W.M. Schlosser Company, Incorporated v. School Board of Fairfax County, Virginia

980 F.2d 253, 1992 WL 335756
Court of Appeals for the Fourth Circuit·Decided January 13, 1993·No. 92-1008·Published·Cited by 9 cases

Opinion

OPINION

LUTTIG, Circuit Judge:

The W.M. Schlosser Company appeals an order of the district court denying its motions to compel arbitration and to appoint an arbitrator to resolve its construction contract dispute with the School Board of Fairfax County, Virginia. We conclude that regardless of whether the School Board agreed to arbitrate the dispute in question, it .lacked the legal authority to arbitrate under the laws of the Commonwealth of Virginia. We therefore affirm.

I.

The relevant facts necessary to the disposition of this appeal are not in dispute. On June 10, 1988, the W.M. Schlosser Company [Schlosser], a Maryland corporation, entered into a contract with the Fairfax County School Board [the School Board] for the performance of renovation construction at the Falls Church High School. The con *254 tract comprised a number of documents, the most important of which were two standard construction forms prepared by the American Institute of Architects, the AIA Standard Agreement and the AIA General Conditions, and a set of Supplementary Conditions that included extensive modifications to the terms of the AIA standard forms. J.A. at 5-41.

The AIA General Conditions provide for the arbitration of claims arising under the contract. Article 2.2.7 of the General Conditions stipulates that all disputes between contractors and owners must first be referred to the project architect for an initial decision. 1 Id. at 14. Article 2.2.10 states that “[a]ny claim, dispute or other matter that has been referred to the Architect ... shall be subject to arbitration upon the written demand of either party.” Id. Finally, Article 7.10, entitled “ARBITRATION,” provides that all contract disputes shall be arbitrated in accordance with the Construction Industry Arbitration Rules of the AIA and outlines the arbitration process. Id. at 20. In the Supplementary Conditions portion of the contract, Schlos-ser and the School Board left Articles 2.2.7 and 2.2.10 unchanged. Id. at 27. They deleted Article 7.10 of the AIA General Conditions, however, in its entirety. • Id. at 30. 2

Prior to completion of the Falls Church High School project, Schlosser alleged that it had been delayed in the performance of its contract obligations by the School Board, and on August 3, 1990, it served the Board with a claim for damages in the amount of $1,152,941. Schlosser submitted a copy of the claim to the project architect for an initial adjudication, pursuant to Article 2.2.7 of the General Conditions. Id. at 3. Several - months later, the architect granted Schlosser a short extension of the time within which it was required to complete its work, but denied Schlosser’s damages claim. Id. at 75-79.

On March 27, 1991, Schlosser presented the Board with.a written demand for arbitration pursuant to Article 2.2.10 of the General Conditions. The following day, invoking the court’s diversity jurisdiction, Schlosser moved in the district court to compel arbitration and to designate and appoint an arbitrator under the terms of the Federal Arbitration Act [FAA], 9 U.S.C. §§ 1 et seq. Schlosser’s petition was referred to a federal magistrate who, after conducting a hearing, denied both of Schlosser’s motions on the ground inter alia that the School Board lacked the authority to arbitrate under Virginia law and thus that any attempt by the Board to contract to arbitrate was unenforceable. J.A. at 103, 105.

Schlosser appealed the magistrate judge’s decision to the district court. 3 The district court adopted the magistrate’s recommendations, holding that the Board had no authority under Virginia law to arbitrate contract disputes. Id. at 125-26. This appéal followed. 4

II.

A.

The question before the court is whether the School Board possesses the authority under the laws of the Commonwealth of Virginia to agree to arbitrate contractual disputes, for if it does not, then any such *255 agreement by the Board is unenforceable as ultra vires and the motion to compel arbitration therefore must be denied. See Richmond Ry. Co. v. Richmond, Etc., 145 Va. 266, 299, 133 S.E. 888, 898 (1926) (“When the contract is once declared ultra vires, the fact that it is executed does not validate it, nor can it be ratified so as to make it the basis of suit or action, nor does the doctrine of estoppel apply.”); accord Richard L. Deal & Assocs., Inc. v. Commonwealth, 224 Va. 618, 299 S.E.2d 346 (1983). The resolution of this question depends in turn upon application of the Dillon Rule, a rule of construction applicable in Virginia when determining the powers of local government: “There can be no question that Virginia long has followed, and still adheres to, the Dillon Rule of strict construction concerning the powers of local governing bodies.” Commonwealth v. County Bd., 217 Va. 558, 232 S.E.2d 30, 40 (1977). 5

Free access — add to your briefcase to read the full text and ask questions with AI

W.M. Schlosser Company, Incorporated v. School Board of Fairfax County, Virginia, 980 F.2d 253, 1992 WL 335756 (4th Cir. 1993).

980 F.2d 253 (W.M. Schlosser Company, Incorporated v. School Board of Fairfax County, Virginia) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Allsopp v. Bolding, 1100432 (Ala. 9-30-2011)
86 So. 3d 952 (Supreme Court of Alabama, 2011)
District of Columbia v. Greene
806 A.2d 216 (District of Columbia Court of Appeals, 2002)
Southern Constructors, Inc. v. Loudon County Board of Education
58 S.W.3d 706 (Tennessee Supreme Court, 2001)
City of Vista v. Sutro & Co.
52 Cal. App. 4th 401 (California Court of Appeal, 1997)