factual/Procedural Background

Owner is the proprietor of the O.D. Cafe, a restaurant and bar in North Myrtle Beach. When the restaurant needed renovations, Owner hired Contractor to perform some of the necessary work. In order to speed up the work, Owner allowed Contractor’s employees to stay at a motel owned by Owner, and Owner gave Contractor a substantial discount on the room rates.

*283 When Contractor’s participation in the renovation project ceased, Owner and Contractor disagreed about the amount Owner owed Contractor. On July 18, 1991, Contractor filed a mechanic’s lien against the property in the amount of $34,-200.46. Three months later, on October 18, 1991, Contractor sued Owner to foreclose the mechanic’s lien. 1 Owner’s answer contained a counterclaim as well as a claim for setoffs and credits. Owner requested that any amounts he owed Contractor be offset by the amount Contractor owed him for the motel room charges for Contractor’s employees.

A special referee heard the action and ruled Contractor was entitled to recover under his mechanic’s lien. Initially, the referee awarded Contractor $14,846.81, having determined Contractor was entitled to $18,376.06 2 less $3,529.25 in offsets. Of the offset amount, $2,595.50 represented the value of the motel accommodations. The special referee also awarded Contractor attorneys’ fees and costs of $14,846.81 plus prejudgment interest at 8.75%.

Owner filed a motion under Rule 59(e), SCRCP, asking the special referee to reconsider, among other things, the determination that Contractor was entitled to attorneys’ fees and costs. On February 15, 1996, the special referee modified his original order, finding Owner the prevailing party as defined in S.C.Code Ann. § 29-5-10 (1991) and awarding Owner attorneys’ fees and costs in the amount of $14,846.81. 3

Contractor appeals on three grounds:

■ 1. There was not sufficient mutuality of interests for the claim regarding motel accommodations to be treated as a setoff;

*284 2. In determining the prevailing party in this action, the special referee should have regarded the verdict as the amount to which Contractor was entitled before the offsets were considered; and

3. In determining the prevailing party under section 29-5-10, the special referee should have considered Owner’s counterclaim a “negative” offer of settlement.

Law/Analysis

A. Propriety of Setoff

Contractor first argues that Owner’s claim for the cost of motel accommodations should not be considered a setoff or a counterclaim and should not, therefore, have been brought in this action. We disagree.

The Record does not reflect that Contractor ever raised to the special referee the propriety of the setoff itself. In its Reply to Owner’s original Answer, Contractor simply stated that the allegations relating to the setoff “require[d] no response.” The Record contains no objection by Contractor to Owner’s introducing evidence concerning the value of the motel accommodations. If Contractor considered the motel accommodations an improper subject for setoff, it should have raised the issue to the special referee. As it failed to do so, the issue is not properly before this Court. See, e.g., Smith v. Phillips, 318 S.C. 453, 458 S.E.2d 427 (1995) (appellate court may not reach issue not raised to or ruled upon by trial court).

On the merits of this issue, we find there is sufficient mutuality for the claim relating to motel accommodations to be asserted as a setoff. Courts “generally do not, with respect to a setoff, require the same strict degree of mutuality as is required in a counterclaim.” Kirkland, Inc. v. Providence Washington Ins. Co., 264 S.C. 573, 580, 216 S.E.2d 518, 521 (1975). Here, there is certainly mutuality of parties. Moreover, although the provision of the motel accommodations may not have been directly encompassed within the terms of the parties’ agreement, the accommodations were provided in order to facilitate Contractor’s performance of the agreement. Also, as best we can discern, the agreement between the parties concerning construction was not limited to the original *285 contract, but encompassed change orders and similar requests. The motel accommodations could certainly be classified as part and parcel of the parties’ entire agreement concerning the renovations at the O.D. Cafe. Under these circumstances, the motel accommodations were an appropriate subject for setoff.

B. Attorneys’ Fees to Prevailing Party

Contractor next argues that the special referee erred in determining Owner was the prevailing party under section 29-5-10 for purposes of an award of attorneys’ fees. We disagree.

S.C.Code Ann. § 29-5-10(a) provides that the prevailing party to an action to foreclose a mechanic’s lien shall be awarded attorneys’ fees and costs up to the amount of the actual lien award. Subsection (b) of the statute specifies the method for determining the prevailing party to the litigation:

Not less than fifteen days before the first term of court at which the trial is set, either party may file and serve on the other party an offer of settlement, and within ten days thereafter the party served may respond by filing and serving his offer of settlement. The offer shall state that it is made under this section and specify the amount, exclusive of interest and costs, which the party serving the offer is willing to agree constitutes a settlement of the lien....
If a written offer of settlement is made by both parties, the party whose offer is closer to the verdict reached is considered the prevailing party in the action. If the difference between both offers and the verdict is equal, neither party is considered to be the prevailing party for purposes of determining the award of costs and attorney’s fees.
If the plaintiff makes no written offer of settlement, the amount prayed for in his complaint is considered to be his final offer of settlement for purposes of this section.
If the defendant makes no written offer of settlement, his offer of settlement is considered to be zero.

(emphasis added).

Contractor first argues that the word “verdict,” as used in the statute, should be construed to mean only the amount *286

Free access — add to your briefcase to read the full text and ask questions with AI

Related

EPS Advisors, LLC v. Fredman
Court of Appeals of South Carolina, 2021
JRS Builders, Inc. v. Neunsinger
614 S.E.2d 629 (Supreme Court of South Carolina, 2005)
Zahn v. Allen
Court of Appeals of South Carolina, 2004
Keystone Elevator Co. v. Johnson & Wales University
850 A.2d 912 (Supreme Court of Rhode Island, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
491 S.E.2d 244, 327 S.C. 280, 1997 S.C. LEXIS 174, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brasington-tile-co-inc-v-worley-sc-1997.