Winter Bros. Underground Inc. v. City of Beresford

2002 SD 117, 652 N.W.2d 99, 2002 S.D. LEXIS 136
CourtSouth Dakota Supreme Court
DecidedSeptember 18, 2002
DocketNone
StatusPublished
Cited by7 cases

This text of 2002 SD 117 (Winter Bros. Underground Inc. v. City of Beresford) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Winter Bros. Underground Inc. v. City of Beresford, 2002 SD 117, 652 N.W.2d 99, 2002 S.D. LEXIS 136 (S.D. 2002).

Opinions

GORS, Acting Justice.

[¶ 1.] Winter Brothers Underground (Winter Brothers) appeals the trial court’s order granting summary judgment to the City of Beresford (Beresford) and Ram-stad Construction (Ramstad). We affirm.

[101]*101FACTS AND PROCEDURE

[¶ 2.] On July 10, 2000, Beresford solicited bids from contractors to prepare a parcel of land for the construction of a Slumberland Furniture Regional Distribution Center (Slumberland). The project included storm sewer, water main, sanitary sewer and other site improvements associated with the construction of Slumberland. Beresford advertised its invitation to bid and received four bids, two of which included Winter Brothers and Ramstad.

[¶ 3.] The bid consisted of 31 line items that required bidders to enter either a lump sum bid or a unit price bid. In particular, Item 3 asked for the bidder’s lump sum bid to grub and clear the site. This work included “all hauling, crushing, rubberizing, labor, tools and workmanship and disposing of all items designated for removal.” The bid also forbade any conditional bids and stated, “[a]ll questions shall be directed to ... Larson Engineering!.]”

[¶ 4.] On July 6, prior to submitting his bid, Cliff Ramstad called Jerry Zeimetz (Zeimetz), the city administrator, and inquired about the possibilities of leaving any excess dirt on the site and disposing of the trees by burning them on site. After contacting the fire marshal, Zeimetz told Ramstad that leaving the dirt and burning the trees would be acceptable. Ramstad also asked Daryl Englund (Englund), the city engineer, if it would be acceptable to place any excess dirt from the project on the adjacent property owned by Beresford. Englund determined this would not pose a problem. Ramstad did not call Larson Engineering to ask these questions, as the bid required. Instead Ramstad relied upon the statements of Zeimetz and En-glund. Beresford did not file an addendum to the bid explaining that burning the trees and placing the dirt on the adjacent property would be. acceptable.

[¶ 5.] After publicly opening the four bids on July 10, Zeimetz announced that Ramstad was the lowest bidder at $271,990.25. Winter Brothers was the next lowest bidder at $280,268.50. Following the opening, Robert Winter (Winter) asked to look at some of the prices on Ramstad’s bid. Winter noticed that Item 3 of Ramstad’s bid was blank, and he informed the city officials. The bid schedule required bidders to complete a bid for each item requested and forbade any conditional bids. Because of this, Winter informed the city officials that the Ramstad bid was illegal.

[¶ 6.] In response to Item 3, the city officials asked Ramstad, in Winter’s presence, if he would accept a bid of zero for Item 3 on the bid schedule. Ramstad agreed. The Beresford City Council accepted Ramstad’s bid the evening of July 10. Ramstad began the project the following day.

[¶ 7.] In the weeks that followed, Winter Brothers brought to Beresford’s attention two additional issues regarding Ram-stad’s bid. One issue related to Ramstad’s conversations with Zeimetz and Englund about the excess dirt and burning the trees. It was discovered that Ramstad had annotated on the back of his bid the understandings Ramstad had with En-glund and Zeimetz about the project. In addition, Ramstad annotated that a manufacturing holdup would delay the installation of storm sewer manhole/drop inlets.1 Winter Brothers argued that these annota[102]*102tions rendered the bid conditional, in violation of the bidding procedures. Englund determined that the annotations were simply clarifications, not unusual in bidding documents.

[¶ 8.] On August 2, 2000, with the project underway, Winter Brothers filed suit seeking, inter alia, declaratory relief and an order to enjoin the award of the bid to Ramstad. Beresford and Ramstad brought motions to dismiss for Winter Brothers’ lack of standing as an unsuccessful bidder. On September 7, Winter Brothers filed a motion to amend its complaint, adding Carleen Weatherton (Weatherton) as an additional plaintiff and additional grounds for an injunction. On October 11, the trial court granted Winter Brothers’ motion to amend and held Beresford’s and Ramstad’s motions to dismiss in abeyance until trial. Since the project was completed by September 7, Winter Brothers conceded that its claim for injunctive relief was moot, but continued its claim for damages.

[¶ 9.] On September 8, 2000, Ramstad brought a second motion to dismiss, which Beresford later joined, claiming Weather-ton was not a taxpayer with standing to sue. The trial court denied this motion. On February 28, 2001, Ramstad brought motion for summary judgment against Winter Brothers. After a hearing, the trial court granted Ramstad’s motion. The court concluded, ‘Winter does not have standing as an alleged aggrieved bidder to bring an action against [Beresford] or [Ramstad].” The court further concluded that Beresford “complied with the competitive bidding laws of the State of South Dakota and acted within its discretion in awarding [Ramstad] the contract.... ” The trial court did not consider Ramstad’s motion for summary judgment with regard to Weatherton’s standing, concluding it was “unnecessary to reach the issue.”

[¶ 10.] Winter Brothers appeals on the following issues: (1) whether Winter Brothers has standing to sue as an unsuccessful bidder, and (2) whether Weather-ton has standing to sue as a taxpayer.

STANDARD OF REVIEW

[¶ 11.] Our standard of review on a trial court’s grant of summary judgment is well established. “[W]e will affirm only if all legal questions have been decided correctly and there are no genuine issues of material fact.” H & W Contracting, LLC, v. City of Watertown, 2001 SD 107, ¶ 7, 633 N.W.2d 167,171 (citing Estate of Juhnke v. Marquardt, 2001 SD 26, ¶ 5, 623 N.W.2d 731, 732). “The evidence is viewed most favorably to the nonmoving party and reasonable doubts are resolved against the moving party.” Brown Eyes v. South Dakota Dept. of Social Services, 2001 SD 81, ¶5, 630 N.W.2d 501, 504. In this case, the facts are not in dispute. Therefore, this Court only needs to determine whether the trial court correctly applied the law. Id.

ANALYSIS AND DECISION

[¶ 12.] 1. WHETHER WINTER BROTHERS HAS STANDING TO SUE.

[¶ 13.] Whether a party has standing to sue is a legal question, which this Court reviews under the de novo standard. H &W Contracting, 2001 SD 107 at ¶ 9, 633 N.W.2d at 171. Generally, a party establishes standing to challenge the bidding process by showing that he personally suffered an “actual or threatened injury as a result of the putatively illegal conduct of the defendant.” Id. (citing Agar Sch. Disk No. 58-1 v. McGee, 527 N.W.2d 282, 284 (S.D.1995)). Therefore, Winter Brothers must show that Beresford’s action caused an actual or threatened injury.

[103]*103[¶ 14.] a. Unsuccessful Bidders Lack Standing to Sue.

[¶ 15.] Winter Brothers claims that Ramstad’s bid was illegal, and therefore Winter Brothers was the lowest responsible bidder and entitled to the Slum-berland project. This Court addressed a similar situation in Tri-State Milling Co. v. Bd. of County Comm’rs, 75 S.D. 466,

Related

Johnson v. City of Omaha
319 Neb. 402 (Nebraska Supreme Court, 2025)
Arnoldy v. Mahoney & Finneman
2010 S.D. 89 (South Dakota Supreme Court, 2010)
Fritzmeier v. Krause Gentle Corp.
2003 SD 112 (South Dakota Supreme Court, 2003)
Stoetzel & Sons, Inc. v. City of Hastings
658 N.W.2d 636 (Nebraska Supreme Court, 2003)
Winter Bros. Underground Inc. v. City of Beresford
2002 SD 117 (South Dakota Supreme Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
2002 SD 117, 652 N.W.2d 99, 2002 S.D. LEXIS 136, Counsel Stack Legal Research, https://law.counselstack.com/opinion/winter-bros-underground-inc-v-city-of-beresford-sd-2002.