Wingate Land & Development, LLC v. Robert C. Walker, Inc.

558 S.E.2d 13, 252 Ga. App. 818, 2001 Fulton County D. Rep. 3341, 2001 Ga. App. LEXIS 1248
CourtCourt of Appeals of Georgia
DecidedOctober 31, 2001
DocketA01A1108
StatusPublished
Cited by10 cases

This text of 558 S.E.2d 13 (Wingate Land & Development, LLC v. Robert C. Walker, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wingate Land & Development, LLC v. Robert C. Walker, Inc., 558 S.E.2d 13, 252 Ga. App. 818, 2001 Fulton County D. Rep. 3341, 2001 Ga. App. LEXIS 1248 (Ga. Ct. App. 2001).

Opinion

Ruffin, Judge.

Robert C. Walker, Inc. (“Walker”) sued Wingate Land & Development, LLC, William Douglas Wingate, and Mary Wingate (collectively “Wingate”) alleging that Wingate owed Walker compensation for golf course architectural services. Following trial, the jury found in favor of Walker. After a separate bench trial on Walker’s claim for litigation expenses, the court also found in Walker’s favor. Wingate appeals, asserting the trial court erred in instructing the jury, admitting certain evidence, denying its motion for directed verdict, and entering judgment nunc pro tunc. For reasons that follow, we affirm.

Walker’s claims stem from Wingate’s development of the Stonebridge Golf & Country Club. In the planning stages, Wingate solicited golf course design proposals from architects, including Walker. In March 1994, Walker submitted a proposed design to Win-gate for consideration. The proposal included Walker’s standard services contract, which was dated March 29, 1994. The contract proposed a “Total Design Fee” of $165,000 and covered six phases of “Architectural Services,” which included “Frequent Construction Inspection Visits & Quality Control” during phase six.

*819 After reviewing the proposal, Wingate informed Walker that it wanted the architect to do the project, but requested that Walker change the pay schedule in the proposed contract. Specifically, Win-gate asked Walker to amend the schedule so that a greater portion of the contract price was paid during the latter phases of Walker’s performance under the contract. Walker changed the payment schedule as requested. The new schedule required Wingate to pay Walker $5,000 upon execution of the agreement, $5,000 upon completion of phase one, $10,000 upon completion of phase two and $10,000 for phase three, $45,000 upon completion of phase four, $10,000 for phase five, and $20,000 upon completion of each quarter of phase six.

Walker returned the amended contract, still dated March 29, 1994, to Wingate and attached a $5,000 invoice “[f] or the initial payment for Golf Course Architectural Services and execution of agreement fee.” Although Wingate did not execute the agreement, following a June 17 meeting between the parties, Wingate paid Walker $5,000.

Walker immediately began drafting golf course plans. As Walker continued its work on the golf course, it invoiced Wingate for the services according to the schedule set out in the March 29, 1994 contract. On July 16, 1994, Walker submitted a $5,400 invoice which stated that it was for reimbursement of expenses and “[flor the completion of Phase I in accordance with our agreement of March 29, 1994.” After receiving the invoice, Wingate paid Walker $5,400. On October 11, 1994, Walker sent Wingate a $10,000 invoice which stated that it was “[flor the completion of Phase II of our agreement for architectural services,” and Wingate subsequently paid that invoice. On January 8, 1995, Walker submitted an invoice “[flor 50% completion of Phase III, Phase IV and Phase V as per our agreement.” The invoice charged $32,500 for “Professional Service Fees Due” and $2,843.22 for expenses. On February 16, 1995, Wingate issued Walker a check for $32,500, which indicated that it was payment of the January 8 invoice. In addition to specifically referencing the phases of work that were covered by each invoice, the July, October, and January invoices clearly provided that they were for golf course architectural services.

Walker continued performing the services required by the March 29, 1994 agreement. As provided in the agreement, the architect completed the plans and construction specifications for the different phases of construction, prepared invitations to bid for the construction, and assisted in the bid conferences. In March 1995, however, the working relationship between Walker and Wingate deteriorated. Wingate complained that Walker was not adequately supervising the contractors and that it was not “on the job on a daily basis.” On March 16, 1995, Walker invoiced Wingate $32,500 for completion of *820 phases three through five. Although Wingate acknowledged that Walker did “a good job” on the invoiced services and that Wingate was satisfied with Walker’s performance as an architect, it paid only part of the invoice because of its complaints about “the things that [Walker] didn’t do.”

Elaborating on his complaints about Walker’s performance, William Wingate repeatedly testified that the parties orally agreed that Walker would be Wingate’s “project manager” and that there was no written agreement. William Wingate also claimed that Walker had agreed to be Wingate’s sole project “consultant” and “construction supervisor,” and that Wingate asked Walker to be the general contractor. According to William Wingate: “[Walker] assured me that [it] would furnish the architectural services and [it] would be the — instruction [sic] of the supervisors, and [it] would also assist in help in buying the materials and building stuff, and . . . would be there on a daily basis looking after the building.”

On March 14, 1995, Wingate sent Walker a letter reiterating his complaints about Walker’s lack of construction supervision and its failure to make daily visits to the site. In the letter, Wingate stated: “[t]his is the basis on which I gave you the job in designing the course, ... if you are unable to supervise these sub-contractors and be on the job on a daily basis you need to reduce your charges for this project for Architect work only.” Wingate subsequently asked Walker to reduce its fee to $100,000 if the architect wanted to stay on the job. Walker completed the project, performing the services required by the March 29, 1994 agreement, and Wingate paid the architect $100,000 for those services.

Walker subsequently sued Wingate for the remaining compensation allegedly owed by Wingate for Walker’s services. In its complaint, Walker asserted alternative causes of action for breach of contract, quantum meruit, and for an obligation on a commercial account. Walker also sought to recover its attorney fees on the ground that Wingate had acted in bad faith and had been stubbornly litigious.

On stipulation by the parties, the trial court bifurcated the trial, separating Walker’s claim for attorney fees, which was to be tried by the court, from the other claims, which were to be heard by a jury. At the trial on Walker’s claims of compensation due for architectural services, the court instructed the jury on all three of Walker’s alternative theories of liability. The jury rendered a verdict in Walker’s favor. The trial court then conducted a bench trial on Walker’s claim for attorney fees and rendered a judgment in Walker’s favor.

1. In two enumerations of error, Wingate asserts that the trial court erred in charging the jury on Walker’s claim of quantum meruit. Wingate argues that, because quantum meruit applies only *821 in the absence of a contract, and the parties here agreed there was a contract, the court should not have submitted this claim to the jury. We disagree.

We note initially that Wingate appears to argue that Walker was required to proceed to trial on only one theory of recovery. Georgia law, however, permits a plaintiff to proceed to trial on alternative theories of recovery. 1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JOHN CHANG v. CITY OF MILTON
Court of Appeals of Georgia, 2024
TAYLOR, EXR. v. THE DEVEREUX FOUNDATION, INC. (And Vice Versa)
885 S.E.2d 671 (Supreme Court of Georgia, 2023)
CAMPBELL v. AILION Et Al.
790 S.E.2d 68 (Court of Appeals of Georgia, 2016)
IDRIS GRISWOLD v. AUDREY COLLINS
Court of Appeals of Georgia, 2012
Griswold v. Collins
734 S.E.2d 425 (Court of Appeals of Georgia, 2012)
PN Express, Inc. v. Zegel
697 S.E.2d 226 (Court of Appeals of Georgia, 2010)
Rogan v. Patterson
668 S.E.2d 459 (Court of Appeals of Georgia, 2008)
Coleman v. Fortner
579 S.E.2d 792 (Court of Appeals of Georgia, 2003)
Harris v. State
572 S.E.2d 370 (Court of Appeals of Georgia, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
558 S.E.2d 13, 252 Ga. App. 818, 2001 Fulton County D. Rep. 3341, 2001 Ga. App. LEXIS 1248, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wingate-land-development-llc-v-robert-c-walker-inc-gactapp-2001.