Williams Pipe Line Co. v. City of Mounds View

651 F. Supp. 551, 1987 U.S. Dist. LEXIS 1408
CourtDistrict Court, D. Minnesota
DecidedJanuary 7, 1987
DocketCiv. 4-86-648, 4-86-651 and 4-86-656
StatusPublished
Cited by11 cases

This text of 651 F. Supp. 551 (Williams Pipe Line Co. v. City of Mounds View) is published on Counsel Stack Legal Research, covering District Court, D. Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williams Pipe Line Co. v. City of Mounds View, 651 F. Supp. 551, 1987 U.S. Dist. LEXIS 1408 (mnd 1987).

Opinion

DIANA E. MURPHY, District Judge.

On July 8, 1986, a portion of a petroleum pipeline owned by Williams Pipe Line Company (Williams) failed. A resulting explosion and fire killed two people and badly injured a third. The accident also caused property and environmental damage. These related law suits are only part of ongoing proceedings relating to the accident and operation of the pipeline.

By order dated August 22, 1986, 651 F.Supp. 544, this court denied motions of the County of Ramsey and the City of Mounds View for orders restraining Williams from testing or restarting the pipeline. 1 The court granted Williams a limited temporary restraining order barring *553 the other parties from interfering with preparation for testing the pipeline. Subsequently, the parties reached agreements permitting Williams to test the pipeline. See Stipulations and Orders of September 16 and 17, 1986. The matter is now before the court on motions by all parties for preliminary injunctions. Williams asks that the court enjoin the other parties from interfering with the reopening and operation of the line. 2 Ramsey County and Mounds View seek to enjoin operation of the pipeline. The county’s proposed injunction would bar resumption of operations without its permission. Mounds View’s proposed injunction would prevent reopening of the pipeline during the pendency of this litigation.

Background

These preliminary findings of fact are drawn from a number of sources. There have been two evidentiary hearings in this court. The parties have also submitted substantial other materials, including affidavits, scientific papers, photographs, volumes of testimony taken in other settings, graphs, charts, press releases, and numerous letters. Many of the material facts are uncontested, but others are vigorously disputed. The parties’ positions are unfortunately not always clear.

A. History of the Pipeline

Williams operates hazardous liquid pipelines in 12 states. It acquired Line 2N from the Great Lakes Pipeline Company in 1966. This line runs from the Roseville Terminal, in or near Minneapolis, Minnesota to Duluth, Minnesota and Superior, Wisconsin. In 1957, prior to Williams’ acquisition of the line, Ramsey County and several private land owners had granted permission to the predecessor company to construct approximately ten miles of the pipeline through their property. 3 The county resolution granting permission to lay two and one-half to three miles of pipe through a county right-of-way along Long Lake Road contained certain conditions: the company was to “remove, reinstall, or repair such pipe when in the opinion of the County Engineer or the Board of County Commissioners such removal, installation or replacement shall be advantageous to the people of this County.” The company was also to give notice of any intended excavation, maintenance or removal and to perform such work under the supervision of the county engineer. The county engineer had the right to “make all rules with respect to possible hazards as he shall deem necessary and advisable.”

The pipe comprising Line 2N is electric resistance weld (ERW) pipeline manufactured by Jones and Laughlin Co. in the late 1950’s. Such ERW pipeline was made from flat steel. The steel was formed into pipe and then welded at a seam, first by use of an electric current and then by use of heat. These seam welds make ERW pipe different from other line pipe materials manufactured in past decades. 4 See J. Kiefner, Evaluating Pipeline Integrity-Flaw Behavior During and Following High Pressure Testing (1986). While most pipes are “tough, ductile materials,” id., the weld zones of some ERW materials are not. As a result, failure in ERW pipes differs from that in most pipes. While extension of a defect “may take the form of slow stretching and tearing if the material is relatively tough and ductile, ... it may take the form of sudden short burst of cracking if the material is not particularly tough and ductile, possibly leading to complete failure.” Id. Some have questioned the integrity of these pipes. Federal law does not forbid their use.

*554 The record contains little evidence of Williams past leak and safety record in Minnesota. The company has publicly stated that it has experienced 55 pipeline leaks and 34 station or terminal leaks in its Minnesota pipeline during the last 10 years. Of the pipeline leaks, 24 involved coated pipeline, such as those at issue here. These leaks apparently had a variety of causes, some wholly outside Williams’ control. Two previous failures — one on Line 2N and one on the Newport Villas line, involved weld seam splits in ERW pipe. In both cases, Williams concluded that the failures resulted from manufacturing defects. There is no evidence in the record to suggest that any of the leaks prior to July 1986 caused serious injury or loss of life.

Williams tested Line 2N in 1984. Seventeen sections of the pipeline failed, most of them as a result of seam failures. Only a limited investigation of those failures was made. After replacing the failed sections, Williams successfully hydrostatically tested the line at approximately 1900 p.s.i.g. 5

B. Federal Regulation

Interstate hazardous liquid pipeline safety is regulated by the United States Department of Transportation (DOT). Under the Hazardous Liquid Pipeline Safety Act of 1979 (HLPSA), 49 U.S.C. §§ 2001-2014 which was enacted in 1979, the Secretary of DOT (the Secretary) must establish and enforce safety regulations for construction of new pipelines and the operation and maintenance of existing pipelines. The Secretary regulates pipeline safety under HLPSA and its companion statute, the Natural Gas Pipeline Safety Act of 1968 (NGPSA), 49 U.S.C. §§ 1671-1686 (enacted 1968), through the Office of Pipeline Safety (OPS) which is part of the Research and Special Programs Administration (RSPA). OPS has direct responsibility for enforcement of HLPSA and the safety regulations promulgated under it. See generally 49 C. F.R. §§ 190.1-195.440. The National Transportation Safety Board (NTSB), which also plays an important role in this case, is not a regulatory agency. NTSB is “an independent Government Agency located with the Department of Transportation [established] to promote transportation safety by conducting independent accident investigations and by formulating safety improvement recommendations.” 49 U.S.C. § 1901(1).

There is very little evidence about past contact between Williams and OPS.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Laclede Gas Company v. St. Charles County
713 F.3d 413 (Eighth Circuit, 2013)
Olympic Pipe Line Co. v. City of Seattle
316 F. Supp. 2d 900 (W.D. Washington, 2004)
Stutler v. Marathon Pipe Line Co.
998 F. Supp. 968 (S.D. Indiana, 1998)
Opinion No. (1997)
Nebraska Attorney General Reports, 1997
Sierra Club v. United States Department of Energy
734 F. Supp. 946 (D. Colorado, 1990)
Williams Pipe Line v. City of Mounds View, Minn.
704 F. Supp. 914 (D. Minnesota, 1989)
United States v. Rainbow Family
695 F. Supp. 314 (E.D. Texas, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
651 F. Supp. 551, 1987 U.S. Dist. LEXIS 1408, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-pipe-line-co-v-city-of-mounds-view-mnd-1987.