Whiteman v. Mayor of New York

28 N.Y. Sup. Ct. 117
CourtNew York Supreme Court
DecidedMay 15, 1880
StatusPublished

This text of 28 N.Y. Sup. Ct. 117 (Whiteman v. Mayor of New York) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Whiteman v. Mayor of New York, 28 N.Y. Sup. Ct. 117 (N.Y. Super. Ct. 1880).

Opinion

Davis, P. J.:

The contract upon wbicb tbis action is brought was made in tbe year 1866. It provided for tbe construction, by tbe assignors of tbe plaintiffs testator, of a dam and appurtenances in tbe town of Kent, Putnam county.

Tbe contract contains a large number of specifications as to tbe parts of tbe work to be done, and tbe manner in which tbe same was to be performed. Tbis action relates solely to tbe stone masonry done upon tbe work. Tbe contract provided for tbe kind of stone to be used in tbe masonry, and that all tbe masonry should be hydraulic masonry of tbe best quality ; and in substance that tbe masonry should be rubble range,” “ cut range,” and dimension cut stone masonry.” It specifies for what these several kinds of masonry were to be used in tbe walls and other parts of tbe work, and it defines with particularity bow tbe rubble range, cut range, and dimension cut stone masonry were to be constructed and laid.

Early after tbe commencement of tbe work, a controversy seems to have arisen between the contractors and tbe engineer in charge as to tbe accurate description of tbe kind of masonry then laid, and being laid, and as to tbe amount wbicb tbe contract required to be paid therefor; tbe contractors claiming that certain portions of the masonry which tbe engineer would only estimate as rubble-range masonry, were in fact cut range masonry under tbe definitions of tbe contract; and that certain other portions wbicb the engineer would only estimate as cut range, were in fact dimension cut stone masonry. Tbe engineer in chief seems to have been [119]*119called in by tbe contractors to pass upon tbe question, and Ms decision was favorable to the construction given by the engineer in charge. This state of things in respect to the controversy seems to have continued throughout the work and until the completion thereof; and the final estimate was made by the engineer in accordance with his views as to which class the particular kinds of work estimated, belonged. The plaintiffs were -finally paid in accordance with the engineer’s estimate ; and after the lapse of more than six years, commenced this action to recover the difference in price between the several kinds of masonry, upon the ground that the estimates ana certificates of the engineer were not conclusive upon the question as to the Mnd or character of the work done. The court below held that the estimates and certificates were conclusive, and directed a verdict accordingly, for the defendants, when the plaintiffs rested their ease.

The contract provided in various parts of it for the control and direction of the work by the engineer, and the estimates to be made by Mm, and the payments to be made thereupon; and that “ whenever, in the opinion of the engineer, the party of the second part have completely performed this contract on them part, said engineer shall certify the same in writing to the parties to this agreement, together with his estimate, embracing both stipulated and extra work, as herein provided, on which the said party of the second part is to be paid.”

It contains also the following provision:

“ And it is further expressly agreed that no money shall become due and payable under this contract except on the certificate of said engineer, as herein provided; and the said party of the second part further agree that they shall not be entitled to/ demand or receive payment for any portion of the aforesaid work or material, except in the manner set forth in this agreement, nor until each and every of the stipulations hereinbefore mentioned are complied with, and the engineer shall have given his certificate to that effect; whereupon the parties of the first part will, at the expiration of twenty days after such completion and delivery of said certificate, pay, and they hereby bind themselves and their successors to pay, the said party of the second part in cash, the whole amount of money [120]*120accruing to the said party of the second part under this contract, excepting such sum or sums as may be lawfully .retained under any of the provisions of this contract hereinbefore set forth.”

The contract also contained a provision in these words:

“ To prevent all disputes and litigations, it is further agreed by and between the parties to this contract, that said engineer shall in all -cases determine the amount or the quantity of the several kinds of work which are to be paid for under this contract; and he shall determine all questions in relation to lines, levels, and dimensions of work; and he shall in all cases decide every question which may arise relative to the execution of this contract on the part of said contractors ; and his estimate and decision shall be final and conclusive.”

Collating and considering these several provisions together, it cannot be doubted that the contracting parties have agreed upon and adopted the decision of the engineer as a final and conclusive arbitrament of all disputes and litigations that should arise under the contract, in respect of the kind or quantity of the several parcels of work to be paid for under the contract; and of every question which might arise relative to its execution on the part of the contractors; and they have made his decision upon these questions final and conclusive. In addition to this they have by express stipulation made the certificate of the engineer a condition precedent to the right of the parties of the second part to demand and receive payment for the work.

In such cases it is an established principle, that no court will undertake to try any of the questions embraced within these provisions of the contract which have been passed upon by the engineer, for the purpose of determining whether his decision was or was not correct. It is only where fraud and bad faith are shown, on the part of the engineer or arbitrator selected by the parties, in making his official decision, that courts will attempt to interfere. This rule was well expressed in Butler v. Tucker (21 Wend., 447), in these words: When jjarties fix on an umpire, and agree to abide his decision, neither of them, without the consent of the other, can withdraw the question of performance from the common arbiter for the purpose of referring it to the decision of a jury.” The questions [121]*121in such cases received a very full and careful consideration by the Court of Appeals in the case of the President and Directors of the Delcmare & Hudson Canal Co. v. Pennsylvania Coal Co. (50 N. Y., 250), in which the duty of the court to give full effect to the intention of the parties as clearly indicated by the agreement in such cases, where the covenants or agreements provide for an adjustment and settlement of all disputes and differences to the exclusion of the courts, as well as the effect to be given to conditions precedent expressed in such contracts either in terms or by necessary implication, are pointed out and enforced. The cases on the subject are quite numerous, and need not be quoted from at length. (See McMahon v. New York & Erie R. R. Co., 20 N. Y., 463; Kihlberg v. United States, 97 U. S., 398 ; Smith v. Briggs, 3 Denio, 73; Butler v. Tucker, supra ; Wyckoff v. Meyers, 44 N. Y., 145 ; Schenke v. Powell, 7 Daly, 286.)

None of the cases which point out and enforce exceptions to the general rule, to wit: Thomas v. Fleury (26 N. Y., 26), Smith v. Brady (17 N. Y., 172), Smith v. Wright

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kihlberg v. United States
97 U.S. 398 (Supreme Court, 1878)
McMahon v. . the New York and Erie Railroad Company
20 N.Y. 463 (New York Court of Appeals, 1859)
President of Delaware & Hudson Canal Co. v. Pennsylvania Coal Co.
50 N.Y. 250 (New York Court of Appeals, 1872)
Thomas v. . Fleury
26 N.Y. 26 (New York Court of Appeals, 1862)
Bowery National Bank v. Mayor of New York
63 N.Y. 336 (New York Court of Appeals, 1875)
Smith v. Briggs
3 Denio 73 (New York Supreme Court, 1846)
Conklin v. Egerton's Administrator
21 Wend. 430 (New York Supreme Court, 1839)
Schenke v. Rowell
7 Daly 286 (New York Court of Common Pleas, 1877)

Cite This Page — Counsel Stack

Bluebook (online)
28 N.Y. Sup. Ct. 117, Counsel Stack Legal Research, https://law.counselstack.com/opinion/whiteman-v-mayor-of-new-york-nysupct-1880.