Kiewit Western Co. v. City & County of Denver

902 P.2d 421, 18 Brief Times Rptr. 2236, 1994 Colo. App. LEXIS 392, 1994 WL 716909
CourtColorado Court of Appeals
DecidedDecember 29, 1994
Docket93CA1160
StatusPublished
Cited by8 cases

This text of 902 P.2d 421 (Kiewit Western Co. v. City & County of Denver) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kiewit Western Co. v. City & County of Denver, 902 P.2d 421, 18 Brief Times Rptr. 2236, 1994 Colo. App. LEXIS 392, 1994 WL 716909 (Colo. Ct. App. 1994).

Opinion

Opinion by

Judge RULAND.

Plaintiff, Kiewit Western Co., appeals from a judgment dismissing its complaint for declaratory and other relief against defendants, City and County of Denver, the Department of Public Works (Department), and Michael Musgrave in his capacity as acting Manager of the Department. We affirm.

The Department advertised for sealed bids to excavate for two runways at the Denver International Airport. It determined that plaintiffs bid was the lowest responsive bid for each of the runways, and accordingly, it awarded plaintiff both contracts. One of the contracts required payment to plaintiff in the approximate amount of $45 million and the other in the approximate amount of $23 million.

Each of the contracts contained a “changes in the work” procedure for plaintiff to obtain additional compensation. Specifically, claims for additional compensation were permitted if plaintiff discovered design errors, if it encountered differing site conditions than those represented by defendants, if there was delay in the progress of the work caused by defendants, and if any other circumstance arose which necessitated a change in the time of performance or payment.

The contracts specified time limits for submitting change orders requesting additional compensation. Each request was first reviewed by the Resident Engineer. If denied, the request had to be submitted to the Construction Manager. Upon denial by that official, a protest was required to the Assistant Director of Aviation, and thereafter to the Manager of Public Works (Manager).

If a claim for additional compensation was ultimately denied, the contracts provided that “disputes regarding this contract shall be resolved by administrative hearing under [the] procedures described in [Denver] Revised Municipal Code Section 56-106.” This provision authorized the Manager to designate a hearing officer to conduct a hearing relative to any dispute. The hearing officer’s decision was binding unless a written request for review by the Manager was made.

If the Manager approved a decision of the hearing officer adverse to plaintiff, plaintiff was authorized to seek judicial review pursuant to C.R.C.P. 106.

Plaintiff filed its complaint asserting 14 claims for relief. In its first two claims, plaintiff asserted that the claims submissions and dispute resolution procedures described above (the Procedures) were ultra vires as not authorized by the Colorado Constitution and the Denver City Charter. Plaintiff also alleged that the Procedures violated plaintiffs rights to due process under the Colorado and United States Constitutions because a fair and impartial hearing procedure was not required at the administrative level.

In its remaining claims for relief, plaintiff alleged that defendants were guilty of misrepresentations concerning the project prior to submission of plaintiffs bid and in conjunction with certain change orders. Plaintiff also alleged that defendants breached both implied warranties relative to site conditions and the covenant of good faith and fair *423 dealing, and had imposed “cardinal changes” to the work not contemplated by the original contracts.

On the basis of these allegations, plaintiff requested that it be awarded a quantum meruit recovery and damages.

In response to the complaint, defendants filed a motion to dismiss pursuant to C.R.C.P. 12(b)(5). As pertinent here, defendants requested that the first two claims for relief be dismissed on the basis that the Procedures were valid and binding. Defendants requested dismissal of the remaining claims on the basis that plaintiff had failed to follow the Procedures in the contracts and that, therefore, plaintiff had failed to exhaust its contractual remedies.

Based upon the parties’ submissions, the trial court agreed with both of defendants’ contentions and dismissed the complaint.

I

Plaintiff first contends that the trial court erred in dismissing its first claim for relief based upon the conclusion that the Procedures contained in the contracts were authorized by Colo. Const. art. XX, § 1 and Denver City Charter eh. A, art. II. Each of the cited provisions addresses the construction of Denver’s public works but neither specifically authorizes the City to include the Procedures in public works contracts. We conclude that it is unnecessary to address this contention.

Generally, appellate courts will not address the constitutionality of a statute or ordinance if the controversy can be resolved on other grounds. See Ricci v. Davis, 627 P.2d 1111 (Colo.1981); State v. American Can Co., 117 Colo. 312, 186 P.2d 779 (1947). Based upon plaintiffs allegations in its complaint, we conclude that principles of contract estoppel apply and require affirmance of the order entered by the trial court on this issue.

In City of Colorado Springs v. Kitty Hawk Development Co., 154 Colo. 535, 392 P.2d 467 (1964), cert. denied, 379 U.S. 647, 85 S.Ct. 612, 13 L.Ed.2d 551 (1965), our supreme court addressed the application of contract estoppel in conjunction with a municipal contract. Kitty Hawk owned property adjacent to the City and entered into a contract with the City for annexation of that property in order to obtain water and sewer service. The contract required Kitty Hawk either to convey certain property to the City or to pay cash in an amount equal to eight percent of the value of the annexed land, at the option of the City.

Following performance of the contract by each of the parties, Kitty Hawk sued to recover the cash payment requested by the City on the basis that the contract provision requiring payment was unconstitutional and ultra vires. The court noted that the City was under no obligation to furnish water or sewer services to anyone outside its corporate limits. Thus, the court determined that no governmental power was bargained for in the contract, and there were no constitutional rights surrendered by Kitty Hawk in the transaction. Further, the court concluded that there were no statutory or constitutional provisions which prohibited imposing a compensation provision in the annexation agreement.

As a result, the court determined that, having received and retained the benefits under the contract, Kitty Hawk was estopped to assert that the compensation provision of the contract was ultra vires or unconstitutional. The rationale in Kitty Hawk was followed by a division of this court in Lone Pine Corp. v. City of Fort Lupton, 653 P.2d 405 (Colo.App.1982).

We view the rule in Kitty Hawk as instructive in resolving plaintiffs contention here.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Luck Brothers v. Agency of Transportation
2014 VT 59 (Supreme Court of Vermont, 2014)
Extreme Construction Co. v. RCG Glenwood, LLC
2012 COA 220 (Colorado Court of Appeals, 2012)
First Christian Assembly of God v. City and County of Denver
122 P.3d 1089 (Colorado Court of Appeals, 2005)
Castle Rock Construction Co. v. Department of Transportation
74 P.3d 491 (Colorado Court of Appeals, 2003)
In Re J.D. Edwards World Solutions Co.
87 S.W.3d 546 (Texas Supreme Court, 2002)
Austin v. U S West, Inc.
926 P.2d 181 (Colorado Court of Appeals, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
902 P.2d 421, 18 Brief Times Rptr. 2236, 1994 Colo. App. LEXIS 392, 1994 WL 716909, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kiewit-western-co-v-city-county-of-denver-coloctapp-1994.