Wunschel & Small, Inc. v. United States

30 Cont. Cas. Fed. 70,354, 1 Cl. Ct. 485, 1982 U.S. Claims LEXIS 2325
CourtUnited States Court of Claims
DecidedOctober 7, 1982
DocketNo. 419-80C
StatusPublished
Cited by2 cases

This text of 30 Cont. Cas. Fed. 70,354 (Wunschel & Small, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wunschel & Small, Inc. v. United States, 30 Cont. Cas. Fed. 70,354, 1 Cl. Ct. 485, 1982 U.S. Claims LEXIS 2325 (cc 1982).

Opinion

OPINION

SCHWARTZ, Judge:

Plaintiff sues for $764,000 as damages for an alleged breach of its contract to lay an irrigation water pipeline for the Bureau of Reclamation in El Dorado County, California, in the Sierra foothills. The contract period began in January 1977; the work was completed in August 1979, 166 days late. The Government withheld, as liquidated damages of $500 per day, $75,000 otherwise payable to plaintiff, and now counterclaims for an additional $8,000, for a total of $83,000 for the 166 days.

The two-fold claim of the plaintiff is, first, that the work was greatly delayed and its cost increased, extending completion for 116 days beyond schedule, by reason of the refusal of the Bureau’s officers to allow the trees on the right-of-way to be cut sufficiently to give plaintiff access to the trench in which pipe was to be laid. Second, that plaintiff was improperly denied extensions of time of 115 days on which weather prevented work. The Government’s position is that both contentions are without merit; that the claim of denial of access is an afterthought for which notice was not given as required; that in fact trees were cut as the contract contemplated; and that plaintiff was allowed all it was entitled by way of extensions for weather. The case has been tried and the Government is upheld in all respects.

The Claim of Denial of Access to the Trench

The Government made available to plaintiff as the contractor, a 50-foot wide right-of-way over the 13.8 mile route, of which about 43 feet was an easement for construction, obtained by the Government, and only the center portion of roughly 6 feet, sufficient for the pipe trench, would be a permanent Government easement. The easement ran through heavily timbered lands, residential property and fruit orchards. The Government was obligated to pay the private owners for any damage to trees. The private ownership of most of the right-of-way and the intense interest in the area in the preservation of trees are reflected in the explicit provisions in the contract, among them repeated statements of the control by the Government over the decision as to cutting of trees required for the work.

One contract clause, 1.5.10.a., provided in part that “in no event shall the contractor remove any trees, shrubs, or vines on the right-of-way or construction easements without the prior approval of the contracting officer.”1

Another, clause 2.1.1., entitled “Clearing,” provided that the portion of the right-of-way required for access to and for constructing the work “shall be cleared of all trees, brush, rubbish, and other objectionable matter,” and, further, that “[o]nly those [487]*487trees designated by the Contracting Officer may be cut.”2

A third, 1.6.1., “Landscape Preservation” required that “[e]xcept where clearing is required for permanent works, for approved construction roads, and for excavation operations, all trees, native shrubbery, and vegetation shall be preserved and shall be protected from damage....”3

Finally, there appeared a clause explicitly entitled “Preservation of Trees,” again conditioning removal of trees on the approval of the contracting officer, and listing the trees not to be removed without such approval.

1.6.2. Preservation of Trees

a. Preservation. — All trees and shrubbery which are not specifically required to be cleared or removed for construction purposes shall be preserved and shall be protected from any damage that may be caused by the contractor’s construction operations and equipment. The removal of trees or shrubs will be permitted only after prior approval by the contracting officer.
The following trees located along the El Dorado Main No. 2 Pipeline shall not be removed unless they are located within the pipe trench excavation:

The list which follows runs for 36 pages and contains over 1800 trees, identified by location on the right-of-way (“station”) whether left or right of the center line, diameter and type of tree. The list begins as follows:

Station Left Right Diameter Tree type
14 + 12 20 feet 30 inches Cedar
14 + 18 6.3 feet 24 inches Cedar
14 + 21 19 feet 18 inches Cedar
14 + 22 22 feet 18 inches Forked oak
14 + 57 13 feet 24 inches Cedar
14 + 72 16.5 feet 30 inches Cedar
15 + 12 11 feet 18 inches Cedar
15 + 23 23 feet 30 inches Cedar
15 + 42 3 feet 48 inches Forked oak
16 + 09 12 feet 36 inches Cedar
16 + 19 12 feet 36 inches Cedar
16 + 88 12 feet 30 inches Oak
17 + 00 Left side 2 to 3 inches Cedars (scattered)
19 + 50 26 feet 36 inches Pine
20 + 26 10 feet 6 inches Apple
20 + 28 12 feet 10 inches Apple
21 + 56 1 foot 18 inches Cedar
21 + 65.5 On centerline 8 inches Cedar
21 + 75 1 foot 8 inches Cedar
21 + 88.5 10 feet 30 inches Pine
21 + 88.5 1 foot 14 inches Pine
21 + 90 7 feet 24 inches Pine
22 + 18 10 feet 8 inches Pine
22 + 27.5 On centerline 4 to 6 inches Cedar cluster
22 + 27.5 16 feet 30 inches Pine
22 + 27.5 24.5 feet 24 inches Pine
22 + 30 30 feet 18 inches Cedar
22 + 36 31 feet 12 inches Cedar
22 + 37 10 feet 24 inches Oak
22 + 62 11.8 feet 24 inches Pine
[488]*488Once the work started, the Bureau’s inspector at the site passed on the cutting of every tree on the right-of-way other than in the space needed for the trench. His instructions were to balance the contractor’s needs against the Government’s interest in preserving trees. Occasional protests by the plaintiff’s site representative would concern the distance between the trees left standing or their proximity to the trench, and the consequent difficulty or awkwardness in moving equipment to the trench to excavate, suspend and lower the pipe into the trench and perform the other necessary operations. The equipment included ditch-digging backhoes, a side-boom pipelaying tractor and various other items of heavy equipment. The terrain was largely wooded and sometimes steep. There was a good deal of give and take about distances between trees, routes and alternative routes for access and what trees should be cut. A few decisions were presented by plaintiff to the inspector’s superior for review.
In some cases, trees would be left standing either near the trench, or so close together as to limit access to only one piece of equipment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Martin Construction, Inc. v. United States
102 Fed. Cl. 562 (Federal Claims, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
30 Cont. Cas. Fed. 70,354, 1 Cl. Ct. 485, 1982 U.S. Claims LEXIS 2325, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wunschel-small-inc-v-united-states-cc-1982.