Wolfe v. Warfield

296 A.2d 158, 266 Md. 621, 1972 Md. LEXIS 768
CourtCourt of Appeals of Maryland
DecidedNovember 8, 1972
Docket[No. 24, September Term, 1972.]
StatusPublished
Cited by5 cases

This text of 296 A.2d 158 (Wolfe v. Warfield) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wolfe v. Warfield, 296 A.2d 158, 266 Md. 621, 1972 Md. LEXIS 768 (Md. 1972).

Opinion

McWilliams, J.,

delivered the opinion of the Court.

Appellants solicit the reversal of an adverse judgment ($16,544.11) of the Circuit Court for St. Mary’s County, the end result of a tedious squabble between an obstetrician and a contractor. We shall not disturb the findings of Chief Judge Dorsey (retired 15 July 1971) before whom, sitting without a jury, the case was tried.

Early in 1965 Dr. Warfield, one of the appellants, commissioned Elkan Groll, a Silver Spring architect, to prepare plans and specifications for a house to be built on a 14 acre tract in the easternmost corner of Montgomery County, about three miles northwest of the town of Laurel in neighboring Prince George’s County. Groll thought the house he had designed should cost between $82,000 and $89,000. The appellee Wolfe, among others, was invited to bid. Groll thought Wolfe’s bid of $61,000 “was pretty low” and he doubted the job could be accomplished at that price. He understood Wolfe was trying to break into “the field of general contracting” and that this would be his “first job.” He so advised Warfield but Wolfe reassured them that his bid was sound. Wolfe testified he referred to the specifications in arriving at the $61,000 figure but that he paid little or no attention to them because “had [he] gone by the specifications it would have cost much greater to do the job. There is no question about that.” He said that was why he “made sure in the contract” to specify “drawings and not specifications.” (Emphasis added.)

The contract, to be sure, is unusual. Dated 3 July 1967 it is between the Warfields (“Owner”) and Arnold Wolfe, *624 Inc. (“Contractor”). The “Contractor” agreed to “furnish all of the materials and perform all of the work shown in the drawings . . . prepared by” Groll. It is true that the word “specifications” does not appear in the contract but the plans (drawings) contain at least four references to the specifications which, incidentally, were received in evidence without objection.

Wolfe began the construction of the house in mid-July. A week or so later he proposed to Ginsburg that he become a joint entrepreneur. Ginsburg agreed and by the end of August the Articles of Incorporation of Wolfe-Ginsburg Const., Inc., had been filed. What their respective interests were is not disclosed but it is not suggested there were other interested parties. Both Wolfe and Ginsburg participated in the supervision of the job.

Trouble developed soon enough. Early in August it was discovered that some 30 brick piers had been omitted from the basement walls. Groll wrote to Ginsburg on 7 August. What follows is an excerpt from his letter:

“On an inspection on 6 August 1967 of the construction work, it was noted among other items that the brick piers, in every instance as called for on the drawings, were not provided and that wood beams were used in lieu of the steel beams as indicated.
“Had the brick piers been constructed no need for bearing plates would have been necessary. It is directed that the following work be provided for adequate structural support or we are not responsible for any damage which might occur due to your failure to follow the drawings:
“1. Provide 12" X %" X 12" bearing plates under the 12 WF 27 beam in the basement.
“2. Provide the 10 WF 25 beam over Bath No. 2 and Dressing Room as called for with 8" X %" X 11" plates.
“3. Provide the 8 WF 24 beam over the bow *625 window in the living room as called for with 8" X %" X 11" plates.
“4. Provide the 8 WF 17 beam over the dining room opening as called for with 8" X 5/s" X 10" plates.”

Not long thereafter it was discovered that an inferior grade of lumber was being used. On another occasion the absence of other brick piers was discovered. Warfield testified that by mid-November there was an accumulation of “some 60 odd deficiencies.” He said either they had not been corrected, or they had been corrected only as a stopgap. He “had just reached the point where . . . [he] was either going to have to take the house and blow it up and start from scratch or try and salvage what [he] had left.” On 22 November he sent to Wolfe the letter which follows:

“This is to notify you that we hereby declare a general breach on your part of our contract with you dated July 3, 1967 in accordance with plans and specifications drawn by Elkan W. Groll & Associates, date May 1967.
“There have been a number of acts constituting your breach, some of which are:
“1.) Failure to comply structurally with plans such as bearing piers, terra cotta drain tile covered by 12 inches of gravel around footings, ash dump left out of fireplace in basement, all wiring in walls and ceilings to be armored cable.
“2.) Definite attempt to defraud by having contracts with subcontractors to provide lesser substitutes for materials and fixtures than those indicated in plans and specifications, without consultation with, or approval of, owner and architect.
*626 “3.) Causing unnecessary delays, and errors in construction, due to complete lack of supervision during construction.
“Please remove forthwith from the premises known as Spring Lake Farm, 15620 Riding Stable Road, Laurel, Maryland by the following date and time:
“12 o’clock noon, Saturday, November 25, 1967.”

On 10 April 1968 Warfield sued the appellants in the Circuit Court for Montgomery County claiming damages in the amount of $75,000. The appellants in their counterclaim demanded $50,000 damages. After extended discovery activities the case was ordered removed to the Circuit Court for St. Mary’s County where it was tried on 14 and 27 January 1971. We shall deal with the appellants’ contentions in the order in which they appear in their brief.

I.

In his opinion Judge Dorsey referred “to the various and sundry eliminations, substitutions and overall failures to comply with the strict requirements of the specifications which were incorporated by reference to the contract.” (Emphasis added.) Appellants, insisting “[t]here is no scintilla of evidence which would even point to, let alone support” such a conclusion, assign reversible error. This is a bold assertion but it is not plausibly maintained; nor is there a citation of authority in support thereof. The contract required Wolfe to “furnish all of the materials” as well as to “perform all of the work shown on the drawings.” As we have said the drawings, in at least four places, refer to the specifications and it is in the specifications that the complete list of the materials will be found. It can hardly be supposed that Warfield and Groll contemplated a structure in which would be used only Wolfe’s choice of materials. Such an *627

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ortiz Muñoz v. Rivera Martínez
170 P.R. 869 (Supreme Court of Puerto Rico, 2007)
Ortiz Muñoz Y Otros v. Rivera Martínez Y Otros
2007 TSPR 79 (Supreme Court of Puerto Rico, 2007)
Turner v. Turner
809 A.2d 18 (Court of Special Appeals of Maryland, 2002)
Goodman v. Darden, Doman & Stafford Associates
670 P.2d 648 (Washington Supreme Court, 1983)
Goodman v. Darden, Doman & Stafford Associates
653 P.2d 1371 (Court of Appeals of Washington, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
296 A.2d 158, 266 Md. 621, 1972 Md. LEXIS 768, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wolfe-v-warfield-md-1972.