Wiseco, Inc. v. Johnson Controls, Inc.

155 F. App'x 815
CourtCourt of Appeals for the Sixth Circuit
DecidedNovember 4, 2005
Docket04-6200
StatusUnpublished
Cited by3 cases

This text of 155 F. App'x 815 (Wiseco, Inc. v. Johnson Controls, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wiseco, Inc. v. Johnson Controls, Inc., 155 F. App'x 815 (6th Cir. 2005).

Opinion

SUTTON, Circuit Judge.

Wiseco, Inc., a Kentucky-based tool-and-die company, seeks review of a ruling summarily rejecting its claim that Johnson Controls, Inc.(JCI) breached a requirements contract between the two companies. Because Wiseco has failed to establish a material fact dispute that JCI acted in bad faith in reducing its requirements under the contract, we affirm.

I.

In 1998, JCI produced metal headrest stays for several DaimlerChrysler vehicles. In December of that year, an employee at *816 JCI’s Foamech plant in Georgetown, Kentucky sought to out-source two aspects of the stay-manufacturing operation to Wise-co: bending the metal rods into a staple shape and chamfering (rounding) the ends. The parties agreed orally that Wiseco would prepare the necessary tooling for the job at its own expense and that it would receive 50$ per part with a manufacturing capacity of approximately 4000 parts per day (with actual requirements to be set by DaimlerChrysler’s needs). JCI also informed Wiseco that the life of the part was at least four years, which Wiseco took to be the expected term of the contract. Using manufacturing plans for the part provided by JCI, Wiseco “tooled-up” for the production, which is to say it bought and prepared equipment to handle the manufacturing work, and for six months produced approximately 4000 parts per day, which were then sent to the Foamech plant for finishing (notching and applying protective coating) before being shipped to JCI’s Tillsonberg, Canada plant for assembly into finished headrests.

About six months after beginning production, JCI told Wiseco that it soon would be terminating orders of part 684F, as the part Wiseco had been producing was called — and indeed over the next six months JCI’s requirements for the part decreased substantially. At the same time, however, JCI asked Wiseco to take over the finishing functions for part 684F, formerly performed by JCI at its Foamech plant, so that not only would Wiseco bend and chamfer the rods, it also would notch and finish them, creating a finished part referred to as 684B. While JCI’s orders to Wiseco for part 684B were well under 4000 parts per day, the company paid Wiseco more for its additional work.

According to JCI, the decline in its requirements for parts 684F and 684B stemmed from changes at DaimlerChrysler. Originally part 684F was used in DaimlerChrysler’s 1999 Cherokee and 1999 Grand Cherokee models. The part was not used in the 2000 Grand Cherokee and subsequent models, but part 684B was used in the 2000 and 2001 Cherokee. DaimlerChrysler retired the Cherokee after the 2001 model year.

The newer Grand Cherokee’s headrest used part 611, a metal rod that is 40 millimeters longer than part 684, has two additional notches and is chamfered to pointed rather than rounded ends. Part 611 was made by Guelph Tool and Die, a company located near the Tillsonberg, Canada plant where the headrests were finally assembled.

On May 14, 2001, Wiseco sued JCI in Kentucky state court for breach of the 684 contract as well as claims relating to several other parts that Wiseco manufactured for JCI. JCI removed the case to federal court based on diversity jurisdiction. After numerous thrusts and parries over a proposed preliminary injunction designed to prevent JCI from pulling other business from Wiseco (denied) and after extensive discovery on all of the claims, Wiseco voluntarily dismissed with prejudice all but its 684F contract claim on October 3, 2003. Initially, with respect to that claim, the district court granted partial summary judgment for Wiseco, ruling that JCI and Wiseco had formed an oral requirements contract under KRS § 355.2-306(1) for the production of part 684F that was ratified, but not controlled, by subsequent purchase orders. At some point after this ruling, Wiseco made several requests for additional discovery to determine whether JCI was buying parts from other suppliers that were “substantially” the same as part 684. The district court allowed further discovery and a further deposition but limited it to “the headrest assembled at the Foamech plant.” Dist. Ct. Op. at 3. On Aug 31, 2004, the District Court granted sum *817 mary judgment to JCI. In doing so, it concluded that “JCI purchased all of its requirements for part 684 from Wiseco and did not breach the contract in this regard” and that because there was no proof that any replacement part was ever used in “any headrest assembled in the Foamech plant,” the undisputed evidence showed that JCI had reduced its requirements in good faith. Dist. Ct. Op. at 18.

II.

We review a district court’s grant of summary judgment de novo. Beecham v. Henderson County, 422 F.3d 372 (6th Cir. 2005). Summary judgment should be granted where the party tasked with the burden of proof at trial fails to establish a factual dispute about the existence of an element essential to its case. Id. at 374.

As with many contract disputes, this one would not have fueled such long and costly litigation had the parties adequately memorialized their intentions. Despite that failing, the district court concluded that the parties’ oral agreement was effectively removed from the statute of frauds and became a valid requirements contract through JCI’s purchase orders, notwithstanding the conflicting terms of those later writings. The U.C.C.’s statute-of-frauds provision appears to demand little of the writing that confirms an oral “agreement.” See § 355.2-201(1); 1 Official Comments to U.C.C. § 2-201; O’Sullivan v. Duro-Last, Inc., 7 Fed.Appx. 509 (6th Cir.2001) (concluding that a letter following an oral agreement, even though nonconforming, removed the agreement from the statute of frauds); C. Itoh & Co. v. Jordan Int'l Co., 552 F.2d 1228, 1233 (7th Cir.1977) (noting that it is easier to remove an oral agreement from the statute of frauds than to modify it under the U.C.C.). While JCI challenges the enforceability of this oral agreement as an alternative ground for affirmance here, it does so solely on the ground that its purchase orders constitute the whole contract between the parties, despite the fact that the purchase orders, in order to be binding, explicitly require Wiseco’s signature and Wiseco never signed the orders. Given the dearth of attention paid to this matter in the appellate briefs and given the reality that the existence of the contract does not change the outcome of the case, we will accept (for purposes of argument) the district court’s ruling on this point.

That leaves the issue we will resolve: Did JCI’s significant reduction in its requirements for part 684 six months after production began breach this requirements contract? Under the U.C.C., as adopted in Kentucky and as adopted in almost every jurisdiction, a requirements contract demands that the buyer order from the seller “such actual output or requirements as may occur in good faith, except that no quantity unreasonably disproportionate to any stated estimate ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
155 F. App'x 815, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wiseco-inc-v-johnson-controls-inc-ca6-2005.