W.L. Goodfellows & Co. of Turnersville, Inc. v. Washington Township Planning Board

783 A.2d 750, 345 N.J. Super. 109, 2001 N.J. Super. LEXIS 416
CourtNew Jersey Superior Court Appellate Division
DecidedNovember 14, 2001
StatusPublished
Cited by13 cases

This text of 783 A.2d 750 (W.L. Goodfellows & Co. of Turnersville, Inc. v. Washington Township Planning Board) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W.L. Goodfellows & Co. of Turnersville, Inc. v. Washington Township Planning Board, 783 A.2d 750, 345 N.J. Super. 109, 2001 N.J. Super. LEXIS 416 (N.J. Ct. App. 2001).

Opinion

The opinion of the court was delivered by

LINTNER, J.A.D.

On December 15, 1998, defendant, Washington Township Planning Board (Board), denied the application of plaintiff, W.L. Goodfellows and Company of Turnerville, Inc., for preliminary site plan approval, based upon plaintiffs failure to demonstrate that it [112]*112had secured a drainage easement that comported with the plaintiffs own plan, and its conclusion that plaintiff did not demonstrate sufficiently that the health, safety and welfare of the surrounding properties would not be adversely affected. Plaintiffs plan incorporated a retention basin within the property’s fifty-foot landscape buffer area and a drainage easement to accommodate and carry excess stormwater across the adjoining property and into a stormwater runoff system located on Ledon Lane. The Board denied the application, notwithstanding plaintiffs representations to the Board that it was in the process of negotiating with its neighbor to procure the easement.

Plaintiff filed its complaint in lieu of prerogative writ in December 1998, seeking to overturn the decision of the Board and for damages for violation of its rights under 42 U.S.C. §§ 1983 and 1988. On March 16, 1999, plaintiff purportedly entered into an agreement with the adjoining property owners for the required drainage easement. On July 9, 1999, the Law Division judge denied plaintiffs motion for summary judgment by which plaintiff sought: (1) a grant of its application for preliminary site plan approval; (2) retention of jurisdiction; and (3) a plenary hearing on plaintiffs entitlement to monetary damages on its constitutional claims. The judge then encouraged the Board to file a motion for summary judgment, which he thereafter granted by order of August 20, 1999, dismissing plaintiffs complaint.1 Plaintiff filed a notice of appeal which we dismissed as interlocutory on September 14, 2000 because there remained, unresolved, a counterclaim by the Board for fees and expenses related to its review of plaintiffs application. The parties thereafter entered into a settlement of the Board’s counterclaim and this appeal followed. During the [113]*113pendency of this appeal, the Township of Washington, which is not a party to the within action, passed an ordinance prohibiting the existence of storm drainage facilities, including retention basins, within the fifty-foot landscape area.

On appeal plaintiff contends that the Board’s denial of its application violated the provisions of N.J.S.A. 40:55D-46 and the judge erred in dismissing plaintiffs claims for damages for alleged violations of its constitutional rights. We reverse the motion judge’s denial of plaintiffs motion for summary judgment and hold that, on the record before the Board, the preliminary site plan should have been granted subject to the procurement of the proposed drainage easement. The Board should determine whether plaintiffs easement comports with plaintiffs plan. We also hold that, consistent with general principles of equity and application of the time of decision rule, the provisions of N.J.S.A. 40:55D-49 should be applied and plaintiff should be afforded the benefit of the statutory protection against a change in use requirements, as if preliminary site plan approval had been granted. In light of our holding, we also reverse the motion judge’s entry of summary judgment dismissing plaintiffs complaint and remand to the Law Division for further proceedings on plaintiffs claim for alleged violations of 42 U.S.C. §§ 1983 and 1988.

The following are the facts relevant to this appeal. Plaintiff, as contract purchaser of property located in Washington Township, Gloucester County, made an application to the Board for preliminary site plan approval for the development of a restaurant. It is undisputed that plaintiffs application, as modified, did not require any variances. It was also deemed complete and satisfied all submission requirements. The application was discussed at three public hearings which were held by the Board on September 15, October 20 and November 24, 1998. At the final hearing the Board’s Planner advised that the drainage plan had been revised to include an overflow drainage pipe across the lot owned by Arthur and Veronica Willet to Ledon Lane. The Planner also testified that a recorded drainage easement document should be [114]*114submitted for review and should contain “a tree protection plan to protect the existing tree line between lots 5.03 and 6.” At the same hearing, the Board’s Engineer, Brian Peterman, was asked:

BOARD MEMBER: You’ve reviewed the whole drainage plan for this area?
MR. PETERMAN: Yes.
BOARD MEMBER: Do you feel confident that it can support this additional facility that it will work?
MR. PETERMAN: Yes. The calculations provided to us show that this will work. It’s not the preferred system because it’s a retention as opposed to detention but it is permissible under the Township ordinance.

At the hearing on September 15, plaintiffs counsel advised the Board that he and plaintiff had discussions with Willet regarding the drainage easement, that it was “not a done deal,” and that the discussions were not concluded. The Board’s resolution denying plaintiffs application expresses the following specific reason for its action:

The applicant failed to demonstrate by way of credible evidence that it had secured a drainage easement which comported with its plans submitted and which would be required in order to demonstrate to the Board a properly functioning and safe detention basin for the proposed site.

In rejecting plaintiffs motion for summary judgment, the motion judge enunciated the following findings at commencement of argument:

Washington Township should have brought a motion for summary judgment, too, because I would have granted their motion, cause I’m going to deny [plaintiffs], because when a planning board says where’s your plan to take care of the run-off, and you say we’re still negotiating the easement to carry the excess water ... you got to give — you got to show them you got the easement.
You don’t have the easement. It’s one little point, but it’s enough to turn you down and they made it____ You got the easement the next day? Too late.

Counsel for the Board agreed with the judge’s conclusions, saying:

The engineer was asked about whether or not this design system worked because of all the surrounding neighbors having great concerns about flooding in the area, et cetera, and Mr. Peterman indicated that he believed that the system that was on the paper would work.
The system that was on the paper that was there was a plan submitted by the applicant that had an outfall structure for the drainage.
[115]*115There was no indication that this easement was in place, and it was on that basis as set forth in the resolution ... which clearly sets forth the basis of the denial was the lack of the drainage easement.

The judge concluded:

I’m going to deny your motion because on the record and on the papers I can’t grant you summary judgment because you said you were getting an easement for the outfall pipe. You didn’t have it and they turned you down because of it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michael Sciore v. the Planning Board of Logan Township
New Jersey Superior Court App Division, 2026
In the Matter of the Application of the Township of Wayne
New Jersey Superior Court App Division, 2025
Randolph v. City of Brigantine Planning Board
963 A.2d 1224 (New Jersey Superior Court App Division, 2009)
Randolph v. City of Brigantine Planning Bd.
963 A.2d 1224 (New Jersey Superior Court App Division, 2009)
Dowel Associates v. Harmony Tp. Land Use Bd.
956 A.2d 349 (New Jersey Superior Court App Division, 2008)
Meridian Quality Care, Inc. v. BD. OF ADJUST.
810 A.2d 571 (New Jersey Superior Court App Division, 2002)
Sartoga v. Borough of W. Paterson
788 A.2d 841 (New Jersey Superior Court App Division, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
783 A.2d 750, 345 N.J. Super. 109, 2001 N.J. Super. LEXIS 416, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wl-goodfellows-co-of-turnersville-inc-v-washington-township-njsuperctappdiv-2001.