Williams v. City of Sioux Falls

846 F.2d 509, 1988 WL 46834
CourtCourt of Appeals for the Eighth Circuit
DecidedMay 16, 1988
DocketNo. 87-5085
StatusPublished
Cited by9 cases

This text of 846 F.2d 509 (Williams v. City of Sioux Falls) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williams v. City of Sioux Falls, 846 F.2d 509, 1988 WL 46834 (8th Cir. 1988).

Opinion

BEAM, Circuit Judge.

Porter Williams appeals from a final judgment dismissing this action against the City of Sioux Falls, South Dakota, and several city officials. Williams, a black contractor, alleges that he is the victim of racial discrimination resulting from activities carried out in the City’s construction contract letting process. The district court1 dismissed the case, finding that Williams had failed to establish a case of intentional discrimination against himself or, more generally, against a certified class of minority contractors. After unsuccessfully seeking a new trial, Williams appeals, charging that the district court erred in overruling the motion for a new trial and in entering judgment in favor of the defendants. Upon a review of the record and the arguments of the parties, we affirm.

A. Background

Plaintiff Williams asserts three claims, each of which was considered and dismissed by the district court following a four day nonjury trial. The first, brought pursuant to 42 U.S.C. §§ 1981, 1983 and 2000d, alleges that the City and certain city officials discriminated against Williams during the bidding process on a demolition contract known as the “Beadle Project,” which project contract was awarded by the City in November of 1980. Plaintiffs second claim, also brought pursuant to sections 1981,1983 and 2000d, alleges that the defendants have engaged in a pattern and practice of discrimination against all minority contractors through the City’s failure to observe minority business enterprise [511]*511(MBE) guidelines. These guidelines are imposed upon the City by the federal government because the City receives federal funds. The district court certified a class of minority contractors consisting of all minority contractors domiciled in South Dakota and those additional minority contractors not domiciled in South Dakota who had become eligible on or before July 1, 1984, to participate in the Sioux Falls MBE program.2 Finally, the plaintiff asserts that the City’s alleged violation of MBE regulations is actionable under 42 U.S.C. § 1983, as a deprivation of rights secured by federal law. We address each of these claims separately.

B. Individual Claim — Beadle Project

The district court correctly recognized that under plaintiffs individual claim, each theory of recovery is viable only if the City intentionally treated the plaintiff less favorably because of his race. See Guardians Ass’n v. Civil Serv. Comm’n, 463 U.S. 582, 103 S.Ct. 3221, 77 L.Ed.2d 866 (1983); Washington v. Davis, 426 U.S. 229, 96 S.Ct. 2040, 48 L.Ed.2d 597 (1976). The court employed the traditional analysis utilized to decide questions of intentional discrimination, asking first whether the plaintiff had established a prima facie case. See McDonnell Douglas Corp. v. Green, 411 U.S. 792, 93 S.Ct. 1817, 36 L.Ed.2d 668 (1973); Craik v. Minnesota State Univ. Bd., 731 F.2d 465 (8th Cir.1984). Because the court found that the plaintiff had not established a prima facie case, it was unnecessary for the court to proceed with the remaining steps of the McDonnell Douglas analysis.3 The record supports the district court’s conclusion.

The Beadle demolition project was divided by the City into five phases, each of which was to be bid separately. Williams was interested in submitting a bid on phase two, which phase involved the removal of a garage structure and site clearance. The bid specifications provided that the job should be completed in 30 days, with a per-day penalty assessed for each additional day necessary for final performance.

In light of his relative inexperience with the bidding process, Williams sought assistance from the City in the preparation of his bid on phase two. Several city officials provided Williams with a significant amount of technical and clerical help, enabling him to submit a bid of $5,000 on the project. Williams’ bid was quite reasonable, falling midway between the bids of most other contractors, which proposals sought from $3,500 to $7,680 to complete the work. However, the project was awarded to General Excavating Company on a bid of $1.00. General Excavating planned to move the garage structure intact to another location for use as a workshop, and apparently concluded that the salvage value of the building was sufficient consideration for the building removal and site clearance.

Williams alleges that he was denied a fair opportunity to submit a competitive bid on this project because the City failed to inform him of the potential for obtaining a stripping order. A stripping order gives a demolition contractor extra time to enter upon the premises to remove objects the contractor wishes to sell as salvage. The City issues a stripping order only when there is an unexpected delay in an earlier phase of a project which, in turn, allows additional time for completion of demolition. The City does not dispute that it failed to inform Williams about the potential for receiving a stripping order on the Beadle project. The City insists, however, that it is unnecessary to discuss stripping [512]*512orders with contractors, and that it would be unwise for any contractor to rely upon such a fortuitous factor in arriving at the amount of a bid.

The district court found that the City treated Williams the same as it did every other contractor with regard to advice about stripping orders. In fact, the district court concluded that the City provided the plaintiff with several hours of extra assistance which it did not give to nonminority contractors interested in the project. The district court said that even if Williams had known he might obtain a stripping order, there was no evidence that Williams would have bid less than the $1.00 proposed by General Excavating. Unlike General Excavating, Williams did not have an alternate use for the building which was to be removed.

We are unable to say that these findings are clearly erroneous. The district court considered all the evidence and thoroughly analyzed plaintiffs claim. The conclusion that the City did not intentionally deceive the plaintiff because of his race is supported by the evidence, and shall be upheld. See Walker v. Int’l Business Machines, 698 F.2d 959, 962 (8th Cir.1983).

C. Class Claim-MBE Regulations

The class claim alleges that the City has engaged in a pattern and practice of intentional discrimination against minority contractors by disregarding federal and local MBE regulations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. McNeese
883 F. Supp. 2d 897 (D. Nebraska, 2012)
King v. Hardesty
517 F.3d 1049 (Eighth Circuit, 2008)
Thomas v. City of Saint Paul
526 F. Supp. 2d 959 (D. Minnesota, 2007)
Jenkins v. Wal-Mart Stores, Inc.
910 F. Supp. 1399 (N.D. Iowa, 1995)
Brown v. American Honda Motor Company
939 F.2d 946 (Eleventh Circuit, 1991)
Brown v. American Honda Motor Co.
939 F.2d 946 (Eleventh Circuit, 1991)
Tinsley v. Kemp
750 F. Supp. 1001 (W.D. Missouri, 1990)
Williams v. City of Sioux Falls
846 F.2d 509 (Eighth Circuit, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
846 F.2d 509, 1988 WL 46834, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-v-city-of-sioux-falls-ca8-1988.