Chiplin Enterprises, Inc. v. City of Lebanon

712 F.2d 1524, 1983 U.S. App. LEXIS 25273
CourtCourt of Appeals for the First Circuit
DecidedAugust 1, 1983
Docket83-1062
StatusPublished
Cited by124 cases

This text of 712 F.2d 1524 (Chiplin Enterprises, Inc. v. City of Lebanon) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chiplin Enterprises, Inc. v. City of Lebanon, 712 F.2d 1524, 1983 U.S. App. LEXIS 25273 (1st Cir. 1983).

Opinion

LEVIN H. CAMPBELL, Chief Judge.

Plaintiff-appellant Chiplin Enterprises, Inc. (“Chiplin”) built, operates, and collects rents from a 24-unit apartment complex in Lebanon, New Hampshire. The building permit for the project was granted only after five years of negotiations with local authorities and a trip through the New Hampshire courts. Once it had the permit in hand, Chiplin brought the present suit in the United States District Court for the District of New Hampshire. It sought $2,000,000 in damages for “violation of plaintiff’s civil and constitutional rights” by the city of Lebanon, its building inspector, and the members of its planning board. After a brief hearing, the district court concluded that it lacked jurisdiction and granted the defendants’ motion to dismiss. 1 We affirm.

I.

The background of this suit is not disputed. Appellant first sought a building permit from the city’s building inspector in the fall of 1976. It was informed that the project required the approval of the Lebanon Planning Board, pursuant to section 504 of the city zoning ordinance, which called for “site plan review” by the board of any project that could have a “substantial impact” on the area. The board granted preliminary approval, but denied the permit after a public hearing, noting possibly severe traffic problems. On January 31, 1977, Chiplin submitted a modified propos *1526 al; this too was rejected after a public hearing. Chiplin then sought review in the New Hampshire Superior Court. See N.H. Rev.Stat.Ann. § 36:34. A hearing was held in May 1978, and on April 19, 1979, the court affirmed the board’s denial of a permit. 2

Chiplin appealed to the state Supreme Court. It argued, as it had below, that section 504 exceeded the scope of the state enabling legislation on which it was based, and that the board therefore had no power to review its plans. In an opinion issued February 14,1980, the New Hampshire Supreme Court agreed. It held that because the enabling legislation authorized planning board review of nonresidential uses only, it could not support review of Chiplin’s project. The enabling legislation had by that time been amended to grant planning boards explicit authority to review site plans for “multi-family dwelling units.” The court found, however, that the amendment came too late to help the city in this case. It remanded the case to the Superior Court.

Meanwhile, Lebanon had repealed section 504 and adopted a new zoning ordinance and master plan. Under the plan, Chiplin’s proposed complex was not permissible. The Superior Court ordered an interlocutory appeal concerning the effect of the new master plan, which the Supreme Court denied in August of 1980. The case was then reheard by the Superior Court, which found, in January 1981, that the project fell within a grandfather clause in the new master plan, and that the amendment to the enabling legislation did not retroactively salvage planning board review. A permit was finally issued on November 12, 1981; work began the following spring; and the apartments were completed in October of 1982.

II.

Chiplin filéd this section 1983 action in April 1982 seeking damages for the five-year delay between its initial application and the grant of the permit. The alleged constitutional violation is not the lengthy delay as such, however. Rather, under appellant’s theory, it is the denial itself that is actionable. The ensuing delay only established the extent of damage; it did not cause it. Had the delay been one year rather than five, or even, in theory, one day, the claim would be no weaker although damages would be much less.

Chiplin asserts that as it had met all legal requirements for the permit, the town had no valid reason to reject the application. It then aims in the general direction of the federal Constitution with buckshot, stating that this improper denial of a permit “unlawfully restricted and interfered with plaintiff’s use and enjoyment of its property,” “interfered with plaintiff’s prospective economic gain,” denied it the equal protection of the law, and took its property without due processor just compensation. As described in its brief to us, the “gravamen of plaintiff’s complaint is that the individuals named as defendants denied the plaintiff due process by maliciously denying it a building permit for invalid and illegal reasons and in bad faith.”

III.

Even taking the factual allegations of the complaint to be true, we do not think Chiplin has made out a federal claim. 3 The Supreme Court has frequently noted the two essential elements of a cause of action under 42 U.S.C. § 1983: 1) that the conduct complained of was carried out under color of state law, and 2) that this conduct de *1527 prived the plaintiff of rights, privileges, or immunities secured by the Constitution or laws of the United States. E.g., Parratt v. Taylor, 451 U.S. 527, 535, 101 S.Ct. 1908, 1912, 68 L.Ed.2d 420 (1981). The first requirement is met here. It is more difficult, however, to identify a constitutional right of which Chiplin has been deprived.

Chiplin’s claim is essentially identical to that rejected in Creative Environments, Inc. v. Estabrook, 680 F.2d 822 (1st Cir.1981), cert. denied,- U.S. -, 103 S.Ct. 345, 74 L.Ed.2d 385 (1982). The plaintiff in that case, “CEI,” was a real estate developer whose plan for a housing development had been rejected by the local planning board. Like Chiplin, CEI alleged that the plan had been improperly rejected, this “arbitrary misapplication of state law resulting ... in denying them their ‘right’ to conduct a legitimate business and make a profit.” Id. at 831. We were willing to “assume that CEI ... could have established at trial that the town engaged in adversarial and even arbitrary tactics with regard to the CEI plan.” Id. at 829. Nonetheless, we held that CEI did not allege a constitutional violation. “[Pjroperty is not denied without due process simply because a local planning board rejects a proposed development for erroneous reasons or makes demands which arguably exceed its authority under the relevant state statutes.” Id. at 832 n. 9. We saw nothing in that controversy to “distinguish it sufficiently from the usual land developer’s claim under state law to warrant recognition of a federal constitutional question,” id. at 833, and we see nothing here.

Chiplin asserts that what it sees as the appellees’ flouting of state law — their refusal to issue a permit “even though all reasonable requirements had been met”— provides a basis for a section 1983 action. Yet it is axiomatic that not every violation of a state statute amounts to an infringement of constitutional rights. Paul v. Davis, 424 U.S. 693, 700, 96 S.Ct. 1155,1160, 47 L.Ed.2d 405 (1976).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maroney v. Fiorentini
D. Massachusetts, 2023
Roe v. Lynch
997 F.3d 80 (First Circuit, 2021)
Property v. Town of Derry, et al.
2008 DNH 200 (D. New Hampshire, 2008)
Henry Co. Homes, Inc. v. Curb
548 F. Supp. 2d 1281 (N.D. Florida, 2008)
Jackson v. Russo
495 F. Supp. 2d 225 (D. Massachusetts, 2007)
Bourne v. Town of Madison
494 F. Supp. 2d 80 (D. New Hampshire, 2007)
Lafortune v. City of Biddeford
142 F. App'x 471 (First Circuit, 2005)
Diva's, Inc. v. Bangor, City of
411 F.3d 30 (First Circuit, 2005)
Matney v. City of North Adams
359 F. Supp. 2d 20 (D. Massachusetts, 2005)
Hernandez-Santiago v. Ecolab, Inc.
397 F.3d 30 (First Circuit, 2005)
Lindquist v. Buckingham Township
106 F. App'x 768 (Third Circuit, 2004)
Aegis of Arizona, L.L.C. v. Town of Marana
81 P.3d 1016 (Court of Appeals of Arizona, 2003)
The Town of Marana v. Aegis of Arizona, LLC.
Court of Appeals of Arizona, 2003
Patterson v. American Fork City
2003 UT 7 (Utah Supreme Court, 2003)
Daddario v. Cape Cod Commission
780 N.E.2d 124 (Massachusetts Appeals Court, 2002)
Macone v. Wakefield, Town of
First Circuit, 2002
Aguilera v. Kirkpatrick
241 F.3d 1286 (Tenth Circuit, 2001)
Welch v. Paicos
66 F. Supp. 2d 138 (D. Massachusetts, 1999)
El Dia, Inc. v. Rossello
30 F. Supp. 2d 160 (D. Puerto Rico, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
712 F.2d 1524, 1983 U.S. App. LEXIS 25273, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chiplin-enterprises-inc-v-city-of-lebanon-ca1-1983.