Tate v. Boeing Helicopters

140 F.3d 654, 1998 U.S. App. LEXIS 6589, 1998 WL 148469
CourtCourt of Appeals for the Sixth Circuit
DecidedApril 2, 1998
DocketNo. 96-5502
StatusPublished
Cited by24 cases

This text of 140 F.3d 654 (Tate v. Boeing Helicopters) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tate v. Boeing Helicopters, 140 F.3d 654, 1998 U.S. App. LEXIS 6589, 1998 WL 148469 (6th Cir. 1998).

Opinion

[656]*656OPINION

GIBSON, Circuit Judge.

The claims arising from the crash of a CH-47D Chinook military helicopter during a July 24, 1990, training mission at Fort Campbell, Kentucky are before us again. The district court1 entered summary judgment on the failure to warn claims asserted by a soldier injured in the crash and the family members of three of the soldiers killed in the crash. The district court held that the government contractor defense established in Boyle v. United, Technologies Corp., 487 U.S. 500, 108 S.Ct. 2510, 101 L.Ed.2d 442 (1988), and this court’s earlier opinion in this case, Tate v. Boeing Helicopters, 55 F.3d 1150 (6th Cir.1995), compelled the entry of summary judgment for the defendant. We affirm the judgment of the district court.

The crew of five on the Chinook helicopter were conducting a night vision goggle training mission involving the transport of a 15,-760 pound concrete block. The helicopter was traveling at approximately fifty knots just before the crash, with the concrete block suspended below the aircraft. Nancy Schultz, who was piloting, told the accident board afterward that she repeatedly activated the cargo hook mechanism but did not know if she had successfully released the block. The block was dragged along the ground eighty-five feet before it was released, and the aircraft struck the ground some 314 feet beyond where the concrete block came to rest. The facts have been stated in considerable detail in this court’s earlier opinion, and we need not develop the factual background further, except as necessary to analyze the appellants’ arguments.

The district court initially granted summary judgment in favor of Boeing and Breeze Eastern on all claims and dismissed the case. This court affirmed the summary judgment on the design defect claim in Tate I, 55 F.3d at 1156-58, but vacated and remanded on the failure to warn claim, holding that the district court had not addressed this claim. We observed that other circuits have applied the government contractor defense against the failure to warn claims, but in doing so did not focus on the underlying design defect but instead upon the warnings. “Warning the government of dangers arising from its specific design ... does not encompass or state a failure to warn claim; it simply encourages contractors to provide the government with all the information required to soundly exercise its discretion.” Id.

We continued that “By contrast, tort law duties to warn accomplish an entirely different objective of helping those who use or otherwise come into contact with a product to protect their own safety.” Id. (quoting Ghispo v. Eagle-Picker Industries (In re N.Y. Asbestos), 897 F.2d 626, 632 (2d Cir.1990)). Thus, design defect and failure to warn claims differ practically, as well as theoretically, and approval of a design does not mean that the government considered the appropriate warnings, if any, that should accompany the product. See id. We squarely held that the government contractor defense to failure to warn claims is not necessarily established merely by satisfying the government contractor defense as to design defect claims. Id at 1157. We further reasoned that:

When the government exercises its discretion and approves designs prepared by private contractors, it has an interest in insulating its contractors from liability for such design defects.... Similarly, when the government exercises its discretion and approves warnings intended for users, it has an interest in insulating its contractors from state failure to warn tort liability-

Id. (internal citations omitted.)

We then stated the Boyle requirements in failure to warn cases as follows:

When state law would otherwise impose liability for a failure to warn of dangers in using military equipment, that law is displaced if the contractor can show: (1) the United States exercised its discretion and approved the warnings, if any; (2) the contractor provided warnings that con[657]*657formed to the approved warnings; and (3) the contractor warned the United States of the dangers in the equipment’s use about which the contractor knew, but the United States did not.

Id.

We observed that the exercise of the government’s discretion must transcend rubber stamping. As none of this analysis was conducted by the district court, we remanded the issue to the district court. Id.

We stated that on remand the district court may elect to assume arguendo that Kentucky law would impose liability under these facts, and proceed to determine the propriety of summary judgment under the contractor defense. Id. at 1157-58. We further stated that the parties might have developed an insufficient record on the failure to warn claim. Id. at 1158.

On remand, the district court, in a succinct opinion, held that “significant conflict” between federal interest and state law, as required by Boyle, is not a precondition for consideration of the three-element test in Boyle. Tate v. Boeing Helicopters, 921 F.Supp. 1562, 1564-65 (W.D.Ky.1996). The court looked to our earlier opinion in reaching this conclusion, and stated that the “significant conflict” inquiry occurs during the analysis for the first element of the Boyle test, whether the United States exercised its discretion and approved the warnings. Id.

The court observed that the plaintiffs termed their theory of causation as “sling hang-up,” in that the hook system caused the dragging load to hang up on an open hook, creating too much tension in the sling for it to release, contrasting this to the statement in Tate I that the plaintiffs cause of action was based on “sling slack.” Id. at 1565-66. The district court simply held that, whether it is the one or the other, the undisputed cause of the action was a failure of the tandem cargo hook system to release the cargo, and the only relevant inquiry was whether Boeing and Breeze Eastern warned of the situation in which the hooks could fail to release. Id. at 1566.

The district court then considered whether the United States had exercised its discretion and approved the warnings, if any. The district court outlined the evidence on this issue in some detail, including the record concerning the substantial number of reviews and revisions of the CD-47D Operator’s Manual. Id. at 1566-67. The district court noted that “the process for creating the new CH-47D Operator’s Manual took one and a half years, even with the baseline YCH-47D Operator’s Manual already in existence.” Id. at 1567. The district court held that the approval could not be said to be rubber stamping and observed that where the government had gone beyond approval and actually determined for itself the warnings to be provided, the contract had surely satisfied the first Tate I condition because the government exercised its discretion. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Steven Papp v. Fore-Kast Sales Co Inc
842 F.3d 805 (Third Circuit, 2016)
Deborah Ripley v. Foster Wheeler LLC
841 F.3d 207 (Fourth Circuit, 2016)
Douglas Leite v. Crane Company
749 F.3d 1117 (Ninth Circuit, 2014)
Najolia v. Northrop Grumman Ship Systems, Inc.
883 F. Supp. 2d 646 (E.D. Louisiana, 2012)
Leite v. Crane Co.
868 F. Supp. 2d 1023 (D. Hawaii, 2012)
Barnes v. Various
770 F. Supp. 2d 736 (E.D. Pennsylvania, 2011)
In Re Asbestos Products Liability Lit.(no. Vi)
770 F. Supp. 2d 736 (E.D. Pennsylvania, 2011)
Cooley v. Lincoln Electric Co.
693 F. Supp. 2d 767 (N.D. Ohio, 2010)
Wiseco, Inc. v. Johnson Controls, Inc.
155 F. App'x 815 (Sixth Circuit, 2005)
Miller v. Diamond Shamrock Co.
275 F.3d 414 (Fifth Circuit, 2001)
Cacevic v. City of Hazel Park
226 F.3d 483 (Sixth Circuit, 2000)
Kerstetter v. Pacific Scientific Co.
210 F.3d 431 (Fifth Circuit, 2000)
Emory v. McDonnell Douglas Corp.
148 F.3d 347 (Fourth Circuit, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
140 F.3d 654, 1998 U.S. App. LEXIS 6589, 1998 WL 148469, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tate-v-boeing-helicopters-ca6-1998.