William S. Happel, Doing Business as Happel Contracting Company v. United States

279 F.2d 88, 1960 U.S. App. LEXIS 4286
CourtCourt of Appeals for the Eighth Circuit
DecidedJune 14, 1960
Docket16412
StatusPublished
Cited by4 cases

This text of 279 F.2d 88 (William S. Happel, Doing Business as Happel Contracting Company v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
William S. Happel, Doing Business as Happel Contracting Company v. United States, 279 F.2d 88, 1960 U.S. App. LEXIS 4286 (8th Cir. 1960).

Opinion

GARDNER, Circuit Judge.

Appellant, a contractor engaged in excavating and grading, brought this action to recover on a contract with the United States for doing certain excavating and filling along the Mississippi River in Perry County, Missouri, described in the record as the construction of a riverside berm revetment and repair to borrow pits. It was the contention of appellant that he was entitled to recover $8,835.37 for borrow pit fill, in addition to the amount paid him by the Government. We shall hereinafter refer to appellant as plaintiff and to appellee as the Government or defendant.

Defendant did not file answer but instead filed a motion for summary judgment based upon various documents and exhibits, including the complaint, the contract, and a certified copy of the transcript of the proceedings before the contracting officer and the Board of Contract Appeals.

The contract between the parties was a standard form Government construction contract, and, among others, contained the following provisions:

“6. Disputes. Except as otherwise provided in this contract, any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the Contracting Officer, who shall reduce his decision to writing and mail or otherwise furnish a copy thereof to the Contractor. Within 30 days from the date of receipt of such copy, the Contractor may appeal by mailing or otherwise furnishing to the Contracting Officer a written appeal addressed to the head of the department, and the decision of the head of the department or his duly authorized representatives for the hearings of such appeals shall, unless determined by a court of competent jurisdiction to have been fraudulent, arbitrary, capricious, or so grossly erroneous as necessarily to imply bad faith, be final and conclusive: Provided, That, if no such appeal to the head of the department is taken, the decision of the Contracting Officer shall be final and conclusive.”

The contract also contained provision that:

“In the event of a dispute as to the amount of any adjustment under this paragraph, the matter shall be treated as a question of fact to be determined in accordance with the ‘Disputes’ clause of this contract.”

Following the completion of his work plaintiff requested that a decision of the contracting officer be issued pursuant to Article 6, supra, as to work performed by plaintiff under the contract. In support of his claim for additional compensation plaintiff made a survey of the newly excavated borrow pit and submitted his mathematical calculations based thereon. The contracting officer, in passing upon plaintiff’s claim for additional compensation, held:

“b. The area where the Contractor performed his measurement was at an area different from that prescribed in the contract for measurement, namely the borrow pits instead of the scoured areas. Since the Contractor’s measurement was in a wholly different area from that provided for measurement under TP 2-08 (a) (1) of the contract, it has no effect on the payment under the contract.
“c. Apparently the Contractor has a misinterpretation of the term ‘actual quantity’ as used in SC-03 of the contract. The term ‘actual quantity’ as used means the quantity determined by the Government’s survey of each scoured area, *90 before the fill has been placed therein, on the basis of the net yardage between the ground surface determined by such survey and the lines and elevations shown on the contract drawings or such modification thereof as directed by the Contracting Officer. Yardage was computed by the average end area method from planimetered cross-sections in accordance with TP 2-08 (a) (1) of the contract and was determined to be 186,386 cubic yards as set forth in paragraphs 5 and 6 of the inclosed findings of fact. The amount considered by the Contracting Officer as the ‘actual quantity’ is 186,-386 cubic yards, and since this does not vary from the ‘estimated quantity’ of 172,000 cubic yards by more than 20 percent, SC-03 of the contract has no application in this case.
“d. The key to the situation lies in TP 2-08 (a) (1) and (2) and TP 2-08 (b) (1). In TP 2-08 (a) (1) there is provided the means of measurement of borrow pit fill for payment. There is no other provision in the contract for such measurement. The estimated quantity of 172,000 cubic yards was not to be relied on by the Contractor as the actual amount of fill to be moved; however, when he received the Government’s measurements, he knew or should have known, that the scoured areas would not and could not be remeasured after the fill was placed. At that time, he had the ‘actual quantity’ for which he would be paid. TP 2-08 (a) (2) gave the Contractor the right, under circumstances stated therein, to request the Government to resurvey prior to placing fill, which right he did not exercise. TP 2-08(b) (1) specifically provides that excavation from borrow areas or ditches or any other excavation used for borrow pit fill, regardless of the source, will not be measured for payment. It was not until 13 March 1957, long after the contract was completed, that the Contractor questioned the amount of compensation for' borrow pit fill.
“Considering the foregoing, there is no basis for allowing the Contractor’s requests. Further, the Contracting Officer has no power to reform the contract, which is what the Contractor seems to be seeking.
“You are hereby advised that the foregoing constitutes the final decision of the Contracting Officer pursuant to Article 6, Disputes, of the contract. Your attention is invited to your right to appeal from this decision within 30 days from the date of your receipt of this letter.”

As indicated by the decision of the contracting officer, the contract contained provision to the effect that:

“Should the actual quantity of work performed under any of these items vary from the estimated quantity by more than 20%, a contract modification will be issued adjusting the estimated quantity and the estimated contract price, and an adjustment in the unit price for that item may be made * *

and since the amount as determined by the Government survey did not vary from the estimated quantity by more than 20% there was no basis for contract modification.

From this decision plaintiff had a right of appeal to the Board of Contract Appeals within 30 days of notice. Copy of the contracting officer’s decision was served on plaintiff by registered mail pursuant to the terms of the contract. No appeal was perfected within the time limited, but thereafter he attempted such an appeal, which the Board of Contract Appeals dismissed as not being timely.

The trial court, in sustaining defendant’s motion for a summary judgment, held that the amount of work performed by plaintiff and the quantity of borrow pit fill was a question of fact and hence, under the terms of the contract, where no appeal has been perfected from the decision of the contracting officer, “the decision of the Contracting Officer shall *91

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
279 F.2d 88, 1960 U.S. App. LEXIS 4286, Counsel Stack Legal Research, https://law.counselstack.com/opinion/william-s-happel-doing-business-as-happel-contracting-company-v-united-ca8-1960.