Yellowstone Pipe Line Company, a Corporation v. Anthony Kuczynski

283 F.2d 415, 1960 U.S. App. LEXIS 3608
CourtCourt of Appeals for the Ninth Circuit
DecidedOctober 11, 1960
Docket16435
StatusPublished
Cited by12 cases

This text of 283 F.2d 415 (Yellowstone Pipe Line Company, a Corporation v. Anthony Kuczynski) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Yellowstone Pipe Line Company, a Corporation v. Anthony Kuczynski, 283 F.2d 415, 1960 U.S. App. LEXIS 3608 (9th Cir. 1960).

Opinion

KOELSCH, Circuit Judge.

Plaintiff’s suit was to recover damages for injury to community property alleged to have been caused by the defendant’s negligent failure to repair the bed and protect the banks of a stream which defendant had altered and cut in order to construct a pipeline. $8,000.00 was sought as general and special damages for injuries to plaintiff’s land and improvements, plus $500.00 for loss of his personal property. 1

The cause was tried to the court sitting without a jury. At the conclusion of plaintiff’s case the defendant made a motion to dismiss on the ground that no negligence was shown; ruling was reserved; a second such motion was made based upon two releases executed by plaintiff. Both motions were denied and the court made findings and entered judgment in favor of plaintiff in the sum of $3,172.00. 2

*417 Defendant has appealed.

Jurisdiction of the court below was based upon diversity of citizenship under 28 U.S.C.A. § 1332, and of this court is conferred by 28 U.S.C.A. §§ 1291 and 1294.

Plaintiff’s land is situated in the mountains of northern Idaho and lies to the south of and adjoining other lands belonging to one William Jackson. A stream known as Wolf Lodge Creek meanders through both tracts in a channel which, following the natural slope of the ground, extends to the east for some distance along the northern boundary of Jackson’s property, then, changing direction, continues to the south into the southerly part of plaintiff’s land when it again turns and stretches on to the southwest. A bridge belonging to plaintiff crossed the creek in the southern portion of plaintiff’s land and afforded access to his house from a public road. To the north of the house was an artificial pond constructed by plaintiff and devoted to the rearing of trout.

The parties had entered into a “Right of Way” agreement in the fall of 1953 by which defendant was granted an easement through plaintiff’s land for an underground pipeline. The agreement recited a cash consideration paid to plaintiff and also provided that the defendant would “ * * * pay any damages which may arise to crops, buildings, drain, tile, fences and timber by reason of grantee’s operations.”

The next year the line was constructed; the route followed intersected Wolf Lodge Creek at two points, first on Jackson’s land and again immediately to the east of the bridge on plaintiff’s land. In the performance of this work defendant first cleared the ground of all vegetation and obstructions, and excavated a trench; sections of pipe were then assembled and welded together, after which the line was laid in place and the trench was filled with the same earth that had been previously removed. This procedure was also followed in laying the pipe through the creek, except that there it was necessary to first cut the banks on each side and then dig the trench to a depth of about 48 inches below the channel. Defendant’s chief inspector, who described that particular part of the work, stated that the soil at the two crossings was “rather gravelly and the banks would only stand at about a forty-five degree angle, so in order to have a ditch wide enough I imagine it was eight foot wide at the top when we were in the process of laying it.”

In 1956, during the annual spring runoff, loose gravel in the channel collected at the abutments of the bridge; this dammed the stream and caused water to rise and flow over the south bank of the creek and to wash out plaintiff’s southerly approach to the bridge over his land in that area. Plaintiff thereupon made demand upon defendant for damages; negotiations were entered into, resulting in an agreement by the terms of which defendant paid plaintiff the sum of $562.-50 and performed some work on and around the bridge. 3 To evidence the settlement, plaintiff executed two documents, one dated July 6, 1956 and the other August 1, 1956; both are entitled “Receipt-Release.”

In May 1957 plaintiff’s land was again flooded when the banks of Wolf Lodge Creek washed out. These washes occurred at both places where defendant had made its excavation and crossed the creek with the pipeline. Water from the *418 breach in the bank on the Jackson property flowed into and filled plaintiff’s fish pond causing the retaining dam to burst and allowing some 500 trout ranging in size from 12 to 14 inches in length to escape ; water from the other break in the bank carried away plaintiff’s bridge and covered the meadow along the creek with gravel and debris. Plaintiff’s demand for damages was refused and the instant suit followed.

None of the items for which plaintiff is claiming compensation is among those for which defendant agreed, as part of the consideration for the right of way agreement, “ * * * to pay any damages which may arise by reason of grantee’s operations.” As defendant correctly points out, plaintiff’s action, as in Shell Pipe Line Corp. v. Coston, Tex.Civ. App.1931, 35 S.W.2d 1056, sounds in tort rather than contract, and the burden was upon plaintiff to establish that the defendant was negligent in constructing its pipeline. But defendant argues that the record fails to reveal any question of fact as to such negligence and also that the two releases signed by plaintiff constitute a final settlement of the very claim he is now asserting.

This appeal therefore presents two issues:

“V. In the construction of said pipeline defendant altered and changed the channel of Wolf Lodge Creek and destroyed the natural creek bed and banks in two places: one place was immediately north of the north boundary of plaintiff’s land and the other was in the place heretofore mentioned where the stream changes its direction to a southwesterly course. Defendant failed to either restore the banks or protect the damaged and changed area thereof with material which would prevent these damaged areas from washing out when the annual runoff of melting snow caused high water.

(1) Was defendant negligent? If so,

(2) Was plaintiff estopped from commencing and prosecuting an action against the defendant to recover on this claim ? 4

The critical findings of the District Court are as follows:

“VI. During the months of April and May, 1957, at the time of high water, washouts occurred at the places where the defendant had constructed its pipeline. These washouts were caused by the weakened condition of the banks where defendant had destroyed their natural condition * * *.
“VII. That the various receipts and releases for damages caused prior to the 1957 flood do not constitute a release by plaintiff to defendant for damages occurring after the year 1956.
“VIII. That the failure of defendant to rip-rap or otherwise protect the damaged banks constitutes a negligent omission on the part of defendant.”

Under Idaho law, negligence is generally a question of fact:

“It has been well said by one court (in Pittsburgh, Ft. W. & C. R. Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
283 F.2d 415, 1960 U.S. App. LEXIS 3608, Counsel Stack Legal Research, https://law.counselstack.com/opinion/yellowstone-pipe-line-company-a-corporation-v-anthony-kuczynski-ca9-1960.