An unpublished opinion of the North Carolina Court of Appeals does not constitute controlling legal authority. Citation is disfavored, but may be permitted in accordance with the provisions of Rule 30(e)(3) of the North Carolina Rules of Appellate Procedure.
IN THE COURT OF APPEALS OF NORTH CAROLINA
No. COA24-479
Filed 15 April 2026
New Hanover County, No. 23CVS002930-640
W.M. JORDAN COMPANY, INCORPORATED, Plaintiff,
v.
CONCRETE TECHNIQUES AND DESIGN INC., Defendant.
Appeal by Plaintiff from order entered 15 December 2023 by Judge Clinton
Rowe in New Hanover County Superior Court. Heard in the Court of Appeals 5
November 2024.
McAngus, Goudelock & Courie, PLLC, by Jeffrey B. Kuykendal and Walt Rapp, for Plaintiff-Appellant.
Cranfill Sumner LLP, by Steven A. Bader and Daniel G. Katzenbach, for Defendant-Appellee.
CARPENTER, Judge.
W.M. Jordan Company Incorporated (“Plaintiff”) appeals from a trial court’s
decision to grant a motion to dismiss filed by Concrete Techniques and Design Inc.
(“Defendant”). On appeal, Plaintiff argues the trial court erred by: (1) concluding it
had authority to determine that res judicata barred Plaintiff’s complaint; and (2) W.M. JORDAN COMPANY, INC. V. CONCRETE TECHS. AND DESIGN INC.
Opinion of the Court
applying res judicata to dismiss Plaintiff’s complaint. After careful review, we
reverse and remand.
I. Factual & Procedural Background
Plaintiff is a Virginia corporation. Wilmington Hotel Group, LLC (“Owner”) is
an entity comprised of two North Carolina members and five Tennessee members.
On 3 August 2015, Plaintiff and Owner contracted for Plaintiff to serve as a general
contractor for the construction of a hotel in Wilmington, North Carolina. Plaintiff
later subcontracted with Defendant, a North Carolina entity, for Defendant to
provide the hotel’s masonry and brick work, including the exterior cladding. The
subcontract required arbitration of all disputes between Plaintiff and Defendant.
On 13 March 2017, Plaintiff sued Defendant and filed a motion to compel
arbitration for “breach of contract/money owed” and “restitution/quantum
meruit/unjust enrichment.” In its complaint, Plaintiff asserted that Defendant failed
to meet the project’s schedule due to insufficient manpower, lack of production, and
failure to complete assigned tasks in a “good workmanlike manner.” On 4 December
2017, after mediation, Plaintiff and Defendant entered into a memorandum of
settlement, requiring Defendant to pay Plaintiff $40,000 and “dispos[ing] of any and
all claims by either Plaintiff or Defendant, which have been made, or which could
have been made, in this civil action and in the related arbitration.”
On 21 December 2017, the parties jointly negotiated the language of the final
settlement agreement. Plaintiff’s counsel expressed concern that the language in the
-2- W.M. JORDAN COMPANY, INC. V. CONCRETE TECHS. AND DESIGN INC.
agreement “significantly expand[ed] the scope of the release in the mediated
settlement agreement” by including “claim[s] that could accrue in the future.”
Ultimately, the parties agreed to the following release language:
Plaintiff does . . . acquit and forever discharge [Defendant], . . . from any and all claims, actions, causes of action, demands, rights, damages, costs, loss of service, consortium, expenses, and any other form of compensation whatsoever, which [Plaintiff] has made or which [Plaintiff] could have made in the Civil Action and/or related Arbitration.
On 22 December 2017, Plaintiff filed a notice of voluntary dismissal with prejudice.
After a hurricane in 2019, mold issues inside the hotel “came to light.”
Throughout the spring of 2021, Owner investigated the moisture issues and
concluded that poor installation and ineffective quality control of the brick veneer
cladding system caused part of the problem. On 22 June 2022, Owner filed a demand
for arbitration with the American Arbitration Association against Plaintiff, alleging
defects in the hotel that included improper installation of the masonry and brick
portions of the exterior cladding, resulting damage to the interior of the hotel, and
subpar work performed by subcontractors during the original construction.
On 28 August 2023, Plaintiff filed a complaint against Defendant in New
Hanover County Superior Court, asserting breach of contract, breach of express or
implied warranties, contractual indemnity, and negligence in the alternative.
Plaintiff also requested that the trial court stay and refer the matter to arbitration.
Plaintiff argued that the prior settlement did not preclude the current litigation
-3- W.M. JORDAN COMPANY, INC. V. CONCRETE TECHS. AND DESIGN INC.
concerning mold remediation because it “neither knew nor could have known of the
issues related to the masonry work” at the time of the prior settlement.
On 22 September 2023, Defendant filed a motion to dismiss in lieu of answer
under Rule 12(b)(6) of the North Carolina Rules of Civil Procedure, arguing that res
judicata barred the current lawsuit. On 15 December 2023, the trial court granted
Defendant’s motion. Plaintiff timely appealed.
II. Jurisdiction
This Court has jurisdiction under N.C. Gen Stat. § 7A-27(b)(1) (2025).
III. Issues
The issues are whether the trial court erred by: (1) concluding it had authority
to determine that res judicata barred Plaintiff’s complaint; and (2) applying res
judicata to dismiss Plaintiff’s complaint.
IV. Analysis
Plaintiff argues the trial court erred by deciding the issue of res judicata and
subsequently applying res judicata to dismiss Plaintiff’s complaint. Specifically,
Plaintiff contends that the Federal Arbitration Act (“FAA”) requires the arbitrator,
not the trial court, to determine whether res judicata applies. We agree.
A. Preservation
Defendant contends Plaintiff failed to properly preserve its arguments that the
arbitrator should decide res judicata under the FAA and that the North Carolina
Revised Uniform Arbitration Act (“RUAA”) did not govern this dispute. We disagree.
-4- W.M. JORDAN COMPANY, INC. V. CONCRETE TECHS. AND DESIGN INC.
“A party cannot raise on appeal issues which were not pleaded or raised below.”
Bethesda Rd. Partners, LLC v. Strachan, 267 N.C. App. 1, 7, 832 S.E.2d 503, 508
(2019). To preserve an issue for appellate review, “a party must have presented to
the trial court a timely request, objection or motion, stating the specific grounds for
the ruling the party desired the court to make if the specific grounds were not
apparent from the context.” N.C.R. App. P. 10(a)(1) (2025). This rule, however, “does
not require a party to recite certain magic words in order to preserve an issue; rather
it creates a functional requirement of bringing the trial court’s attention to the issue
such that the court may rule on it.” M.E. v. T.J., 380 N.C. 539, 559, 869 S.E.2d 624,
637 (2022) (citing State v. Garcia, 358 N.C. 382, 410, 597 S.E.2d 724 (2004)).
Here, Plaintiff raised the issue of choice of law during the hearing. See
Bethesda Rd. Partners, LLC, 267 N.C. App. at 7, 832 S.E.2d at 508. Specifically,
Plaintiff contended that it was “for the arbitration panel to decide whether or not this
Free access — add to your briefcase to read the full text and ask questions with AI
An unpublished opinion of the North Carolina Court of Appeals does not constitute controlling legal authority. Citation is disfavored, but may be permitted in accordance with the provisions of Rule 30(e)(3) of the North Carolina Rules of Appellate Procedure.
IN THE COURT OF APPEALS OF NORTH CAROLINA
No. COA24-479
Filed 15 April 2026
New Hanover County, No. 23CVS002930-640
W.M. JORDAN COMPANY, INCORPORATED, Plaintiff,
v.
CONCRETE TECHNIQUES AND DESIGN INC., Defendant.
Appeal by Plaintiff from order entered 15 December 2023 by Judge Clinton
Rowe in New Hanover County Superior Court. Heard in the Court of Appeals 5
November 2024.
McAngus, Goudelock & Courie, PLLC, by Jeffrey B. Kuykendal and Walt Rapp, for Plaintiff-Appellant.
Cranfill Sumner LLP, by Steven A. Bader and Daniel G. Katzenbach, for Defendant-Appellee.
CARPENTER, Judge.
W.M. Jordan Company Incorporated (“Plaintiff”) appeals from a trial court’s
decision to grant a motion to dismiss filed by Concrete Techniques and Design Inc.
(“Defendant”). On appeal, Plaintiff argues the trial court erred by: (1) concluding it
had authority to determine that res judicata barred Plaintiff’s complaint; and (2) W.M. JORDAN COMPANY, INC. V. CONCRETE TECHS. AND DESIGN INC.
Opinion of the Court
applying res judicata to dismiss Plaintiff’s complaint. After careful review, we
reverse and remand.
I. Factual & Procedural Background
Plaintiff is a Virginia corporation. Wilmington Hotel Group, LLC (“Owner”) is
an entity comprised of two North Carolina members and five Tennessee members.
On 3 August 2015, Plaintiff and Owner contracted for Plaintiff to serve as a general
contractor for the construction of a hotel in Wilmington, North Carolina. Plaintiff
later subcontracted with Defendant, a North Carolina entity, for Defendant to
provide the hotel’s masonry and brick work, including the exterior cladding. The
subcontract required arbitration of all disputes between Plaintiff and Defendant.
On 13 March 2017, Plaintiff sued Defendant and filed a motion to compel
arbitration for “breach of contract/money owed” and “restitution/quantum
meruit/unjust enrichment.” In its complaint, Plaintiff asserted that Defendant failed
to meet the project’s schedule due to insufficient manpower, lack of production, and
failure to complete assigned tasks in a “good workmanlike manner.” On 4 December
2017, after mediation, Plaintiff and Defendant entered into a memorandum of
settlement, requiring Defendant to pay Plaintiff $40,000 and “dispos[ing] of any and
all claims by either Plaintiff or Defendant, which have been made, or which could
have been made, in this civil action and in the related arbitration.”
On 21 December 2017, the parties jointly negotiated the language of the final
settlement agreement. Plaintiff’s counsel expressed concern that the language in the
-2- W.M. JORDAN COMPANY, INC. V. CONCRETE TECHS. AND DESIGN INC.
agreement “significantly expand[ed] the scope of the release in the mediated
settlement agreement” by including “claim[s] that could accrue in the future.”
Ultimately, the parties agreed to the following release language:
Plaintiff does . . . acquit and forever discharge [Defendant], . . . from any and all claims, actions, causes of action, demands, rights, damages, costs, loss of service, consortium, expenses, and any other form of compensation whatsoever, which [Plaintiff] has made or which [Plaintiff] could have made in the Civil Action and/or related Arbitration.
On 22 December 2017, Plaintiff filed a notice of voluntary dismissal with prejudice.
After a hurricane in 2019, mold issues inside the hotel “came to light.”
Throughout the spring of 2021, Owner investigated the moisture issues and
concluded that poor installation and ineffective quality control of the brick veneer
cladding system caused part of the problem. On 22 June 2022, Owner filed a demand
for arbitration with the American Arbitration Association against Plaintiff, alleging
defects in the hotel that included improper installation of the masonry and brick
portions of the exterior cladding, resulting damage to the interior of the hotel, and
subpar work performed by subcontractors during the original construction.
On 28 August 2023, Plaintiff filed a complaint against Defendant in New
Hanover County Superior Court, asserting breach of contract, breach of express or
implied warranties, contractual indemnity, and negligence in the alternative.
Plaintiff also requested that the trial court stay and refer the matter to arbitration.
Plaintiff argued that the prior settlement did not preclude the current litigation
-3- W.M. JORDAN COMPANY, INC. V. CONCRETE TECHS. AND DESIGN INC.
concerning mold remediation because it “neither knew nor could have known of the
issues related to the masonry work” at the time of the prior settlement.
On 22 September 2023, Defendant filed a motion to dismiss in lieu of answer
under Rule 12(b)(6) of the North Carolina Rules of Civil Procedure, arguing that res
judicata barred the current lawsuit. On 15 December 2023, the trial court granted
Defendant’s motion. Plaintiff timely appealed.
II. Jurisdiction
This Court has jurisdiction under N.C. Gen Stat. § 7A-27(b)(1) (2025).
III. Issues
The issues are whether the trial court erred by: (1) concluding it had authority
to determine that res judicata barred Plaintiff’s complaint; and (2) applying res
judicata to dismiss Plaintiff’s complaint.
IV. Analysis
Plaintiff argues the trial court erred by deciding the issue of res judicata and
subsequently applying res judicata to dismiss Plaintiff’s complaint. Specifically,
Plaintiff contends that the Federal Arbitration Act (“FAA”) requires the arbitrator,
not the trial court, to determine whether res judicata applies. We agree.
A. Preservation
Defendant contends Plaintiff failed to properly preserve its arguments that the
arbitrator should decide res judicata under the FAA and that the North Carolina
Revised Uniform Arbitration Act (“RUAA”) did not govern this dispute. We disagree.
-4- W.M. JORDAN COMPANY, INC. V. CONCRETE TECHS. AND DESIGN INC.
“A party cannot raise on appeal issues which were not pleaded or raised below.”
Bethesda Rd. Partners, LLC v. Strachan, 267 N.C. App. 1, 7, 832 S.E.2d 503, 508
(2019). To preserve an issue for appellate review, “a party must have presented to
the trial court a timely request, objection or motion, stating the specific grounds for
the ruling the party desired the court to make if the specific grounds were not
apparent from the context.” N.C.R. App. P. 10(a)(1) (2025). This rule, however, “does
not require a party to recite certain magic words in order to preserve an issue; rather
it creates a functional requirement of bringing the trial court’s attention to the issue
such that the court may rule on it.” M.E. v. T.J., 380 N.C. 539, 559, 869 S.E.2d 624,
637 (2022) (citing State v. Garcia, 358 N.C. 382, 410, 597 S.E.2d 724 (2004)).
Here, Plaintiff raised the issue of choice of law during the hearing. See
Bethesda Rd. Partners, LLC, 267 N.C. App. at 7, 832 S.E.2d at 508. Specifically,
Plaintiff contended that it was “for the arbitration panel to decide whether or not this
contractual indemnity claim that wasn’t pursued before, that wasn’t part of the
lawsuit that was dismissed, should be barred . . . .” Despite not using the “magic
words” FAA, RUAA, or res judicata, Plaintiff brought the issue to the trial court’s
attention. See M.E., 380 N.C. at 539, 869 S.E.2d at 637. Accordingly, whether the
trial court had authority to decide res judicata is preserved for appellate review. See
N.C.R. App. P. 10(a)(1).
B. Choice of Law
We review de novo a trial court’s decision to grant a motion to dismiss. See
-5- W.M. JORDAN COMPANY, INC. V. CONCRETE TECHS. AND DESIGN INC.
Allred v. Cap. Area Soccer League, Inc., 194 N.C. App. 280, 283, 669 S.E.2d 777, 779
(2008). “ ‘Under a de novo review, the court considers the matter anew and freely
substitutes its own judgment’ for that of the lower tribunal.” State v. Williams, 362
N.C. 628, 632–33, 669 S.E.2d 290, 294 (2008) (quoting In re Greens of Pine Glen Ltd.
P’ship, 356 N.C. 642, 647, 576 S.E.2d 316, 319 (2003)).
Res judicata “ ‘applies to a judgment entered on an arbitration award as it does
to any other final judgment.’ ” Moody v. Able Outdoor, Inc., 169 N.C. App. 80, 85, 609
S.E.2d 259, 262 (2005) (quoting Rodgers Builders, Inc. v. McQueen, 76 N.C. App. 16,
22, 331 S.E.2d 726, 730 (1985)). For res judicata to bar an arbitration claim, a party
“must show (1) a final judgment on the merits in an earlier suit, (2) an identity of the
cause of action in both the earlier and the later suit, and (3) an identity of parties or
their privies in the two suits.” Erler v. Aon Risks Servs., Inc., 141 N.C. App. 312, 316,
540 S.E.2d 65, 68 (2000).
We first consider whether the trial court or an arbitrator should decide the
issue of res judicata. In other words, “[a] threshold question . . . is whether the [FAA]
or the [RUAA] governs the instant case.” WMS, Inc. v. Alltel Corp., 185 N.C. App. 86,
90, 647 S.E.2d 623, 626 (2007). That is because the FAA, which mandates that the
arbitrator decide the issue of res judicata, see id. at 93, 647 S.E.2d at 628, preempts
conflicting state law like the RUAA, which permits the trial court to decide the issue
of res judicata, compare 9 U.S.C. § 3 (2018), with N.C. Gen. Stat. § 1-569.5(a) (2025).
The FAA governs “[a] written provision in any . . . contract evidencing a
-6- W.M. JORDAN COMPANY, INC. V. CONCRETE TECHS. AND DESIGN INC.
transaction involving commerce,” 9 U.S.C § 2 (2018), between states and over
admiralty, Prima Paint Corp v. Flood & Conklin Mfg. Co., 388 U.S. 395, 405, 87 S.
Ct. 1801, 1807, 18 L. Ed. 2d 1270, 1278 (1967). The United States Supreme Court
has interpreted the statute’s language “broadly” in an effort “to exercise Congress’
commerce power to the full.” Allied-Bruce Terminix Cos., Inc. v. Dobson, 513 U.S.
265, 277, 115 S. Ct. 834, 841, 130 L. Ed. 2d 753, 766 (1995); see also Perry v. Thomas,
482 U.S. 483, 491, 107 S. Ct. 2520, 2526, 96 L. Ed. 2d 426, 436 (1987) (describing the
FAA as “a statute that embodies Congress’ intent to provide for the enforcement of
arbitration agreements within the full reach of the Commerce Clause”).
Indeed, the United States Supreme Court expressly overruled a narrower
interpretation of the FAA, concluding that the statute applies to any transaction that
“in fact involv[es] interstate commerce, even if the parties did not contemplate an
interstate commerce connection.” Allied-Bruce Terminix Cos. Inc., 513 U.S. at 281,
115 S. Ct. at 843, 130 L. Ed. 2d at 769, overruling Burke Cnty. Public Schs. Bd. of
Educ. v. Shaver P’ship., 303 N.C. 408, 418, 279 S.E.2d 816, 822 (1981). For example,
a transaction involves interstate commerce if the companies are from different states,
see id. at 282, 115 S. Ct. at 843, 130 L. Ed. 2d at 769, or intrastate activities “which
might have a substantial and harmful effect” on interstate commerce, see Heart of
Atlanta Motel v. United States, 379 U.S. 241, 258, 261, 85 S. Ct. 348, 358, 360, 13 L.
Ed. 2d 258, 269, 271 (1964) (“Congress may—as it has—prohibit racial discrimination
by motels serving travelers, however ‘local’ their operations may appear.”).
-7- W.M. JORDAN COMPANY, INC. V. CONCRETE TECHS. AND DESIGN INC.
Here, the transaction involved interstate commerce. See Allied-Bruce
Terminix Cos. Inc., 513 U.S. at 282, 115 S. Ct. at 843, 130 L. Ed. 2d at 769. First, the
companies were from different states: Plaintiff from Virginia, Defendant from North
Carolina, and Owner with members from North Carolina and Tennessee. See id. at
282, 115 S. Ct. at 843, 130 L. Ed. 2d at 769. {Def Br p 11} Second, the transaction
involved a local hotel serving interstate travelers. See Heart of Atlanta, 379 U.S. at
258, 261, 85 S. Ct. at 358, 360, 13 L. Ed. 2d at 269, 271. The construction project,
therefore, implicated the FAA’s broad coverage. See 9 U.S.C § 2; see also Allied-Bruce
Terminix Cos. Inc., 513 U.S. at 281, 115 S. Ct. at 843, 130 L. Ed. 2d at 769.
Accordingly, we conclude that the FAA controls this dispute. See WMS, Inc.,
185 N.C. App. at 93, 647 S.E.2d at 628. Because the FAA applies, the arbitrator, not
the trial court, should have decided the application of res judicata. See id. at 93, 647
S.E.2d at 628. The trial court, therefore, erred in granting Defendant’s motion to
dismiss on res judicata grounds. See id. at 93, 647 S.E.2d at 628. Because the trial
court’s error in deciding res judicata is dispositive, we do not reach the issue of
whether the trial court properly applied res judicata.
V. Conclusion
Where the FAA applies, an arbitrator must initially decide the viability of a
res judicata defense. Accordingly, the trial court erred in granting Defendant’s Rule
12(b)(6) motion to dismiss. We reverse the trial court’s dismissal with instructions to
refer the matter to arbitration, and we do not reach the issue of whether the trial
-8- W.M. JORDAN COMPANY, INC. V. CONCRETE TECHS. AND DESIGN INC.
court properly applied res judicata in this case.
REVERSED AND REMANDED.
Judges STROUD and STADING concur.
Report per Rule 30(e).
-9-