Williams v. 7-11

CourtCourt of Appeals of Tennessee
DecidedJune 18, 1999
Docket01A01-9710-CV-00560
StatusPublished

This text of Williams v. 7-11 (Williams v. 7-11) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williams v. 7-11, (Tenn. Ct. App. 1999).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE FILED June 18, 1999

Cecil W. Crowson Appellate Court Clerk MIKE WILLIAMS, INDIVIDUALLY, ) From the Circuit Court and d/b/a MIKE’S FOOD VALUE ) for Sumner County, Tennessee and WESTMORELAND BI-RITE, ) The Honorable Thomas Goodall, Judge ) Plaintiff/Appellee, ) Sumner Circuit No. 15697-C ) Appeal No. 01A01-9710-CV-00560 v. ) ) AFFIRMED IN PART, REVERSED IN 7-11 INSTALLATION & SERVICE, ) PART, AND REMANDED INC. and BUD CARTER, ) ) John R. Phillips, Jr. Defendants/Appellants. ) Gallatin, Tennessee ) Attorney for Defendants/Appellants ) ) Cynthia Hall Templeton ) Gallatin, Tennessee ) Attorney for the Plaintiff/Appellee

RULE 10 MEMORANDUM OPINION

This matter appears appropriate for consideration pursuant to Rule 10(b) of the Rules of the

Court of Appeals of Tennessee.1

This is a breach of contract case involving the sale and installation of refrigeration

equipment. The owner of the property alleged that the contractor breached the agreement to install

the equipment. The trial court entered a judgment in favor of the property owner. The contractor

appeals. We affirm in part, reverse in part, and remand to the trial court as set forth below.

The facts are essentially undisputed. On March 23, 1995, Marshall Carter (“Carter”), the

owner of 7-11 Installation & Service, Inc. (“7-11 Installation”), submitted a proposal to Mike

Williams (“Williams”), owner of Mike’s Food Value and Westmoreland Bi-Rite, for the sale and

installation of refrigeration equipment. The proposal quoted $66,200 for the refrigeration equipment

and $40,000 for materials and labor for the installation of the equipment. Williams subcontracted

1 Rule 10 (Rules of the Court of Appeals of Tennessee).--(b) Memorandum Opinion. The Court, with the concurrence of all judges participating in the case, may affirm, reverse or modify the actions of the trial court by memorandum opinion when a formal opinion would have no precedential value. When a case is decided by memorandum opinion it shall be designated “MEMORANDUM OPINION,” shall not be published, and shall not be cited or relied on for any reason in a subsequent unrelated case. the refrigeration work to 7-11 Installation as part of a construction project which was designed to

add 5,000 square feet to the grocery store.

Neither party signed the proposal, although Williams concedes that he orally agreed to it.

The proposal did not state the date by which the installation of the equipment was to be completed.

However, the proposal stated:

All material is guaranteed to be as specified. All work to be completed in a workmanlike manner according to standard practices. Any alteration or deviation from specifications below involving extra costs will be executed only upon written orders, and will become an extra charge over and above the estimate. All agreements contingent upon strikes, accidents or delays beyond our control . . . . (emphasis added).

On March 28, 1995, Carter delivered the first load of equipment to the grocery store, with

the final delivery of the equipment on May 4, 1995. Williams paid for half of the equipment when

7-11 Installation made the initial delivery and paid the remaining amount owed upon final delivery

on May 4. The equipment was stored in a rented trailer on site.

However, prior to the excavation work in preparation for construction, Williams encountered

a boundary line dispute with the adjacent property owner involving a six foot strip of property

behind the store. On May 4th, the date of the final delivery, Williams told Carter about the delay.

Carter observed that no work had commenced on the property, and Carter had not been paid for any

labor costs. The parties did not discuss whether the delay would affect Carter’s performance. The

boundary line dispute required four to six weeks to resolve.

In addition, in May, upon final delivery of the equipment, Williams requested 7-11

Installation to install a walk-in freezer as well as move old equipment in preparation for construction

to begin on the new addition. 7-11 Installation installed the walk-in freezer that month. The walk-in

freezer was included in the equipment list as part of the proposal.

In approximately the third week of June 1995, another subcontractor began the excavation

of dirt and rock in preparation for construction. This was completed ten days later. Williams then

scheduled a meeting for July 10, 1995, with Carter, the contractor, and the plumbing and electrical

workers. Carter did not attend the meeting. On July 11, Williams called 7-11 Installation. On July

14, Williams was told that 7-11 Installation had sold its assets to Maynard Fixturecraft, and that 7-11

Installation would not be conducting any further business. The record reflects that Carter sold 7-11

2 Installation to Maynard Fixturecraft by agreement dated July 13, 1995. The agreement included a

non-compete clause regarding Carter.

Subsequently, Williams executed a contract with Maynard Fixturecraft to complete the

installation of the refrigeration equipment. Williams paid Maynard Fixturecraft $53,390 for labor,

$13,390 more than the $40,000 in labor costs to which 7-11 Installation had agreed. Maynard

Fixturecraft performed some of the work in August 1995, and completed the project in October

1995.

Williams then filed this lawsuit against 7-11 Installation and Bud Carter, personally, to

recover the difference between the amount paid to Maynard Fixturecraft and 7-11 Installation’s

contract price. 7-11 Installation and Carter filed a counter-complaint denying liability on the breach

of contract claim, and Carter denied personal liability on the claim. In addition, 7-11 Installation

and Carter sought damages for equipment storage expenses and for the installation of the walk-in

freezer.

At trial, Carter testified that he believed that installation would be completed within four to

five weeks after the final delivery date. He testified that it is customary in a refrigeration contract

to perform within approximately sixty days of agreeing on the proposal. Williams testified that he

expected Carter to install the equipment within thirty to sixty days after the parties orally agreed to

the proposal on March 28, 1995.

The record does not indicate why Maynard’s labor costs were $13,390 more than 7-11

Installation’s quoted labor costs. Williams testified that he received a bid from Maynard at the time

he received 7-11 Installation’s bid. Williams testified that Maynard’s bid at that time was “quite a

bit higher,” but could not recall the amount of Maynard’s original bid. 7-11 Installation argues that

Maynard’s labor costs were higher because the work Maynard finally did for Williams was done on

an emergency basis, since Williams’ store was closed while the work was being done and that the

store closure cost him considerably. Williams acknowledges some time impetus; he took Maynard’s

bid after 7-11 Installation was out of business because Maynard was in a position to begin work

immediately. However, there is no proof that the amount of Maynard’s bid was affected by this

factor. Nevertheless, Carter testified that 7-11 Installation’s labor costs would have increased if he

had been required to do the work on an emergency basis, to pay for unanticipated overtime.

3 The trial court issued an oral ruling from the bench in favor of Williams in the amount of

$7,323. The trial court held that both 7-11 Installation and Carter were liable on the breach of

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Buice v. Scruggs Equipment Co.
267 S.W.2d 119 (Court of Appeals of Tennessee, 1953)
Airline Construction, Inc. v. Barr
807 S.W.2d 247 (Court of Appeals of Tennessee, 1990)
Hamblen County v. City of Morristown
656 S.W.2d 331 (Tennessee Supreme Court, 1983)
Minor v. Minor
863 S.W.2d 51 (Court of Appeals of Tennessee, 1993)
Moore Construction Co. v. Clarksville Department of Electricity
707 S.W.2d 1 (Court of Appeals of Tennessee, 1986)
Turner v. Yow
657 S.W.2d 94 (Court of Appeals of Tennessee, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
Williams v. 7-11, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-v-7-11-tennctapp-1999.