York v. York Railways Co.

78 A. 128, 229 Pa. 236, 1910 Pa. LEXIS 578
CourtSupreme Court of Pennsylvania
DecidedJuly 1, 1910
DocketAppeal, No. 144
StatusPublished
Cited by16 cases

This text of 78 A. 128 (York v. York Railways Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
York v. York Railways Co., 78 A. 128, 229 Pa. 236, 1910 Pa. LEXIS 578 (Pa. 1910).

Opinion

Opinion by

Mr. Justice Moschzisker,

This action was brought by the city of York against the York Railways Company, successor to the Colonial Street Railway Company, and the Fidelity & Deposit Company of Maryland, to recover $25,000 liquidated damages, under a contract evidenced by an ordinance of councils granting a franchise to construct and operate a railway upon certain of the highways and bridges of the city of York, an acceptance of the ordinance, and a bond given under its provisions with the last-named defendant as surety. The court below instructed a verdict in favor of the plaintiff for the full amount of the bond with interest, and the defendants have appealed.

The ordinance was passed finally by councils March 2, 1906, approved by the mayor March 20, 1906, accepted by the railway company March 27, 1906, the bond given and accepted on March 30, 1906, and work commenced April 1, 1906. The breach relied upon was the failure to complete and put the whole line in actual operation within three years from the last date as required by the terms of the ordinance.

The only sections of the ordinance essential to our present consideration are the ninth and thirteenth, and the material parts of these are: "Sec. 9. The company in good faith shall commence the construction of its line prior to April 1, 1906, and shall complete the construction of its line upon all the streets and between all the points above mentioned and put same in actual operation within three years from said date and on its failure so to commence, or having commenced, on its failure to complete its line, its right to occupy the portion of any street or streets on which its line shall not have been completed at the time fixed for the completion of the same, shall terminate and end, except as hereinafter provided, unless the completion of the construction of its said line of railway at the existing City grades for said streets, avenues, bridges or highways at the time of the construction shall be delayed or rendered impossible by proceedings [240]*240either at law or in equity to invalidate its charter or to prevent the construction or completion of its line of railway upon the streets, avenues, bridges and highways, or a’ny of them, mentioned in section 1 hereof . . . and “Sec. 13. The Colonial Street Railway Company, . . . . shall .... accept all the obligations, conditions and duties by this ordinance imposed upon said company .... the certificate (of acceptance) and this ordinance to constitute a contract, between the said Colonial Street Railway Company and the City of York. Said Company shall also at the same time of filing said certificate furnish a bond in the sum of Twenty-five thousand dollars .... conditioned to faithfully comply with all the provisions of this ordinance and to indemnify the City of York of and from all loss and damage accruing to it in any way by reason of the passage of this ordinance, .... the said Company, its successors and assigns, also agrees that the said bond shall become forfeited to and collectible by the City of York as assessed and liquidated damages due and owing said city in the event of the failure of said Company, its successors and assigns, to complete and operate its line of railway as set forth in section 9 hereof; for which bond, after the Company shall have completed and begun to operate its railway line, shall be substituted the bond of the company in the sum of $5,000. . . .”

The condition of the bond is: “If the above bounden, the Colonial Street Railway Company, shall faithfully comply with all the provisions of a certain ordinance .... entitled ‘An Ordinance granting to the Colonial Street Railway Company, its successors and assigns, the right to' construct, operate and maintain its line or lines of street railway over, and along certain streets, bridges, avenues and highways in the City of York, under certain conditions and restrictions/ approved by the mayor of the said City of York on March 20, 1906, and shall indemnify the City of York of and from all loss and damage accruing to it in any way by reason of the passage of the above-recited ordinance, then this obligation to be [241]*241void; otherwise to be and remain in full force and virtue.”

The defendants contend that the court below erred in treating the sum of the bond as liquidated damages. They argue (a) the presumption to be that a lump sum named by the parties to a contract is a penalty rather than liquidated damages; and (b) where an agreement contains several matters of different degrees of importance and yet the sum named is payable for the breach of any, even the least, it is to be construed as a penalty and not as liquidated damages. Neither of these principles governs the present case.

(a) “The question whether the amount stated in a conditional bond or contract is to be taken as a penalty or a liquidation of damages arising from a breach of the condition, is to be determined by the. intention of the parties, drawn from the words of the whole contract, examined in the light of its subject-matter, and its surroundings; and in this examination we must consider the relation which the sum stipulated bears to the extent of the injury which may be caused by the several breaches provided against, the ease or difficulty of measuring a breach in damages, and such other matters as are legally or necessarily inherent in the transaction:” March v. Allabough, 103 Pa. 335. “The difficulty of measuring the damages which would result from a breach of contract is always an important element, even a controlling one, in determining whether the intention of the parties was to fix a sum certain as the just amount to be recovered instead of leaving the question to the uncertain estimate of the jury. Generally where the covenant is for the performance or non-performance of a single act or of several acts, damages for the breach of which cannot be measured by any fixed standard, the sum named if reasonable in amount will be considered as liquidated damages:” Emery v. Boyle, 200 Pa. 249. “It is competent for the parties by mutual agreement to settle the amount of the damages that are in their nature uncertain [242]*242and difficult of estimation, where they depend upon the failure to perform a single act:” Shreve v. Brereton, 51 Pa. 175. Here the action was to recover on the single ground that the appellant railway company had failed to complete and operate its line within the time required by the ordinance. That the completion and operation of the line within the limited period was the most important thing that the parties had in mind is made apparent by the agreement that after such completion the city was to accept a bond of $5,000 in substitution for the bond of $25,000. That the last-named sum was intended as liquidated damages to cover the loss which the city would sustain in the event of the company’s failure to complete and operate its line within the stipulated time is made plain by the words of the ordinance: “The said company, its successors and assigns, also agrees that said bond shall become forfeited to and collectible by the city of York as assessed and liquidated damages due and owing said city in the event of the failure of said company, its successors and assigns, to complete and operate its line of railway. . . .” This was the only breach for which the ordinance provided that the sum named in the bond should be considered as liquidated damages, and clearly it was one where the difficulty of measuring the damages would be insurmountable; such is always the case where the object is to give compensation for public inconvenience: Malone v. Phila., 147 Pa. 416.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Traylor v. Grafton
332 A.2d 651 (Court of Appeals of Maryland, 1975)
Franchise Realty Interstate Corp. v. State College Shopping Center, Inc.
47 Pa. D. & C.2d 632 (Centre County Court of Common Pleas, 1969)
Commonwealth v. Telegraph Press
62 Pa. D. & C. 328 (Dauphin County Court of Common Pleas, 1948)
Holmes Electric Protective Co. v. Goldstein
24 A.2d 162 (Superior Court of Pennsylvania, 1941)
Heller v. First National Bank & Trust Co. of Newtown
38 Pa. D. & C. 79 (Bucks County Court of Common Pleas, 1940)
Vrooman v. Milgram
188 A. 538 (Superior Court of Pennsylvania, 1936)
Power Manufacturing Co. v. Bellefonte Trust Co.
13 Pa. D. & C. 321 (Centre County Court of Common Pleas, 1929)
Lackawanna Boiler & Grate Co. v. Lee Coal Storage Co.
139 A. 315 (Supreme Court of Pennsylvania, 1927)
Sautter v. Rowland
131 A. 733 (Supreme Court of Pennsylvania, 1925)
Graver v. Chamis & Galationos
6 Pa. D. & C. 731 (Lancaster County Court of Common Pleas, 1925)
Delmont Gas Coal Co. v. Diamond Alkali Co.
119 A. 710 (Supreme Court of Pennsylvania, 1923)
Curran v. Philadelphia
107 A. 636 (Supreme Court of Pennsylvania, 1919)
Egolf v. City of York
92 A. 695 (Supreme Court of Pennsylvania, 1914)
Weschler v. Buffalo & Lake Erie Traction Co.
51 Pa. Super. 92 (Superior Court of Pennsylvania, 1912)
Gottschall v. Kapp
47 Pa. Super. 102 (Superior Court of Pennsylvania, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
78 A. 128, 229 Pa. 236, 1910 Pa. LEXIS 578, Counsel Stack Legal Research, https://law.counselstack.com/opinion/york-v-york-railways-co-pa-1910.