White v. Fincantieri Bay Shipbuilding Company, Inc

CourtDistrict Court, E.D. Wisconsin
DecidedNovember 2, 2021
Docket1:19-cv-00946
StatusUnknown

This text of White v. Fincantieri Bay Shipbuilding Company, Inc (White v. Fincantieri Bay Shipbuilding Company, Inc) is published on Counsel Stack Legal Research, covering District Court, E.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
White v. Fincantieri Bay Shipbuilding Company, Inc, (E.D. Wis. 2021).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF WISCONSIN

RODNEY WHITE,

Plaintiff,

v. Case No. 19-C-946

FINCANTIERI BAY SHIPBUILDING, et al.,

Defendants.

DECISION AND ORDER ON DEFENDANTS’ MOTIONS FOR SUMMARY JUDGMENT

Plaintiff Rodney White brought this action against Defendants Fincantieri Bay Shipbuilding, Fincantieri Marine Group LLC (collectively, Fincantieri), Keystone Shipping Co., and Wawa Inc. White alleges he sustained significant injuries while working aboard a vessel on Lake Michigan as it was undergoing sea trials. The Court previously dismissed White’s claims under the Jones Act, 46 U.S.C. § 688, general maritime tort law, and Wisconsin common law negligence, leaving White’s negligence claim under the Longshore and Harbor Workers’ Compensation Act (LHWCA), 33 U.S.C. § 905(b). The case is before the Court on Defendants’ motions for summary judgment. Dkt. Nos. 74–76. For the following reasons, summary judgment will be granted in favor of Keystone and Wawa. Fincantieri’s motion, however, will be denied. BACKGROUND In February 2016, Fincantieri Bay Shipbuilding and Wawa Inc. entered into a contract for the construction of an articulated tug/barge vessel. Dkt. No. 74 at 25. The contract identifies Fincantieri as the builder of the vessel and Wawa as the owner but notes that legal title of the completed vessel, the Millville, would not pass to Wawa until successful completion of “sea trials” and delivery of the vessel. Id.; Dkt. No. 93 at 6; Dkt. No. 74-3 at 13. These sea trials are designed to “put the newly constructed vessel through a series of proving exercises to confirm that the vessel conforms to the technical specifications to which the vessel was to be built.” Dkt. No. 74 at 25. Per the terms of the shipbuilding contract, the builder, Fincantieri, was to carry out the sea trials.

Id. at 26; Dkt. No. 93 at 29. Wawa, however, was to provide the crew for the sea trials and reached out to Keystone to obtain a crew for the trials. Dkt. No. 80-12 at 7–8. Ultimately, a crew headed by Captain Buddy Davis was secured for the sea trials, although the crew was employed by non- party Key Marine, LLC, rather than by Keystone. Dkt. No. 74-5 at 7–9. Key Marine was to become the bareboat charter of the Millville upon its delivery. Dkt. No. 74 at 26. In November 2017, the sea trials of the Millville were commenced. White participated in the sea trials by virtue of his employment with Engine Motors, Inc., and was primarily responsible for monitoring the performance of the vessel’s steering control systems and troubleshooting any issues. Dkt. No. 74 at 28. During the sea trials, a number of maneuvers were to be conducted, including “hard-over” maneuvers. Id. at 27. A hard-over maneuver “calls for sailing the vessel

on a level course, turning the rudder full over to one side, followed by turning the rudder back full over to the other side, then back to center.” Id. This maneuver causes the vessel to roll side-to- side to allow the crew to measure the vessel’s stability when turning, and takes the vessel to its “operational limits, to see if the vessel can operate at the extremes, and to ensure that, should something go wrong, it happens before the vessel is completed as opposed to during her service.” Id. Prior to the execution of the sea trials and the hard-over maneuvers, a series of safety meetings were held, including a meeting that was held on the main deck of the Millville the morning of the trials. Dkt. No. 80-11 at 37. White attended this safety meeting and acknowledged that the meeting informed him of the agenda for the sea trials and the fact that hard-over maneuvers were going to take place. Id. The morning of the trials, White conducted a “dock side trial,” verifying that the “material was all right and that the captain approved.” Id. at 10. After verifying that the steering system

was satisfactory, White testified that he “went down to the rudder room to make sure that there were no leaks” and then “probably went to the gall[e]y,” although he acknowledged he could have been in the wheelhouse or engine room. Id. at 23–24. What happens next is the heart of the dispute. As the vessel approached the trials area, an initial announcement was made informing those on board that the vessel was approaching the trials area and that personnel should secure any loose belongings and prepare for hard-over maneuvers. See, e.g., Dkt. No. 74-10 at 17–18; Dkt. No. 80-10 at 11; Dkt. No. 80-7 at 22. Beyond this, the testimony varies regarding the warnings. Amelia Ott, the project manager for the construction of the Millville, testified that, as part the safety announcements, personnel on board were instructed that “maneuvers were going to be ongoing and that they would not be completed until another announcement was made.” Dkt. No.

80-15 at 14. Ott further testified that those who made the announcements informed personnel that, although “there may be brief pauses where [the personnel] believe that we may be complete,” the maneuvers would not truly be complete until there was an announcement confirming that the maneuvers were actually finished. Id. Ott was the only one who testified that such a detailed warning took place. An electrician who was aboard the vessel at the time of the trials, Jan Hucek, stated that, after some hard-overs had been completed, he and those in the galley and mess area thought the maneuvers were finished. Dkt. No. 80-7 at 18. The boat had “come back to straight,” but after a couple of minutes, another hard-over was allegedly initiated without warning. Id. At some point during the hard-over maneuvers, White was injured after sliding into the “starboard wall in the mess room, outboard,” leaving a dent in the wall. Dkt. No. 80-8 at 3; Dkt. No. 80-7 at 21. White testified that, while he had heard the initial announcement concerning the vessel approaching the trials area and to prepare for hard-over maneuvers, there had been no

announcement just prior to White’s initial injury. Dkt. No. 80-11 at 27–28, 41. As a result of White sliding into the wall, White suffered various injuries, including a herniated cervical disc and closed head injuries (a traumatic brain injury). Dkt. No. 1 at 6. LEGAL STANDARD Summary judgment is appropriate when the moving party shows that there is no genuine dispute as to any material fact and that the movant is entitled to judgment as a matter of law. Fed. R. Civ. P. 56(a). In deciding a motion for summary judgment, the Court must view the evidence and make all reasonable inferences in the light most favorable to the non-moving party. Johnson v. Advocate Health & Hosps. Corp., 892 F.3d 887, 893 (7th Cir. 2018) (citing Parker v. Four Seasons Hotels, Ltd., 845 F.3d 807, 812 (7th Cir. 2017)). The party opposing the motion for

summary judgment must “submit evidentiary materials that set forth specific facts showing that there is a genuine issue for trial.” Siegel v. Shell Oil Co., 612 F.3d 932, 937 (7th Cir. 2010) (citations omitted). “The nonmoving party must do more than simply show that there is some metaphysical doubt as to the material facts.” Id. Summary judgment is properly entered against a party “who fails to make a showing to establish the existence of an element essential to the party’s case, and on which that party will bear the burden of proof at trial.” Austin v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McLaurin v. Noble Drilling (U.S.), Inc.
529 F.3d 285 (Fifth Circuit, 2008)
Romero v. Cajun Stabilizing Boats Inc.
307 F. App'x 849 (Fifth Circuit, 2009)
Scindia Steam Navigation Co. v. De Los Santos
451 U.S. 156 (Supreme Court, 1981)
Pegram v. Herdrich
530 U.S. 211 (Supreme Court, 2000)
Siegel v. Shell Oil Co.
612 F.3d 932 (Seventh Circuit, 2010)
Langfitt v. Federal Marine Terminals, Inc.
647 F.3d 1116 (Eleventh Circuit, 2011)
Dennis L. Capps v. N.L. Baroid-Nl Industries, Inc.
784 F.2d 615 (Fifth Circuit, 1986)
Trinidad Pimental v. Ltd Canadian Pacific Bul
965 F.2d 13 (Fifth Circuit, 1992)
Donald W. Elberg v. Mobil Oil Corporation
967 F.2d 1146 (Seventh Circuit, 1992)
Mark Hudson v. Schlumberger Technology Corp., Et A
452 F. App'x 528 (Fifth Circuit, 2011)
Spearing v. County of Bayfield
394 N.W.2d 761 (Court of Appeals of Wisconsin, 1986)
Robin Austin v. Walgreen Company
885 F.3d 1085 (Seventh Circuit, 2018)
Warren Johnson v. Advocate Health and Hospitals
892 F.3d 887 (Seventh Circuit, 2018)
Holder v. Fraser Shipyards, Inc.
288 F. Supp. 3d 911 (W.D. Wisconsin, 2018)
Parker v. Four Seasons Hotels, Ltd.
845 F.3d 807 (Seventh Circuit, 2017)
Cook v. Exxon Shipping Co.
762 F.2d 750 (Ninth Circuit, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
White v. Fincantieri Bay Shipbuilding Company, Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/white-v-fincantieri-bay-shipbuilding-company-inc-wied-2021.