Wicor, Inc. v. United States

116 F. Supp. 2d 1028, 86 A.F.T.R.2d (RIA) 6567, 2000 U.S. Dist. LEXIS 15813, 2000 WL 1531583
CourtDistrict Court, E.D. Wisconsin
DecidedSeptember 28, 2000
Docket97-C-393
StatusPublished
Cited by1 cases

This text of 116 F. Supp. 2d 1028 (Wicor, Inc. v. United States) is published on Counsel Stack Legal Research, covering District Court, E.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wicor, Inc. v. United States, 116 F. Supp. 2d 1028, 86 A.F.T.R.2d (RIA) 6567, 2000 U.S. Dist. LEXIS 15813, 2000 WL 1531583 (E.D. Wis. 2000).

Opinion

DECISION AND ORDER

GOODSTEIN, United States Magistrate Judge.

Wicor, Inc., and its subsidiaries bring this action against the United States to receive a federal income tax refund under 26 U.S.C. §§ 41 and 1341. The § 41 and § 1341 issues were bifurcated and, on September 30, 1999, this court granted the defendant’s motion for partial summary judgment, wherein the court denied the plaintiffs request for an income tax credit under § 1341.

On April 19, 1999, a trial to the court was conducted on the plaintiffs claim that it is entitled to a research credit under § 41. Following the trial, the parties submitted their respective proposed findings of fact, conclusions of law and supporting memoranda. The following constitutes this court’s findings of fact and conclusions of law. The parties have consented to this court’s complete jurisdiction. See 28 U.S.C. § 636(c)(1).

WICOR and the Wisconsin Gas Company (“WGC”) are accrual basis taxpayers and maintain their books and records on a calendar-year basis. WGC is a wholly-owned subsidiary of WICOR and is hereinafter included with references to WICOR. WICOR filed consolidated federal income tax returns on a calendar-year basis and timely filed income tax returns for 1990 and 1991. WICOR also timely filed for a tax refund; $332,119 for 1990 and $336,637 for 1991. Its requests for refunds were denied. The parties stipulated that WI-COR complied with all jurisdictional prerequisites for bringing a lawsuit to dispute the government’s denial of WICOR’s request for a tax refund. For tax years 1990 and 1991, WICOR claims a credit for qualified research activities under Internal Revenue Code § 41(26 U.S.C. § 41) and for expenditures incurred to develop a computer-based information system.

I. FINDINGS OF FACT

Numerous lay and expert witnesses testified during the course of this trial, and a substantial number of documents were received in evidence. Since credibility is not determinative of the issues in this case, a general overview of the chronology of Wi-cor’s project will be presented instead of a detailed analysis of each witness’ testimony. The issues in dispute can be resolved with a determination of whether the generally undisputed facts fit under the Internal Revenue Code’s definition of what constitutes “qualified research.” During the discussion of each of the issues, specific reference will be made to the more relevant testimony.

WICOR, in conjunction with its contract consultants, developed a computerized integrated customer information system (“CIS”), which resulted in improved customer service and company performance in the areas of automated meter reading, computer and dispatch and online cash posting. This CIS was the end product of a process that began in 1984, when WI-COR formed an internal customer project team to identify business and information needs, develop conceptual design, and review and evaluate cost/benefit feasibility and make recommendations. The initial CIS devised by the project team was to provide a greater level of service to customers while decreasing the amount of time and expense required to perform day-to-day customer service functions; specifically, the CIS was designed to improve service order processing, customer billing, cash processing and maintenance. During 1986, the team evaluated various CIS packages but were unable to locate a system that performed the functions required by WICOR. WICOR eventually selected a package by Computer Systems & Associates (“CS & A”) entitled the Customer Information System/Data Base (“CIS/ DB”) — a software package designed for the gas and utility industries.

WICOR and CS & A entered into a service agreement, wherein CS & A *1031 agreed to provide systems consultants, systems analysts and programmers to help manage, customize, modify and develop the CIS. In July 1989, the original CIS cost estimate of $5.4 million was increased to $10.9 million based on additional functional, technical and staffing needs.

Eventually, WICOR concluded that CS & A could not meet its technological needs at an acceptable cost and concluded that in-house custom development was necessary. To facilitate such internal development, WICOR retained the Andersen Consulting Division of Arthur Andersen & Co. to review the CIS plan. Andersen had previously performed customer information system work with other utilities, including Madison Gas & Electric and Wisconsin Public Service. In its report dated August 18, 1989, James Drayer of Andersen Consulting summarized the findings and recommendations from its review of the CIS project. Drayer stated that the overall project scope “was well-defined and included the functions and features normally found in a CIS.” Drayer noted that the online architecture appeared well-structured. However, Drayer identified four areas of concern: project approach, database, project planning and control, and functional. With regard to project approach, Drayer noted that the design for two of the largest and most critical areas (billing and conversion) had not been started. With regard to the data base, Drayer stated that the primary concern was the performance worthiness of the new system and that the existing prototype database would not perform satisfactorily and would have to be modified. As for project planning, Drayer said that the overall project plan did not establish a baseline against which project status could be tracked and that the project’s link to company management was neither well-defined nor understood. (Drayer Letter to Paul Petry, Ex. 65).

In December 1989, WICOR’s contract with CS & A was terminated and CS & A phased out of the project, while Andersen Consulting was phased in. In January 1990, a consulting services agreement was entered between WICOR and Andersen Consulting, which documented Andersen’s arrangement to assist WICOR with completing the CIS project.

In May 1990, the IDMS database, which was acquired during the CS & A phase, was abandoned and WICOR purchased a DB2 database to use as the platform for its new CIS. Andersen commenced work on the CIS project in the summer of 1990. WICOR’s agreement with Andersen estimated 19,000 WICOR labor days and 16,-000 Andersen labor days. A 29-month project schedule was proposed with a November 1, 1990, start date. The time line called for software development to be completed in early 1993 with the system released and available for production sometime between February and April 1993. The CIS, as envisioned in January 1990, included service order processing, meter reading, billing, billing adjustments, rate maintenance, cash processing, meter management, interface to a third-party credit and collection system and partial non gas-user billing.

Anderson Consulting embarked on the project by establishing a structural format which included several components.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tax & Accounting Software Corp. v. United States
301 F.3d 1254 (Tenth Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
116 F. Supp. 2d 1028, 86 A.F.T.R.2d (RIA) 6567, 2000 U.S. Dist. LEXIS 15813, 2000 WL 1531583, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wicor-inc-v-united-states-wied-2000.