Williams Natural Gas Company v. Federal Energy Regulatory Commission, Missouri Public Service Commission, Intervenor

90 F.3d 531, 319 U.S. App. D.C. 308, 1996 U.S. App. LEXIS 18931
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 2, 1996
Docket95-1472
StatusPublished
Cited by4 cases

This text of 90 F.3d 531 (Williams Natural Gas Company v. Federal Energy Regulatory Commission, Missouri Public Service Commission, Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williams Natural Gas Company v. Federal Energy Regulatory Commission, Missouri Public Service Commission, Intervenor, 90 F.3d 531, 319 U.S. App. D.C. 308, 1996 U.S. App. LEXIS 18931 (D.C. Cir. 1996).

Opinion

Opinion for the Court filed by Circuit Judge TATEL.

TATEL, Circuit Judge:

A gas pipeline petitions for review of a Federal Energy Regulatory Commission order requiring it to refund interest collected from its customers for the period between the Commission’s approval of the tariff and the date the pipeline eventually billed its customers. Finding that the Commission reasonably concluded that the pipeline’s tariff did not authorize interest collection in cases of delayed billing and that the pipeline lacked adequate justification for delaying billing, we deny the petition for review.

I.

Williams Natural Gas, a gas pipeline, sought to recover from its local distribution company customers a portion of its long-term “take-or-pay” liabilities. As we explained in Baltimore Gas & Electric Company v. FERC, “‘to maintain inventories for [their] sales customers,’ ” pipelines like Williams entered into contracts requiring them “ ‘either to take or to pay for the gas [they] ha[ve] contracted to buy’ ” from natural gas producers. 26 F.3d 1129, 1132 (D.C.Cir.1994) (quoting Public Util. Comm’n v. FERC, 988 F.2d 154, 157 (D.C.Cir.1993)). Pipelines entered into these contracts in the 1970s when demand for gas was high. When demand fell in the 1980s, many pipelines found themselves obligated to purchase more gas than they could re-sell. Id. To address this problem, the Commission issued Order No. 500, allowing pipelines to shift some of their liability under these contracts to producers, consumers, and downstream pipelines. See Order No. 500, Regulation of Natural Gas Pipelines after Partial Wellhead Decontrol, 52 Fed.Reg. 30,334, at 30,342-43 (1987). The order allowed pipelines to recover twenty-five to fifty percent of their take-or-pay costs through a fixed charge if they agreed to absorb an equal amount themselves. Id. Pipelines choosing to recover a portion of their costs through a fixed charge could recover the remaining amount through a volumetric surcharge on each unit of gas sold. Id. at 30,343.

This ease arises from a series of Williams filings and Commission orders over the 10-month period from March 1989 to January 1990. In the first filing, on March 31, 1989, Williams proposed absorbing twenty-five percent of its $41.7 million in take-or-pay settlement costs, billing twenty-five percent to its customers through a fixed charge, and recovering the remaining fifty percent through a volumetric surcharge. On April 28, the Commission accepted Williams’s tariff effective May 1 subject to certain refunds and conditions. Williams Natural Gas Co., 47 F.E.R.C. ¶ 61,155, reh’g granted in part and denied in part, 48 F.E.R.C.1161,079 (1989). To comply with the conditions of the April 28 order and to recover an additional $4.38 million in take-or-pay settlement costs, Williams filed its second tariff on June 14. The Commission accepted this second tariff effective July 1, again subject to certain refunds and conditions. Williams Natural Gas Co., 48 F.E.R.C. ¶ 61,046 (1989). After Williams revised its tariff several more times to comply with the Commission’s conditions, the Commission accepted the tariff in a letter order issued in January 1990. To recover an additional $4.1 million in take-or-pay settlement costs, Williams filed its third tariff on August 31, 1989. The Commission accepted this filing effective September 1, again subject to refunds. Williams Natural Gas Co., 48 F.E.R.C. ¶ 61,395, reh’g denied by operation of law, 49 F.E.R.G-¶ 61,273 (1989).

Following the first tariffs effective date— May 1, 1989 — Williams immediately began billing its customers for the volumetric surcharge portion of its take-or-pay costs. But it did not begin billing the fixed charge portion of the settlement costs until thirteen *533 months later, June 1, 1990. Williams included in those bills interest on the settlement costs for the entire thirteen months, totaling $1,088,254.

Following a routine audit of Williams’s books and records, the Commission’s accounting office recommended that Williams refund the $1,088,254 in interest to its customers. When Williams objected, the Commission set the matter for a hearing before an administrative law judge. Relying primarily on several Commission decisions forbidding pipelines from collecting interest when they voluntarily delay billing, the ALJ ordered Williams to refund the interest. Williams Natural Gas Co., 62 F.E.R.C. ¶ 63,027, at 65,133-35 (1993) (initial decision). The ALJ rejected Williams’s argument that the tariff authorized collection of interest in the case of delayed billing, finding the tariff silent on this matter. Id. at 65,136. The ALJ was equally unpersuaded by Williams’s argument that because it lacked a final Commission order and had internal administrative difficulties, it could not issue bills when the tariffs became effective. According to the ALJ, “subsequent Commission actions modif[ying] Williams’ initial proposals” should not have operated as a “bar to billing”: Williams could have issued initial bills on May 1st, and then made refunds or adjustments later to comply with subsequent Commission orders. Id. at 65,135-36.

The Commission adopted the ALJ’s reasoning and affirmed. Williams Natural Gas Co., 69 F.E.R.C. ¶ 61,049 (1994) (order affirming initial decision). Denying Williams’s petition for rehearing, the Commission emphasized that the pipeline’s tariff did not provide for the “specific circumstances of this ease.” 72 F.E.R.C. ¶ 61,135, at 61,703 (1995). In response to Williams’s argument that it lacked a final order, the Commission pointed out that the pipeline had billed the volumetric portion of the surcharge even though subject to adjustment and that, as Williams concedes, it had a final order in January 1990 yet did not bill until five months later. Id. at 61,704. Williams now petitions for review.

II.

We uphold the Commission’s order if it “is supported by substantial evidence and reached by reasoned decisionmaking— that is, a process demonstrating the connection between the facts found and the choice made.” ANR Pipeline Co. v. FERC, 771 F.2d 507, 516 (D.C.Cir.1985) (per curiam). Recognizing that “ ‘Congress explicitly delegated to FERC broad powers over ratemak-ing, including the power to analyze relevant contracts,’” we give “substantial deference” to the Commission’s interpretation of filed tariffs. Natural Gas Clearinghouse v. FERC, 965 F.2d 1066, 1070 (D.C.Cir.1992) (quoting Tarpon Transmission Co. v. FERC, 860 F.2d 439, 441-42 (D.C.Cir.1988)). At the same time, we do not accept the Commission’s interpretation of a tariff unless it is ‘“amply supported both factually and legally.’ ” Tarpon, 860 F.2d at 442 (quoting Vermont Dep’t of Pub. Serv. v. FERC, 817 F.2d 127, 134 (D.C.Cir.1987)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
90 F.3d 531, 319 U.S. App. D.C. 308, 1996 U.S. App. LEXIS 18931, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-natural-gas-company-v-federal-energy-regulatory-commission-cadc-1996.