William A. Gross Construction Associates, Inc. v. American Manufacturers Mutual Insurance

262 F.R.D. 354, 2009 U.S. Dist. LEXIS 106315, 2009 WL 3536615
District Court, S.D. New York·Decided November 2, 2009·No. No. 07 Civ. 10639(LAK)(AJP)·Published·Cited by 11 cases

Opinion

OPINION AND ORDER

ANDREW J. PECK, United States Magistrate Judge.

The background to this litigation is set forth in my three prior decisions in this case, familiarity with which is assumed. William A. Gross Constr. Assoc., Inc. v. American Mfrs. Mut. Ins. Co., 07 Civ. 10639, 2009 WL 427280 (S.D.N.Y. Feb.23, 2009) (Peck, M.J.); William A. Gross Constr. Assoc., Inc. v. American Mfrs. Mut. Ins. Co., 600 F.Supp.2d 587 (S.D.N.Y.2009); and William A. Gross Constr. Assoc., Inc. v. American Mfrs. Mut. Ins. Co., 256 F.R.D. 134 (S.D.N.Y.2009).

Presently before the Court is the motion (Dkt. No. 476) of fifth-party defendants and sixth-party plaintiffs Rafael Vinoly Architects, P.C., DMJM H & N, Inc. and Rafael Vinoly Arehitects/DMJM Architects and Engineers, a Joint Venture (collectively, “RVA/DMJM”) to compel production of certain documents involving claims analysis performed by non-party Hill International, Inc., a company retained by fourth-party defendant and fifth-party plaintiff Dormitory Authority of the State of New York (“DAS-NY”).1 In the alternative, RVA/DMJM seeks in camera review of the documents to determine if privilege was properly asserted. (Dkt. No. 476: RVA/DMJM Motion; see Dkt. No. 477: RVA/DMJM Br. at 1.)

For the reasons set forth below, RVA/ DMJM’s motion is DENIED.

FACTS

This case involves a multi-million dollar dispute over alleged defects and delays in the construction of the Bronx County Hall of Justice, also known as the Bronx Criminal Court Complex. The Dormitory Authority of the State of New York (“DASNY”) was the “owner” of the project. DASNY retained non-party Hill under two different contracts to perform two different services: (a) to provide construction management services, and (b) to assist counsel by reviewing and analyzing claims submitted by various contractors. DASNY has produced documents relating to the former but withheld the latter as privileged.

In the mid-1990’s, the City of New York, in conjunction with the New York State Office of Court Administration, determined that a new criminal justice facility was required in the Bronx. (Dkt. No. 485: Weissman Aff. ¶ 3.) The approximately 775,000 square foot facility, consisting of courtrooms, offices, a jury assembly building, and a parking garage, had an anticipated initial cost of approximately $325 million and was initially slated to open in 2005. (Weissman Aff. ¶ 4.) DASNY assumed control over the project in 2000 and shortly thereafter entered into several contracts for the design and construction of the facility. (Weissman Aff. ¶ 5.) “DASNY contracted with at least 17 different prime contractors for construction of the Project .... [and,] each agreement contained General Conditions that were either identical or substantially similar.” (Dkt. No. 479: D’Al-essandro Aff. ¶ 18 & Ex. J: General Conditions.)

Article 8 of the General Conditions governs “Changes in the Work.” (See D’Alessan-dro Aff. Ex. J: General Conditions Art. 8.) Section 8.01(A) provides that “[without invalidating the Contract, the Owner [i.e., DASNY] may order Extra Work or make changes by altering, adding to, or deducting from the Work, the Contract consideration being adjusted accordingly.” (General Conditions § 8.01(A).) Section 8.01(B) provides:

The amount by which the Contract consideration is to be increased or decreased by any change order may be determined by the Owner [DASNY] by one (1) or more of the following methods:
[356]*3561. By applying the applicable unit price or prices contained in the Contract.
2. By estimating the fair and reasonable
cost of the extra work____
3. By determining the actual cost of the Extra Work....

(General Conditions § 8.01(B).)

Article 11 of the General Conditions addresses the procedure by which contractors’ claims for extra work or delays will be addressed by DASNY. (General Conditions at Art. 11.) Under Section 11.01, a contractor who claims that DASNY ordered extra work beyond the terms of the contract must:

1. Promptly comply with the [work] order.
2. File with [DASNY] ... a written notice of the basis of the Contractor’s claim, including estimated cost, and request for a determination thereof.
3. Proceed diligently, pending and subsequent to the determination of [DASNY] with respect to any said disputed matter, with the performance of the Work in accordance with all instructions of [DASNY],

(General Conditions § 11.01(A).) Section 11.02 of the General Conditions deals with delay claims, as follows:

No claims for increased costs, charges, expenses or damages of any kind shall be made by the Contractor against [DASNY] for any delays or hindrances from any cause whatsoever, provided that [DASNY], in [DASNY]’s discretion, may compensate the Contractor for any said delays by extending the time for completion of the Work as specified in the Contract.

(General Conditions § 11.02.) Section 11.03 of the General Conditions provides:

Any decision or determination of the Consultant, [DASNY] or [DASNY’s] Representative shall be final, binding and conclusive on the Contractor unless the Contractor shall, within ten (10) working days after said decision, make and deliver to [DASNY] a verified written statement of the Contractor’s contention that said decision is contrary to a provision of the Contract. [DASNY] shall determine the validity of the Contractor’s contention.

(General Conditions § 11.03.)2

Commencing in 2002, DASNY contracted with fifth party defendant Bovis Lend Lease, LMB, Inc. for construction management services. The services Bovis was required to provide as construction manager included:

10. Claims

Analyze and evaluate all claims for Contract time extension or cost adjustment. Make recommendations to [DASNY] for resolution, approval, or disapproval.

(Dkt. No. 478: Semetis Aff. ¶3 & Ex. 1: Bovis Construction Mgmt. Contract Appendix A, Scope of Services, ¶ 10.) “Bovis indeed provided this service to DASNY during the time that Bovis performed work on the Project.” (Semetis Aff. ¶ 4; see also id. ¶ 6.) “Bovis has produced all of this discovery, which includes records relating to Bovis’ claims analysis pursuant to its Contract, without any claim of privilege.” (Semetis Aff. ¶ 6.)

Free access — add to your briefcase to read the full text and ask questions with AI

William A. Gross Construction Associates, Inc. v. American Manufacturers Mutual Insurance, 262 F.R.D. 354, 2009 U.S. Dist. LEXIS 106315, 2009 WL 3536615 (S.D.N.Y. 2009).

262 F.R.D. 354 (William A. Gross Construction Associates, Inc. v. American Manufacturers Mutual Insurance) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related