OPINION
Before RABINOWITZ, C. J., and CON-NOR, BOOCHEVER, BURKE and MATTHEWS, JJ.
RABINO WITZ, Chief Justice.
After the 1964 earthquake, the City of Valdez obtained assistance from the United States Army Corps of Engineers in its efforts to relocate and rebuild. As a part of this rebuilding project the Corps built a storm drainage ditch across a parcel of land in United States Survey 635. This portion of the ditch was constructed from August 4, 1965, through August 18, 1965, and, as a part' of the overall project, was operational on December 1, 1965. The ditch was to be the principal conduit for storm sewer discharge from the City into the port of Valdez.
At the time the ditch was constructed the parcel of land in question was owned by the Port Valdez Company. In 1971, the Port Valdez Company filed a complaint against the City seeking relief for various allegedly unlawful acts.
In a portion of this complaint, the Company alleged that in 1965 the City unlawfully excavated the drainage ditch, blocking development and use of this parcel of land. The Company sought a remedy of ejectment, damages and restoration of the property. On August 14, 1974, the City and Company entered into a settlement agreement resolving this dispute in its entirety. In this agreement the Company waived “any objection it might have to the ditch being there and to any claim to damages relating to the ditch.”
Prior to this settlement, on May 24,1973, the Company conveyed a 1.39 acre parcel of land which the ditch traversed to J. V. Williams by quitclaim deed.
Williams, at approximately the same time, also purchased an adjoining 4.158 acre parcel from the Company by warranty deed. It was on this latter, adjoining parcel that the Totem Inn motel, restaurant, and bar facilities had been constructed by Williams in 1972 and completed in early 1973. Williams knew that the drainage ditch existed at the time of these purchases, and was also aware of the pre-existing controversy and law suit between the City and the Company with respect to the ditch. In fact, his affidavit in the superior court in this case stated that “the property was purchased in two separate parcels separating that portion which contained the ditch from the remainder of the property so that no legal dispute existed on the parcel on which [he had] constructed [the Totem Inn facilities].”
At some time between May 20 and June 1, 1973, approximately the time of his purchase of the property, Williams filled in a portion of the ditch for the purpose of constructing access and additional parking space for the Totem Inn, apparently after some discussion with the City on the matter.
Shortly thereafter, the City filed a complaint for a mandatory injunction and damages for the cost of removing this obstruction to Valdez’ storm drainage system. While the request for a restraining order requiring the immediate reopening of the ditch was denied, the superior court concluded that the City could reopen the ditch pursuant to its general police powers.
Instead of clearing out the entire length of the filled ditch, the City, evidently as a temporary measure until the merits of the suit were decided, cleared only a portion of the ditch on Williams’ property. This allowed any drainage water to bypass the filled portion of the ditch and flow instead along the highway right-of-way.
This did
not resolve the dispute, however, since the State Highway Department objected to this use of its right-of-way.
Accordingly, on January 4, 1974, the City filed an amended complaint requesting relief directing Williams to remove the obstruction to the ditch at his cost, as well as other relief and damages, including the City’s expenses for the initial partial clearing of the ditch. Williams answered and counterclaimed, requesting a declaration that the ditch was unlawfully constructed on his property by the City and seeking damages for the cost of filling in the remainder of the ditch. The City then moved for summary judgment on its claim, but this motion was denied by the superior court.
Approximately a year later, a second motion for summary judgment was filed by the City. The superior court also denied this second summary judgment motion by the City.
Subsequently, the City again moved for summary judgment, terming its motion one for “partial summary judgment.” The motion sought a declaration that inverse condemnation had occurred in 1965 when the Corps of Engineers constructed the drainage ditch on behalf of the City of Valdez. It purported not to deal with the amount of inverse condemnation damages, to whom such damages should be paid, or the City’s claim for damages resulting from Williams’ blockage of the drainage ditch.
Williams submitted a memorandum and affidavit in opposition to this motion, which argued that summary judgment was not proper, in part because there were genuine issues of fact as to:
1. The exact location of the present drainage ditch.
2. Whether or not the Court should limit the use where the ditch is presently existing; that is, should the Court require the plaintiff [to] utilize the ditch in the same manner that it is utilizing the same throughout the CITY OF VALDEZ; that is, by laying a pipe and covering the same.
At a decisional hearing, the superior court granted the City’s motion for summary judgment, basing its decision on
Wickwire v. City and Borough of Juneau, 557
P.2d 783 (Alaska 1976). The superior court held that the date of the initial invasion by the Corps was the proper valuation date for computing any claim to inverse condemnation damages. The City’s counsel then asserted, as an addition to its motion, that, therefore, the Port Valdez Company rather than Williams had a claim for such damages. The superior court, relying on the
Wickwire
decision, agreed that “it was not a right that can be passed by a quitclaim deed, and consequently Mr. Williams has no right to any compensation.”
An order granting partial summary judgment, which the City had submitted with its motion prior to the decisional hearing, was subsequently entered, and Williams filed a notice of appeal from this order on October 3, 1977.
On October 11, 1977, the City filed a motion for amendment of that order and entry of final judgment on the grounds that the order, prepared prior to the decisional hearing, did not reflect the broader decision rendered at the hearing by the judge. On January 19,1978, the superior court vacated its earlier order and entered judgment in favor of the City of Valdez, stating that he had “reconsidered the entire case file and previous actions taken in it as well as the objections” raised by Williams to the entry of a final judgment.
Free access — add to your briefcase to read the full text and ask questions with AI
OPINION
Before RABINOWITZ, C. J., and CON-NOR, BOOCHEVER, BURKE and MATTHEWS, JJ.
RABINO WITZ, Chief Justice.
After the 1964 earthquake, the City of Valdez obtained assistance from the United States Army Corps of Engineers in its efforts to relocate and rebuild. As a part of this rebuilding project the Corps built a storm drainage ditch across a parcel of land in United States Survey 635. This portion of the ditch was constructed from August 4, 1965, through August 18, 1965, and, as a part' of the overall project, was operational on December 1, 1965. The ditch was to be the principal conduit for storm sewer discharge from the City into the port of Valdez.
At the time the ditch was constructed the parcel of land in question was owned by the Port Valdez Company. In 1971, the Port Valdez Company filed a complaint against the City seeking relief for various allegedly unlawful acts.
In a portion of this complaint, the Company alleged that in 1965 the City unlawfully excavated the drainage ditch, blocking development and use of this parcel of land. The Company sought a remedy of ejectment, damages and restoration of the property. On August 14, 1974, the City and Company entered into a settlement agreement resolving this dispute in its entirety. In this agreement the Company waived “any objection it might have to the ditch being there and to any claim to damages relating to the ditch.”
Prior to this settlement, on May 24,1973, the Company conveyed a 1.39 acre parcel of land which the ditch traversed to J. V. Williams by quitclaim deed.
Williams, at approximately the same time, also purchased an adjoining 4.158 acre parcel from the Company by warranty deed. It was on this latter, adjoining parcel that the Totem Inn motel, restaurant, and bar facilities had been constructed by Williams in 1972 and completed in early 1973. Williams knew that the drainage ditch existed at the time of these purchases, and was also aware of the pre-existing controversy and law suit between the City and the Company with respect to the ditch. In fact, his affidavit in the superior court in this case stated that “the property was purchased in two separate parcels separating that portion which contained the ditch from the remainder of the property so that no legal dispute existed on the parcel on which [he had] constructed [the Totem Inn facilities].”
At some time between May 20 and June 1, 1973, approximately the time of his purchase of the property, Williams filled in a portion of the ditch for the purpose of constructing access and additional parking space for the Totem Inn, apparently after some discussion with the City on the matter.
Shortly thereafter, the City filed a complaint for a mandatory injunction and damages for the cost of removing this obstruction to Valdez’ storm drainage system. While the request for a restraining order requiring the immediate reopening of the ditch was denied, the superior court concluded that the City could reopen the ditch pursuant to its general police powers.
Instead of clearing out the entire length of the filled ditch, the City, evidently as a temporary measure until the merits of the suit were decided, cleared only a portion of the ditch on Williams’ property. This allowed any drainage water to bypass the filled portion of the ditch and flow instead along the highway right-of-way.
This did
not resolve the dispute, however, since the State Highway Department objected to this use of its right-of-way.
Accordingly, on January 4, 1974, the City filed an amended complaint requesting relief directing Williams to remove the obstruction to the ditch at his cost, as well as other relief and damages, including the City’s expenses for the initial partial clearing of the ditch. Williams answered and counterclaimed, requesting a declaration that the ditch was unlawfully constructed on his property by the City and seeking damages for the cost of filling in the remainder of the ditch. The City then moved for summary judgment on its claim, but this motion was denied by the superior court.
Approximately a year later, a second motion for summary judgment was filed by the City. The superior court also denied this second summary judgment motion by the City.
Subsequently, the City again moved for summary judgment, terming its motion one for “partial summary judgment.” The motion sought a declaration that inverse condemnation had occurred in 1965 when the Corps of Engineers constructed the drainage ditch on behalf of the City of Valdez. It purported not to deal with the amount of inverse condemnation damages, to whom such damages should be paid, or the City’s claim for damages resulting from Williams’ blockage of the drainage ditch.
Williams submitted a memorandum and affidavit in opposition to this motion, which argued that summary judgment was not proper, in part because there were genuine issues of fact as to:
1. The exact location of the present drainage ditch.
2. Whether or not the Court should limit the use where the ditch is presently existing; that is, should the Court require the plaintiff [to] utilize the ditch in the same manner that it is utilizing the same throughout the CITY OF VALDEZ; that is, by laying a pipe and covering the same.
At a decisional hearing, the superior court granted the City’s motion for summary judgment, basing its decision on
Wickwire v. City and Borough of Juneau, 557
P.2d 783 (Alaska 1976). The superior court held that the date of the initial invasion by the Corps was the proper valuation date for computing any claim to inverse condemnation damages. The City’s counsel then asserted, as an addition to its motion, that, therefore, the Port Valdez Company rather than Williams had a claim for such damages. The superior court, relying on the
Wickwire
decision, agreed that “it was not a right that can be passed by a quitclaim deed, and consequently Mr. Williams has no right to any compensation.”
An order granting partial summary judgment, which the City had submitted with its motion prior to the decisional hearing, was subsequently entered, and Williams filed a notice of appeal from this order on October 3, 1977.
On October 11, 1977, the City filed a motion for amendment of that order and entry of final judgment on the grounds that the order, prepared prior to the decisional hearing, did not reflect the broader decision rendered at the hearing by the judge. On January 19,1978, the superior court vacated its earlier order and entered judgment in favor of the City of Valdez, stating that he had “reconsidered the entire case file and previous actions taken in it as well as the objections” raised by Williams to the entry of a final judgment. This judgment held that the City acquired a fee simple interest in the property on which the drainage ditch had been constructed as of the date of the taking, August 4, 1965; permanently restrained Williams from interfering with the drainage ditch; required Williams to pay the cost of clearing the original blockage and of restoring the ditch to its original condition, while retaining jurisdiction to resolve any disputes as to this restoration. Williams filed an amended notice of appeal and statement of points on appeal in response to the trial court’s entry of this judgment.
The City subsequently filed a motion for attorney’s fees, arguing that the award was “appropriate under the particular facts and circumstances of this case.” The superior court entered an order denying the City an award of attorney’s fees, because of. its conclusion that the case “should be treated as one for condemnation” and that the City, as the condemning authority, was therefore not' entitled to recover its attorney’s fees. The City brings a cross-appeal from this order.
Williams argues on appeal that the superior court did not have the authority to modify its “partial summary judgment” order and enter a final judgment after the filing of Williams’ notice of appeal from that earlier order.
We find this argument to be without merit because Williams’ initial “appeal” was not taken from an appeal-able “final judgment” as required by Alaska Appellate Rule 5.
As a general rule, a partial summary judgment order is considered “interlocutory” and non-appealable unless there is a specific statutory provision providing for appeal.
However, in order to assess finality “the reviewing court should look to the substance and effect, rather than form, of the rendering court’s judgment, and focus primarily on the operational or ‘decretal’ language therein.” “The basic thrust of the finality requirement is that the judgment must be one which disposes of the entire case, ‘. . . one which ends the litigation on the merits and leaves nothing for the court to do but execute the judgment.’ ”
'
The “partial summary judgment” order of August 29, 1977, entered in this case was not a “final judgment” which disposed of the entire case on its merits. The order was limited to the legal issue of inverse condemnation and, like the City’s partial summary judgment motion seeking the order, did not purport to resolve the issues of condemnation damages, to whom such damages should be paid, or the City’s claim for damages resulting from Williams’ blockage of the drainage ditch. A comparison of this order with the judgment entered January 19, 1978, emphasizes that several issues were not addressed or resolved by the order which required resolution in order to dispose of the entire case and end the litigation on the merits.
Since Williams’ initial notice of appeal was taken from an order of the superior court which was not a final judgment, the superior court was not thereby divested of its authority to modify that order and enter a final judgment in thé case.
Williams also argues that the entry of a summary judgment was improper because there was a genuine issue of material fact as to whether the Port Valdez Company originally agreed or acquiesced to the construction of the ditch on its property.
The nature and duration of any such agreement would be relevant to a determination as to the fact and time of any “taking” by the City.
Williams did not raise this question in the superior court in his objections to the entry of a summary judgment or in his denomination of genuine issues of material fact. However, Alaska Civil Rule 56(c) provides only that the party opposing a motion for summary judgment “may serve opposing affidavits, a concise ‘statement of genuine issues’ setting forth all material facts as to which it is contended there exists a genuine issue necessary to be litigated.” It remains the responsibility of the trial judge to determine whether the record presents any factual issues which would preclude the entry of a summary judgment as a matter of law. Still, any such factual • issues must have been fairly presented to the trial court, since, as a general rule, appellate review is precluded where “questions which appellants denominate as ‘tria-ble issues of fact’ were not presented to the court below.”
The sole support in the record for Williams’ assertion as to this “genuine issue of material fact” is an allegation in the City’s amended complaint, as one of several alternative grounds for relief, that the Port Valdez Company allowed the ditch to be constructed “by agreement or acquiescence.” However, at the decisional hearing the superior court observed, without objection from Williams, that “[t]he City is apparently abandoning any contention that it constructed the ditch rightfully or it subsequently obtained the right to maintain it.”
Other than this allegation by the City, the record consistently indicates that there was no such agreement between the City and the Port Valdez Company. In his response to the City’s complaint, Williams denied that his predecessors in interest had so agreed or acquiesced, and in an affidavit concerning his negotiations with the Port Valdez Company to purchase the property Williams stated:
It was my understanding that the ditch was constructed on the property without any legal authority whatsoever and that the CITY OF VALDEZ had no easement or valid right to enter the property, nor did the CITY OF VALDEZ acquire any right to construct the ditch on the subject property, or to maintain the same, and that it has been in dispute with the owner of said property since the ditch was constructed.
The record before the superior court also included a complaint filed by the Port Valdez Company in the civil action against the City commenced more than a year and a half before Williams purchased the property in question, as well as an affidavit from the Company’s attorney in these matters. These documents assert that the ditch was constructed on the property by the City “without the consent or authorization” of the Port Valdez Company and that the Company cohsidered the ditch an illegal encroachment on its property which it had repeatedly sought to have removed.
It is well established that
[t]o avoid summary judgment once the moving party meets its burden, the non-moving party must produce competent evidence showing that there are issues of material fact to be tried. The respondent must set forth specific facts showing that it could produce admissible evidence reasonably tending to dispute the movant’s evidence or establish an affirmative defense.
The respondent’s burden can only be met by “competent evidence to show that there are issues of material fact to be tried,” and “[assertions of fact in [the] pleadings and memoranda are not admissible in evidence and cannot be relied upon for the purposes of summary judgment.”
Such assertions in the City’s complaint are Williams’ only source of “evidence” in the record concerning the possibility of an agreement between
the Port Valdez Company and the City to allow construction of the ditch on what was then the Company’s property. Those assertions are not sufficient in themselves to raise a genuine issue of fact, particularly where abandoned as a alternative theory of relief, and did not make the superior court’s entry of a summary judgment improper.
Williams also argues that the superior court erred in granting the City a fee simple interest in the property by inverse condemnation, rather than an easement by prescription. However, as the superior court noted at the decisional hearing, the City sufficiently established its authority to utilize condemnation to obtain the property for this purpose and Williams did not dispute the City’s eminent domain power in this respect.
Given this power of eminent domain.
Wickwire v. City and Borough of Juneau,
557 P.2d 783 (Alaska 1976), provides the answer to Williams’ contention. In a context analogous to the present situation in all respects important to this question,
Wickwire
held that “[t]he landowner’s only remedy in a situation such as the one presented is an inverse condemnation action for just compensation.”
However, while eminent domain is the source of the City’s power and right to construct the drainage ditch, Williams also asserts that the superior court should not have granted the City a fee simple interest in the land on which the ditch was constructed. The City argues that our decision in
City of Fairbanks v. Metro,
540 P.2d 1056 (Alaska 1975), recognized discretion in the condemnor to choose the estate to be taken. In that case, in the context of statutory condemnation proceedings, we recognized that the power of eminent domain is such that “particular questions as to the route, location or amount of property to be taken are to be left to the sound discretion of the condemning authority absent a showing by clear and convincing evidence that such determinations are the product of fraud, caprice, or arbitrariness.”
Id.
at 1058. That opinion does not extend the City’s discretion to the matter of the choice of the estate to be taken.
The nature and extent of the estate taken in the exercise of eminent domain power depends on the statute conferring that power.
At the time of the taking in this case as determined by the superior court, the relevant Alaska statute, AS 09.-55.250 provided:
Classification of estates and lands subject to be taken.
The following is a classification of the estates and rights in lands subject to be taken for public use:
(1) a fee simple, when taken for public buildings or grounds, or for permanent buildings, for reservoirs and dams and permanent flooding occasioned by them, or for an outlet for a flow, or a place for the deposit of debris or tailings of a mine, or when, in the judgment of the Department of Public Works or the Department of Highways, a fee simple is necessary for any of the purposes for which the depart
ment, on behalf of the state, is authorized by law to acquire real property by condemnation;
(2) an easement when taken for any other use;
(3) the right of entry upon an occupation of lands, and the right to take from the land earth, gravel, stones, trees, and timber as may be necessary for a public use.
Consistent with general principles of eminent domain, this statute specifies certain uses for which a fee simple taking is authorized and allows only an easement to be taken for any other use.
It is the “general rule that only such an estate in property sought to be acquired by eminent domain may be taken as is reasonably necessary for the accomplishment of the purpose” for which the property is taken.
Therefore, the principle that “statutes authorizing the exercise of eminent domain are to be strictly constructed against the condemnor . has been applied to statutory declarations with respect to the extent of the interest which is to be acquired.”
Pertinent to the drainage ditch for which the taking in this case occurred, the Alaska statute quoted above authorized a fee simple taking “for an outlet for a flow.” While this phrase, in isolation, is sufficiently ambiguous to include the drainage ditch here, an examination of other eminent domain provisions and the principle of strict construction do not allow such an expansive reading.
The provisions of AS 09.55.240 enumerate the public uses for which the right of eminent domain may be exercised. The only portion of that statute which speaks in terms of “an outlet for a flow” is AS 09.55.-240(5), which authorizes the exercise of eminent domain power for:
roads, tunnels, ditches, flumes, pipes, and dumping places for working mines; also outlets, natural or otherwise, for the flow, deposit, or conduct of tailings or refuse matter from mines; also an occupancy in common by the owners or possessors of different mines of any place for the flow, deposit, or conduct of tailings or refuse matter from their several mines, and sites for reservoirs necessary for collecting and storing water .
This provision suggests that “an outlet for a flow” for which a fee simple taking is allowed refers only to the flow of tailings or refuse matter from mines. This narrow interpretation of this phrase is also consistent with its context in AS 09.55.250, allowing a fee simple taking “for an outlet for a flow, or a place for the deposit of debris or tailings of a mine.”
We conclude that the City was authorized to take only an easement for this drainage ditch. This conclusion is in accord with the decisions of other courts in inverse condemnation cases which have found that an easement was taken for a drainage ditch or culvert.
Moreover, the record indicates that the City may replace the drainage ditch with a covered culvert to minimize the impact on Williams’ business, in which case, even were a fee simple taking authorized by statute, an easement would be the most appropriate interest for the City to acquire.
On remand, the superior court should amend its judgment to designate the estate taken as an easement, rather than a fee simple interest. In so doing, the superi-
or court should enter an order specifically describing the easement and any necessary right-of-way which has been taken by the City.
In amending its judgment, the superior court should also eliminate that portion of the judgment which purports to decide that the Port Valdez Company has no claim to compensation as owner of the property at the time of the taking, since the Company was not a party to the present case and its rights therefore could not be adjudicated by the superior court.
We have considered each of the other points raised by Williams on appeal and find them to be without merit, with the exception of two issues relating to the provisions of the superior court’s judgment which awarded the City of Valdez the costs of clearing the original blockage, as well as the costs of restoration of the ditch to its original condition.
Our study of the parties’ briefs has led us to the conclusion that further briefing of those questions is indicated. Thus, jurisdiction will be retained as to these two issues and further briefing will be ordered.
In the cross-appeal in this case, the City argues that the superior court erred in refusing to award the City attorney’s fees. As noted above, the superior court awarded no attorney’s fees to the City because of its view that the case “should be treated as one for condemnation.”
Civil Rule 72(k) contains specific provisions for the award of attorney’s fees to defendant landowners in' eminent domain proceedings.
We have interpreted these
provisions to be the exclusive source and guide for the award of attorney’s fees to landowners in such proceedings.
With regard to the question presented in this case, our opinion in
City of Anchorage v. Scavenius,
539 P.2d 1169, 1171-76 (Alaska 1975), extensively analyzed the question of allowing attorney’s fees to condemnors in eminent domain cases. Rejecting a rule allowing attorney’s fees for condemnors,
Scaven-ius
reasoned that
the interpretation of the rule posited by the City, albeit plausible, is too literal. A more persuasive interpretation consistent with the language of the rule and with this court’s discussion of that rule in
Stewart & Grindle
[524 P.2d 1242 (Alaska 1974)], is also available. That construction would view subsection (k) to be totally exclusive in regard to the allocation of costs and attorney’s fees in a condemnation proceeding. The “except as otherwise provided in this rule” language of subsection (a) would be directly applicable. Rule 72
does provide
for costs and attorney’s fees to be awarded only to the property owner in a condemnation proceeding and only under certain narrowly-defined circumstances. Therefore, far from construing the silence as a license to invoke the general provisions regarding costs and attorney’s fees, subsection (a) expressly prohibits allusion to the other civil rules when a specific eminent domain procedural rule is prescribed.
Therefore, we concluded “that since Rule 72(k) fails to specify any conditions which would warrant imposition of costs against the property owner, the trial court did not err in refusing to authorize such an award.”
The City argues that the Rule 82 “prevailing party” attorney’s fees provisions should apply here rather than those of Rule 72. It argues that our previous cases interpreting the Rule 72 provisions were dealing with statutory condemnation procedures and that we should limit the application of the principles enunciated there to statutory proceedings. The City argues that it would be difficult to apply Rule 72(k)’s provisions for allowing landowners attorney’s fees in an inverse condemnation case. Williams rebuts the City’s argument by asserting that since the basis for the judgment was inverse condemnation, “[wjhether or not [the City] was the prevailing party is of no consequence since in almost every condemnation case, the condemning authority is in effect the prevailing party.”
We have concluded that a con-demnor should not be allowed to recover attorney’s fees in inverse condemnation cases. While all of the special procedures of Civil Rule 72 cannot be followed, the policy concerns underlying Rule 72(k)’s implicit disallowance of condemnor attorney’s fees are still implicated.
A condemnor should not be allowed to benefit from its failure to institute statutory proceedings
prior to the taking. The fact remains that it is the power of eminent domain which allowed the City to prevail in this case. Therefore, as we have noted, “the concept of prevailing party to which the state seems to be referring is not applicable to eminent domain proceedings, where the state almost always ‘prevails.’ ”
As we said with respect to inverse condemnation in
State Department of Highways v.
Crosby; 410 P.2d 724, 728 (Alaska 1966) (footnote omitted):
When the state appropriated appellees’ land for the construction of a highway, it was exercising the power of eminent domain. It is true that the state did not utilize condemnation proceedings prescribed by law and by rule. But neither the failure to institute a condemnation action nor appellees’ assertion of a claim based on the theory of trespass changed the essential nature of the state’s action in appropriating appellees’ property. Such action was still the exercise of the power of eminent domain because private property was being taken by the state for a public use.
In
Crosby,
we also held that while all of the legally required procedures for condemnation cannot, as a practical matter, apply in an inverse condemnation case where the property has already been appropriated, the “statutory requirements and procedural steps” should be used to determine unresolved issues “so far as practicable.”
While the City’s argument that Rule 72(k)’s provisions for the award of attorney’s fees to landowners cannot be applied to the different circumstances of inverse condemnation has some merit, those provisions might be employed in appropriate circumstances.
In any event, the fact that there may be difficulties in using that rule to determine when an award of attorney’s fees to a landowner is appropriate does not compel the conclusion that the rule’s inherent policies should be discarded and landowners in inverse condemnation cases in effect forced to finance the condemnation litigation of the state, borough, or city.
Accordingly, we Affirm the superior court’s order denying an award of attorney’s fees to the City in the cross-appeal, No. 4149. The superior court’s judgment in the main appeal, No. 3709, is Affirmed in part; Modified in part; Remanded for further proceedings consistent with this opinion; and jurisdiction retained for further briefing pertaining to the issues concerning Williams’ liability for the costs of clearing the original blockage and the costs of restoration of the ditch to its original condition.