Commonwealth v. Telegraph Press

62 Pa. D. & C. 328, 1948 Pa. Dist. & Cnty. Dec. LEXIS 214
CourtPennsylvania Court of Common Pleas, Dauphin County
DecidedFebruary 2, 1948
Docketno. 2
StatusPublished

This text of 62 Pa. D. & C. 328 (Commonwealth v. Telegraph Press) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Dauphin County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commonwealth v. Telegraph Press, 62 Pa. D. & C. 328, 1948 Pa. Dist. & Cnty. Dec. LEXIS 214 (Pa. Super. Ct. 1948).

Opinion

Woodside, J.,

— This comes before us on preliminary objections to the complaint. The objections were three: (1). A motion to. strike off; (2) a motion for a more specific complaint; and (3) a demurrer. The first two objections having been cured by an amended complaint, the only question before us now is the demurrer which is based on the theory that plaintiff is seeking to enforce a penalty rather than collect liquidated damages.

A contract was awarded The Telegraph Printing Company of Pennsylvania to publish the decisions of the Superior Court of Pennsylvania for a term of 10 years, commencing July 1, 1935, and ending June 30, 1945. This contract provided, inter alia, that the printing company should cause each volume to be electrotyped and the plates thereof backed and preserved as the property of the Commonwealth. The printing company further agreed that all volumes of Superior Court Reports published under the contract should be ready for delivery to the purchasers thereof not later [330]*330than 45 days after the last correction for said volume was received.

Subsequent to the contract defendant changed its name to The Telegraph Press. The contractor failed to publish the reports within the time specified in the contract. The breach was attributed to difficulty in obtaining metal for electrotyping plates required by the contract due to abnormal shortages and dislocations caused by the war.

To remedy this situation the Act of May 6, 1943, P. L. 189, authorized the State reporter to waive the provision requiring that the reports be electrotyped and on November 16,1943, pursuant to this authority an agreement was concluded between the State reporter and The Telegraph Press which provided, inter alia, that the State reporter agreed to waive the electrotyping requirement commencing with Volume 151 and in consideration of such waiver as to Volumes 151 and 152 The Telegraph Press agreed to deliver to the Secretary of the Commonwealth, for payment to the State Treasurer, the sum of $700 within 30 days after the completion of Volume 151 and an additional sum of $700 within 30 days after the completion of Volume 152, the sum of $700 representing the approximate cost to the contractor of electrotyping one volume of reports.

It was further agreed by the parties that in lieu of making a payment of $700 for Volume 153 and each succeeding volume the contractor would speed up the publication of the advance reports and bound volumes of the Superior Court Reports. The contract set up a schedule of liquidated damages to be paid by the contractor for failure to meet the specified deadlines for galley proofs, advance reports and bound volumes. Paragraph Bid) is the only part of this schedule of importance since the Commonwealth is not invoking the others. It provides as follows:

“id) The Telegraph Press will pay, as liquidated damages for failure to publish and deliver the bound [331]*331volume to the State Librarian and to all subscribers for the bound volume, according to the terms of paragraph 10 of the original contract, the sum of Twenty-five Dollars ($25.00) for each day after the 45th day, provided that such penalty shall not be imposed unless, in a contract year beginning July 1 and ending June 30, publication and delivery of at least one volume are delayed for thirty days, or publication and delivery of two or more volumes are delayed for a total and cumulative number of thirty days or more.”

The contract also provided that the total amount payable as liquidated damages on any one volume should not exceed $700.

The terms of the November 1943 contract relative to the time for delivery of bound volumes 153,154,155, 156 and 157 were breached by the contractor so that the maximum sums provided therein became applicable.

Suit was instituted by the Commonwealth to recover the sum of $4,900 together with interest and fees allowed by law to the Attorney General, representing $1,400 due on the publication of Volumes 151 and 152, and $3,500 damages for delay in the publication of bound Volumes 153, 154, 155, 156 and 157.

Defendant contractor pleaded tender of the $1,400 sum due on Volumes 151 and 152 and moved for a dismissal of the complaint for legal insufficiency for the reason that the sums demanded were not liquidated damages but penalties.

The question at issue is whether the sums sued for are recoverable by the Commonwealth as liquidated damages or whether being in the nature of a penalty recovery should be denied.

Whether a sum stipulated for breach of contract is a penalty or liquidated damages cannot be determined by the name given it in the contract: Philadelphia Dairy Products Company, Inc., v. Polin et al., 147 Pa. Superior Ct. 26 (1941); Lackawanna Boiler & Grate Co. [332]*332v. Lee Coal Storage Co., 290 Pa. 561 (1927). In the present case both terms are used, as witness paragraph 3 {d) of the contract quoted above.

The rule most often cited by the courts of Pennsylvania is that the intent of the parties should control: Holmes Electric Protective Co. of Philadelphia v. Goldstein, 147 Pa. Superior Ct. 506 (1942) ; York v. York Rys. Co., 229 Pa. 236 (1910). Professor Williston in his work on contracts, volume 3, paragraphs 777 and 778, points out that if this rule is followed strictly nearly every penalty would be enforced for if the parties provided a penalty they must have intended a penalty. If the intent of the parties test is applied to the contract in question there can be no question that the sums in question are liquidated damages.

A. L. I. Restatement of the Law of Contracts, §339, sbts forth the law as follows:

“LIQUIDATED DAMAGES AND PENALTES.

“ (1) An agreement, made in advance of breach, fixing the damages therefor, is not enforceable as a contract and does not affect the damages recoverable for the breach, unless

“(a) the amount so fixed is a reasonable forecast of just compensation for the harm that is caused by the breach, and

“(b) the harm that is caused by the breach is one that is incapable or very difficult of accurate estimation.”

The damages the Commonwealth suffered are incapable of accurate estimation and the liquidated damages stipulated are not unreasonable. Defendant contends that the Commonwealth was only inconvenienced not damaged, but this inconvenience to the Bench, the Bar and the public generally caused by the delay in publishing the bound volumes of the Superior Court Reports was of sufficient public concern to warrant the liquidated damages stipulated.

[333]*333The Commonwealth further contends that even if the sums in question are construed a penalty there is sufficient authority to take them out of operation of the general rules of contract. This contention is based on the Act of May 6, 1943, P. L. 185, which reads as follows:

“See. 3. The State Reporter shall have full power to formulate and prescribe terms and specifications of the contract for the printing and publication of the . . . bound volumes ..., in addition to those enumerated in this act, including, but not limited to . . . (b) the form and the terms of the contract, including penalty provisions deemed necessary or desirable by Mm to assure proper performance by the contractor . . .”. (Italics supplied.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lackawanna Boiler & Grate Co. v. Lee Coal Storage Co.
139 A. 315 (Supreme Court of Pennsylvania, 1927)
Holmes Electric Protective Co. v. Goldstein
24 A.2d 162 (Superior Court of Pennsylvania, 1941)
Philadelphia Dairy Products Co. v. Polin
23 A.2d 221 (Superior Court of Pennsylvania, 1941)
Boas v. City of Philadelphia
84 Pa. Super. 340 (Superior Court of Pennsylvania, 1924)
City of Marshall v. Adkins
127 S.W. 1148 (Court of Appeals of Texas, 1910)
Malone v. Philadelphia
23 A. 628 (Supreme Court of Pennsylvania, 1892)
York v. York Railways Co.
78 A. 128 (Supreme Court of Pennsylvania, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
62 Pa. D. & C. 328, 1948 Pa. Dist. & Cnty. Dec. LEXIS 214, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commonwealth-v-telegraph-press-pactcompldauphi-1948.