Wolverine Fire Prot. v. Tougher Indust., No. Cv 01-0805554 S (Jun. 20, 2001)

2001 Conn. Super. Ct. 8002, 29 Conn. L. Rptr. 731
CourtConnecticut Superior Court
DecidedJune 20, 2001
DocketNo. CV 01-0805554 S
StatusUnpublished
Cited by1 cases

This text of 2001 Conn. Super. Ct. 8002 (Wolverine Fire Prot. v. Tougher Indust., No. Cv 01-0805554 S (Jun. 20, 2001)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wolverine Fire Prot. v. Tougher Indust., No. Cv 01-0805554 S (Jun. 20, 2001), 2001 Conn. Super. Ct. 8002, 29 Conn. L. Rptr. 731 (Colo. Ct. App. 2001).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
The present action arose following the defendants' alleged nonpayment for work that the plaintiff performed on a sub-subcontract. The plaintiff CT Page 8003 is Wolverine Fire Protection Co., Inc., d/b/a Smith Automatic Sprinkler. The defendants are Tougher Industries, Inc. (Tougher), and Employers Insurance of Wausau, A Mutual Company (Wausau).

The plaintiff alleges the following facts. Tougher was awarded a public contract by the department of public works on April 29, 1999, to act as a general contractor for construction and/or renovation to the Learning Corridor, a public building in Hartford, Connecticut. It is undisputed that the total contract exceeded $50,000. Pursuant to General Statutes § 49-41,1 Wausau, as surety, and Tougher, as principal, executed a labor and material payment bond, in favor of Gilbane Building Company, the obligee, in the amount of $10,440,000 to secure Tougher's obligation to pay all claimants for labor and materials used or reasonably required for use in completing its public contract. Prior to June 9, 1999, Tougher entered into a subcontract with Accurate Automatic Fire Protection, Inc. (Accurate), for the installation of a complete fire protection system in the Learning Corridor. Accurate subcontracted with the plaintiff for "engineering [services including] stamped drawings [and] fabrication of piping and materials" for the Learning Corridor project. (Complaint, ¶ 4.) The plaintiff was to be paid the contract price of $224,000 in periodic installment payments while performing the sub-subcontract.

The plaintiff commenced performance on the sub-subcontract in June 1999. The plaintiff received several progress payments in the form of checks from Tougher to Accurate and the plaintiff jointly. On April 18, 2000, the plaintiff completed its work on the sub-subcontract. The plaintiff alleges that it substantially performed all the terms and conditions on its part and submitted timely invoices.

The plaintiff alleges that Tougher failed to perform under the terms of the bond by failing to pay promptly for labor and material used or required for use in the performance of the contract. The plaintiff alleges it is owed $77,094 under the terms of the subsubcontract. Pursuant to General Statutes § 49-42,2 the plaintiff notified Tougher and Wausau of the amount due and owing on July 17, 2000. On September 25, 2000, Wausau denied liability as surety on the bond. On October 11, 2000, the plaintiff served a notice of claim by Federal Express and certified mail, return receipt requested on Wausau and Tougher demanding that Wausau make payment under the bond. Despite the plaintiff's notice of nonpayment, it has not been paid.

The plaintiff seeks payments and damages from Tougher, alleging that Tougher is liable on the following theories: the obligation on the bond pursuant to § 49-42 (count one); quantum meruit (count two); breach of implied covenant of good faith and fair dealing (count three); and breach of the Connecticut Unfair Trade Practices Act (CUTPA), General Statutes CT Page 8004 § 42-110b(a) et seq., (counts five)3. Similarly, the plaintiff alleges that the actions of Wausau constitute a violation of its surety obligation on the bond pursuant to § 49-42 (count one). The plaintiff also brings this action against Wausau for damages in quantum meruit (count two) and breach of the implied covenant of good faith and fair dealing (count four) and (CUTPA) (Count six). On April 5, 2001, Tougher and Wausau filed a motion to strike counts three, four, five and six of the plaintiff's complaint. The plaintiff filed an objection on April 18, 2001.

DISCUSSION
"The purpose of a motion to strike is to contest . . . the legal sufficiency of the allegations of any complaints . . . to state a claim upon which relief can be granted." (Internal quotation marks omitted.)Peter-Michael, Inc. v. Sea Shell Associates, 244 Conn. 269, 270,709 A.2d 558 (1998). "Thus, [i]f facts provable in the complaint would support a cause of action, the motion to strike must be denied. . . . [W]hat is necessarily implied [in an allegation] need not be expressly alleged. . . . It is fundamental that in determining the sufficiency of a complaint challenged by a defendant's motion to strike, all well-pleaded facts and those facts necessarily implied from the allegations are taken as admitted. . . . Indeed, pleadings must be construed broadly and realistically, rather than narrowly and technically." (Citations omitted; internal quotation marks omitted.) Gazo v. Stamford,255 Conn. 245, 260, 765 A.2d 505 (2001).

A
Counts Three and Four
Breach of Implied Covenant of Good Faith and Fair Dealing
1
Tougher and Wausau argue that counts three and four should be stricken because § 49-42 provides the plaintiff's exclusive remedy. The plaintiff argues that § 49-42 is not its exclusive remedy and that it has properly alleged all of the counts in its complaint.

"General Statutes (Rev. to 1983) §§ 49-41 through 49-43, which provide for the furnishing of bonds guaranteeing payment (payment bonds) on public works construction projects, were enacted to protect workers and materials suppliers on public works projects who cannot avail themselves of otherwise available remedies such as mechanic's liens." (Internal quotation marks omitted.) Blakeslee Arpaia Chapman, Inc. v. ElCT Page 8005Constructors, Inc., 239 Conn. 708, 714, 687 A.2d 506 (1997). "This legislation, known as the Little Miller Act (act), was patterned after the federal legislation popularly known as the Miller Act; 40 U.S.C. § 270a through 270d; and, therefore, [courts] have regularly consulted federal precedents to determine the proper scope of our statute. . . . The federal precedents, like our own, counsel liberal construction of statutory requirements other than those relating to specific time constraints. . . . As the United States Supreme Court has stated, the federal Miller Act is highly remedial in nature . . . [and] entitled to a liberal construction and application in order properly to effectuate the [legislative] intent and to protect those whose labor and materials go into public projects." (Citations omitted; internal quotation marks omitted.) Blakeslee Arpaia Chapman, Inc. v. ElConstructors, Inc., supra, 239 Conn. 716.

"Section

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Campbell v. Town of Plymouth
811 A.2d 243 (Connecticut Appellate Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
2001 Conn. Super. Ct. 8002, 29 Conn. L. Rptr. 731, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wolverine-fire-prot-v-tougher-indust-no-cv-01-0805554-s-jun-20-connsuperct-2001.