Wsp USA Solutions Inc. v. Secretary of the Army

Court of Appeals for the Federal Circuit·Decided February 21, 2025·No. 23-1256·Unpublished

Opinion

NOTE: This disposition is nonprecedential.

United States Court of Appeals for the Federal Circuit

WSP USA SOLUTIONS INC., Appellant

v.

SECRETARY OF THE ARMY, Appellee

2023-1256

Appeal from the Armed Services Board of Contract Appeals in No. 62674, Administrative Judge J. Reid Prouty, Administrative Judge Richard Shackleford, Administrative Judge Kenneth David Woodrow.

Decided: February 21, 2025

SCOTT ARNOLD, Blank Rome LLP, Washington, DC, argued for appellant. Also represented by DAVID LEE BODNER, STEPHANIE HARDEN, DAVID MICHAEL NADLER, ADAM SETH PROUJANSKY.

PATRICK ANGULO, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington , DC, argued for appellee. Also represented by BRIAN 2 WSP USA SOLUTIONS INC. v. SECRETARY OF THE ARMY

M. BOYNTON, PATRICIA M. MCCARTHY, CORINNE ANNE NIOSI.

Before PROST, TARANTO, and HUGHES, Circuit Judges.

HUGHES, Circuit Judge.

WSP USA Solutions Inc., a private contractor, appeals the final decision of the Armed Services Board of Contract Appeals that WSP was properly compensated for its services rendered pursuant to a contract with the United States Army Corps of Engineers. WSP submitted a certified claim under the Contract Disputes Act, 41 U.S.C. §§ 7101–09, alleging costs it was owed by the government because of incorrect pricing for services performed under three specific task orders. The Contracting Officer determined the services were correctly priced and denied the claim. WSP appealed the Contracting Officer’s final decision , and the Board concluded the underlying contract unambiguously provided that pricing for the contested task orders was determined by the time the orders were first issued and denied the appeal on this basis. Because we conclude the Board did not properly consider the contract in its entirety as modified by the later-issued task orders in evaluating each of the parties’ purported unambiguous interpretations of the contractual pricing scheme and reject both parties’ arguments that the pricing scheme is unambiguous , we vacate the Board’s finding that the contract was unambiguous and remand for proper investigation of the contract terms, including modifications made to task orders issued pursuant the contract.

I

The pricing dispute underlying this appeal turns on a question of contract interpretation. The question raised on appeal is whether the fixed price for work performed under a task order is established by the date the task order is issued or by the date on which the work is actually performed

WSP USA SOLUTIONS INC. v. SECRETARY OF THE ARMY 3

under the task order when such work extends beyond its initial expected period of performance and into a later contract year. Before addressing the merits, we will first describe the overall contract, the provision at issue, and the underlying series of events relevant to this dispute.

A

On October 22, 2014, the United States Army Corps of Engineers awarded requirements contract No. W911WN- 15-D-0001 to WSP USA Solutions Inc.1 Under the contract, WSP would provide temporary emergency power services required for federally declared emergencies. Specifically, WSP would provide emergency support to the Federal Emergency Management Agency (FEMA) Region IX (Arizona , California, and Nevada), Region X (Idaho, Oregon, and Washington), and certain areas outside the continental United States (Puerto Rico, US Virgin Islands, Alaska, Hawaii, Guam, and American Samoa). J.A. 10016. The

1 The Board’s final decision described the contract as “an indefinite quantity indefinite delivery” (IDIQ) contract instead of an indefinite delivery requirements contract. J.A. 2. While the contract explicitly includes the Requirements Clause at subsection 52.216-21 of the Federal Acquisition Regulation, see J.A. 10058–59, it does not include the IDIQ Clause at subsection 52.216-22 of the Federal Acquisition Regulation. To the extent the record includes references to an indefinite delivery indefinite quantity requirements contract, we note that subsection 16.501-2(a) of the Federal Acquisition Regulation specifically defines indefinite-quantity contracts and requirements contracts as two separate and distinct “types of indefinite-delivery contracts.” As such, we find substantial evidence supports a finding that the contract was a requirements contract and not an indefinite quantity contract.

4 WSP USA SOLUTIONS INC. v. SECRETARY OF THE ARMY

initial contract was for $95,000,000 and had a one-year base period and four one-year option periods. See J.A. 10001–11.

The contract is divided into three parts. See J.A. 10001.

Part I of the contract contains the Schedule, which consists of Sections A–C and E–G. J.A. 10001–55. Relevant here is Section B (Supplies or Services and Prices/Costs); Section C (Description/ Specs/ Work Statement); and Section F (Deliveries or Performance). Part II of the contract consists of Section I (Contract Clauses), which contains the specific Federal Acquisition Regulation (FAR) clauses that are incorporated into the contract by either reference or full text. J.A. 10056–78. Two FAR clauses are relevant here: FAR 52.216-21 (Requirements) subsection (f) and 52.216- 21 (Ordering). Part III of the contract is Section J (List of Documents, Exhibits and Other Attachments), which contains additional documents applicable to the contract. J.A. 10079–84. Relevant to this appeal, Section J includes a Rate Schedule document with pricing details.

Section B outlines the specific “Supplies or Services and Prices” to be provided under the contract. The contract ’s required supplies and services are divided into two basic categories: “ACI[2] Emergency Power”3 and

2 As defined in the contract’s Performance Work Statement (PWS), an Advanced Contract Initiative (ACI) is “[t]he process of having a contract in place prior to a disaster to permit quick and immediate response.” J.A. 10016–17.

3 The contract line-item numbers for ACI Emergency Power cover the contractor’s provision of “all labor, transportation , equipment, materials supervision, and required internal logistic support to perform generator set activities in support of [certain] FEMA regions . . . as stated in the [PWS].” J.A. 10002.

WSP USA SOLUTIONS INC. v. SECRETARY OF THE ARMY 5

“Readiness and Preparedness.”4 Section B structures the contract around ten firm-fixed price (FFP) contract line- item numbers (CLINs): two for the initial Base Year and two each for the four exercisable option years (OY). See J.A. 10002–11. CLINs 0001, 1001, 2001, 3001, and 4001 cover ACI Emergency Power for the Base Year and the four option years, respectively. See J.A. 10002, 10004, 10006, 10008, 10010. CLINs 0002, 1002, 2002, 3002, and 4002 cover Readiness and Preparedness for the Base Year and the four option years, respectively. See J.A. 10003, 10005, 10007, 10009, 10011. Section B also specifies the applicable period of performance for each CLIN. “The period of performance for the Base Year will be a period of one year from the date of the contract award,” J.A. 10002, 10003, and “[t]he period of performance for [each] option will be a period of one year upon expiration of [the prior] year,” J.A. 10004–11. The exact dates of the period of performance for each CLIN are set forth in Section F of the contract :

CLIN 0001 and 0002 (i.e., base year): Oct. 22, 2014–Oct. 21, 2015 CLIN 1001 and 1002 (i.e., OY 1): Oct. 22, 2015– Oct. 21, 2016 CLIN 2001 and 2002 (i.e., OY 2): Oct. 22, 2016– Oct. 21, 2017

4 The contract line-item numbers for Readiness and Preparedness “cover[] the submission and updating of specific plans and reports, coordination with government agencies on the movement of personnel and equipment when necessary, and readiness activi[ti]es that will be described in the task order scope of work and in accordance with the [PWS] of the contract” and in support of certain FEMA regions. J.A. 10003.

Free access — add to your briefcase to read the full text and ask questions with AI

Wsp USA Solutions Inc. v. Secretary of the Army, (Fed. Cir. 2025).

Wsp USA Solutions Inc. v. Secretary of the Army (Wsp USA Solutions Inc. v. Secretary of the Army) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Medlin Construction Group, Ltd. v. Harvey
449 F.3d 1195 (Federal Circuit, 2006)
Edward R. Marden Corporation v. United States
803 F.2d 701 (Federal Circuit, 1986)
McAbee Construction, Inc. v. United States
97 F.3d 1431 (Federal Circuit, 1996)
Laura v. King v. Department of the Navy
130 F.3d 1031 (Federal Circuit, 1997)
Coast Federal Bank, Fsb v. United States
323 F.3d 1035 (Federal Circuit, 2003)
Garcia v. Department of Homeland Security
780 F.3d 1145 (Federal Circuit, 2015)
Agility Logistics Servs. Co. KSC v. Mattis
887 F.3d 1143 (Federal Circuit, 2018)
Premier Office Complex of Parma, LLC v. United States
916 F.3d 1006 (Federal Circuit, 2019)
CITGO Asphalt Refining Co. v. Frescati Shipping Co.
589 U.S. 348 (Supreme Court, 2020)
Triple Canopy, Inc. v. Secretary of the Air Force
14 F.4th 1332 (Federal Circuit, 2021)