Wood Group USA, Inc. v. Targa NGL Pipeline Company LLC

CourtCourt of Appeals of Texas
DecidedAugust 17, 2023
Docket01-21-00542-CV
StatusPublished

This text of Wood Group USA, Inc. v. Targa NGL Pipeline Company LLC (Wood Group USA, Inc. v. Targa NGL Pipeline Company LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wood Group USA, Inc. v. Targa NGL Pipeline Company LLC, (Tex. Ct. App. 2023).

Opinion

Opinion issued August 17, 2023

In The

Court of Appeals For The

First District of Texas ———————————— NO. 01-21-00542-CV ——————————— WOOD GROUP USA, INC., Appellant V. TARGA NGL PIPELINE COMPANY, LLC, Appellee

On Appeal from the 215th District Court Harris County, Texas Trial Court Case No. 2019-85546

MEMORANDUM OPINION

In this pipeline construction dispute, appellant Wood Group USA, Inc.

sought additional payments through change order requests pursuant to a

construction agreement between the parties. Appellee Targa NGL Pipeline

Company, LLC refused to agree to the change order requests, asserting that the requests were barred by the parties’ agreement. Targa filed a suit for declaratory

judgment, and Wood Group countersued alleging, among other claims, that Targa

breached the parties’ agreement. The trial court granted summary judgment in

favor of Targa, denying Wood Group’s counterclaims and rendering the

declarations requested by Targa, including that Wood Group was not entitled to

additional compensation under the parties’ construction agreement.

On appeal, Wood Group advances issues challenging the summary judgment

by arguing that (1) the trial court erred in rendering a take-nothing judgment on

Wood Group’s claim that Targa breached the terms of the agreement that required

Targa to provide specific easements and workspaces because Targa made no

argument for why it was entitled to summary judgment on that counterclaim;

(2) the trial court erred in “nullifying” a portion of the agreement regarding Wood

Group’s rights following a force majeure event and declaring that Wood Group “is

not entitled to receive any monetary compensation for delays relating to . . . Force

Majeure events”; (3) the trial court misinterpreted the release-or-waiver provision

in one of the parties’ change orders and wrongly declared that it “constituted an

accord and satisfaction of all claims . . . contained within” any subsequent change

orders; and (4) the trial court erred in granting summary judgment based on

Targa’s allegations that Wood Group’s contractually-required notices were

untimely.

2 Based on the record, we hold that Targa proved that Wood Group’s

counterclaims fail as a matter of law, and Targa proved that it was entitled to the

declarations rendered by the trial court. Accordingly, we affirm.

Background

In September 2018, Targa contracted with Wood Group, a construction

contractor, to build an 80-mile section of Targa’s Grand Prix NGL Pipeline

System, a natural-gas liquid pipeline. The parties entered into the Construction

Agreement on September 7, 2018, and work began on the pipeline on September

10, 2018. The initial contract price was $43 million, and the Agreement required

Wood Group to finish the project by March 6, 2019.

Despite several delays and difficulties, Wood Group completed the pipeline

construction project by July 3, 2020. During and immediately after construction,

the parties agreed to several change orders that increased the contract price to

$60,104,766.70, which Targa paid to Wood Group in December 2020. A dispute

remained, however, regarding more than $25 million in additional costs. Wood

Group claims that Targa still owes payment based on delays for which Targa was

responsible or for which Targa bore the risk under the Agreement.

A. Construction Agreement

The Agreement used a “unit price” model to determine the total contract

price. For example, the Agreement provided that Targa would pay $164.48 per

3 linear foot for the completion of horizontally directionally drilled (HDD) bores in

dirt and $351.58 per linear foot for HDD bores in rock. The Agreement stated that

this unit price “shall include, but not be limited to, excavation, . . . all HDD related

activities such as set up and preparation of entry and exit hole work areas, boring

and reaming, . . . and making tie-ins to the mainline.” Stringing, welding, and other

related activities were included in other unit prices set out in the Agreement. The

Agreement originally provided that the total price was not to exceed $43 million,

and it provided that “[t]he Contract Price is subject to adjustment only by Change

Order as provided in Article 6” of the Agreement.

In order for Wood Group, as the Contractor, to perform the agreed-upon

work, section 4.2 of the Agreement obligated Targa, the Owner, to provide Wood

Group “with reasonable access to the Site on which the Pipeline is to be physically

situated . . . sufficient to permit [Wood Group] to progress with the Work without

material interruption or interference.” The Agreement expressly referenced

“Alignment Sheets” as providing the particular details of the access to the right of

way and temporary workspaces necessary for Wood Group to do the work.

The Agreement set out the project schedule and provided for a “Guaranteed

Substantial Completion Date” of February 28, 2019. It further provided for

“Guaranteed Final Completion” by March 6, 2019, and it provided that these dates

“shall only be adjusted by Change Order as provided under this Agreement.” The

4 Agreement included a liquidated damages clause providing that, if substantial

completion occurs after the agreed-upon date, Wood Group “shall, following a

grace period of five (5) days, pay to [Targa] as liquidated damages twenty-five

thousand dollars ($25,000) per Day for each Day of delay until Substantial

Completion occurs, up to a maximum aggregate of one million dollars

($1,000,000).” In the event that Wood Group completed construction early,

however, the Agreement provided for an early-completion bonus.

The Agreement provided that Wood Group “reviewed the information that

forms the Agreement [and] the Scope of Work” and “warrants and represents that

such information is adequate and complete to construct the Pipeline for the

Contract Price, within the required times set forth in the Project Schedule.” Wood

Group further warranted “that it will make all investigations and inspections that it

deems necessary to perform the Work in accordance with the Project Schedule, and

understands the climate, terrain and other difficulties that it may encounter in

performing the Work. . . .”

The Agreement stated that Wood Group

assumes all risks related to, and waives any right to claim an adjustment in the Contract Price or the Project Schedule in respect of, any failure to timely perform the Work in accordance with the Project Schedule as a result of any conditions of the Site or any other locations where the Work is performed, including . . . climactic conditions and seasons (excluding Force Majeure events)[.]

5 The Agreement defined “Force Majeure” as including, among other things,

“catastrophic storms or floods, tornadoes, hurricanes, earthquakes and other acts of

God[.]” The Agreement stated:

[Wood Group’s] obligations under this Agreement shall be suspended to the extent that performance of such obligations is delayed by Force Majeure. . . . If the commencement, prosecution or completion of any Work is delayed by Force Majeure, then [Wood Group] shall be entitled to an extension to the Guaranteed Substantial Completion Date or Guaranteed Final Completion Date if such delay affects the performance of any work that is on the critical path of the Project Schedule . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Kellogg Brown & Root, Inc.
166 S.W.3d 732 (Texas Supreme Court, 2005)
In Re Bank One, N.A.
216 S.W.3d 825 (Texas Supreme Court, 2007)
Gym-N-I Playgrounds, Inc. v. Snider
220 S.W.3d 905 (Texas Supreme Court, 2007)
Goodyear Tire and Rubber Co. v. Mayes
236 S.W.3d 754 (Texas Supreme Court, 2007)
Mann Frankfort Stein & Lipp Advisors, Inc. v. Fielding
289 S.W.3d 844 (Texas Supreme Court, 2009)
American Airlines Employees Federal Credit Union v. Martin
29 S.W.3d 86 (Texas Supreme Court, 2000)
Centeq Realty, Inc. v. Siegler
899 S.W.2d 195 (Texas Supreme Court, 1995)
Komatsu v. United States Fire Insurance Co.
806 S.W.2d 603 (Court of Appeals of Texas, 1991)
Community Bank & Trust, S.S.B. v. Fleck
107 S.W.3d 541 (Texas Supreme Court, 2002)
Victoria Bank & Trust Co. v. Brady
811 S.W.2d 931 (Texas Supreme Court, 1991)
Cathey v. Booth
900 S.W.2d 339 (Texas Supreme Court, 1995)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Henry v. Masson
333 S.W.3d 825 (Court of Appeals of Texas, 2010)
Britton v. Texas Department of Criminal Justice
95 S.W.3d 676 (Court of Appeals of Texas, 2002)
In Re Border Steel, Inc.
229 S.W.3d 825 (Court of Appeals of Texas, 2007)
Dresser Industries, Inc. v. Page Petroleum, Inc.
853 S.W.2d 505 (Texas Supreme Court, 1993)
El Paso County v. Sunlight Enterprises Co., Inc.
504 S.W.3d 922 (Court of Appeals of Texas, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Wood Group USA, Inc. v. Targa NGL Pipeline Company LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wood-group-usa-inc-v-targa-ngl-pipeline-company-llc-texapp-2023.