White v. Cridlebaugh

178 Cal. App. 4th 506, 100 Cal. Rptr. 3d 434, 2009 Cal. App. LEXIS 1693
California Court of Appeal·Decided October 20, 2009·No. F053843·Published·Cited by 23 cases

Opinion

Opinion

DAWSON, J.

Homeowners sued a building contractor, supplier, surety, and individuals involved in the construction of their retirement home for breach of contract, negligence, fraud, and violations of California’s licensure requirements. The trial court allowed certain theories against the building contractor to go to the jury but granted nonsuit and directed verdicts on the rest. The *509 jury then found against the homeowners and for the building contractor. After entry of judgment against the homeowners, they appealed.

In the published portion of this opinion, we conclude the corporation that acted as the building contractor on the project violated California’s licensure requirements and, based on that violation, the homeowners are entitled under Business and Professions Code section 7031, subdivision (b) (section 7031(b)) 1 to recover all compensation paid to the contractor for the unlicensed work. Also, as a matter of statutory construction, we conclude that the recovery authorized by section 7031(b) may not be reduced by an unlicensed contractor’s claim of offset for materials and services provided in connection with the unlicensed work. We note that the latter conclusion qualifies for publication because, among other things, some secondary authorities create the impression that an unlicensed contractor may assert offset as a defense to the liability imposed by section 7031(b).

In the unpublished portion of this opinion, we conclude that (1) the homeowners’ pleading adequately stated their section 7031(b) reimbursement claim, (2) the homeowners failed to demonstrate the trial court committed reversible error in granting nonsuit on certain claims and directed verdicts on others, (3) the trial court’s determinations regarding alter ego are supported by substantial evidence, (4) the trial court’s exclusion of certain testimony under Evidence Code section 352 was not an abuse of discretion, and (5) the homeowners, as the prevailing parties, are entitled to recover their court costs from the contractor.

Accordingly, the judgment will be modified.

FACTS AND PROCEEDINGS

Robert D. White (White) and Carole K. White wanted to build a retirement home on an empty lot in Pine Mountain Club, California. Terry E. Harper Cridlebaugh (Cridlebaugh), Vickie Harper Cridlebaugh, Robert Paul Diani, JC Master Builders, Inc., and Building Technology are individuals and entities involved in the initial phases of building that home. Surety Company of the Pacific provided the contractor’s bond for JC Master Builders, Inc.

The Construction Project

The Whites purchased the empty lot in Pine Mountain Club in 2005 for the purpose of building their retirement home. The Whites had been looking at log homes for a number of years, and White obtained estimates on log home packages.

*510 The Whites met the Cridlebaughs at church. In February 2006 or earlier, Carole White attended a women’s prayer meeting at their church and Vickie Cridlebaugh told her that they, the Cridlebaughs, desperately needed work. They prayed about it and decided that since the Whites needed to have a house built and the Cridlebaughs needed work, it might be a good fit. The Whites also went and looked at a log home that Cridlebaugh was building.

When they reached the point of entering a contract, White suggested a time and materials contract. Cridlebaugh drafted an initial contract which, after making a few changes, the parties signed on March 14, 2006. Prior to signing the contract, the parties reviewed the plans and specifications for the project. Although the contract listed the owners as the general contractor, White testified that his understanding with Cridlebaugh was that Cridlebaugh would do the actual work on the site and was responsible for reading the plans and doing the work on the drawings. They also discussed the foundation, which “was a slab on grade walkout first floor.”

In March 2006, Cridlebaugh began work by clearing brush from the site. The rough grading was complete by April 21st. About that time, White became concerned with the amount of excavating that Cridlebaugh was doing and asked him to get a soils engineer to test the site. Cridlebaugh responded that he would know when to get a soil test.

Cridlebaugh excavated to a depth of seven feet or more. He testified that the excavation was necessary because of the topsoil, the slope, and Kern County grading regulations. He also testified the excavation was consistent with the elevations indicated on the plans, which showed that the soil at one comer of the house was six and a half feet lower than an uphill comer. In contrast, the Whites contend that the pad staking document prepared by Prewitt Land Surveying indicated a cut and fill excavation for the slab-on-grade pad for the first floor and that Cridlebaugh did not follow that document or the other plans. Also, White testified that JC Master Builders, Inc., substantially exceeded the budget that he, White, had established for site preparation.

White’s concerns led him to request Cridlebaugh to subcontract the grading work to L & M Construction, which was familiar with the area and had equipment on the hill where the Whites’ lot was located. White also asked Cridlebaugh to get a rebar contractor to do the rebar because Cridlebaugh did not have anyone experienced to do the work. White was concerned with paying Cridlebaugh to drive back and forth between the jobsite and Frazier Park, which is where Cridlebaugh bent the rebar. White believed the rebar should be bent on site.

*511 White also was concerned with the billings he received from JC Master Builders, Inc., which he considered convoluted. For example, Cridlebaugh would convert the time of laborers he hired into time that was billed at his hourly rate. Cridlebaugh said it was easier to do on his computer than having a separate hourly rate for each laborer. With respect to billing for materials, the invoices showed a lump sum instead of indicating how many units of the material were used and the cost per unit. Also, the invoices indicated the source of the material was Building Technology 2 and did not state where the items had been purchased. White asked Cridlebaugh for the invoices from the suppliers at least five times but they were not provided. White was concerned that unpaid suppliers might place a lien on the lot.

Through mid-May 2006, White paid the bills of JC Master Builders, Inc., because “I had no reason to believe that they would not perform and keep their agreement to operate the business with . . . integrity . . . .”

On June 19, 2006, White sent Cridlebaugh a memo confirming his oral instructions to Cridlebaugh to stop all construction activities until he provided the original documents requested by White to verify the billings. On June 22, 2006, White sent Cridlebaugh a letter stating that the relationship was finished. White testified that Cridlebaugh finished returning rebar and then stopped work.

On July 14, 2006, JC Master Builders, Inc., filed a mechanic’s lien in the amount of $13,561.62 against the Whites’ lot.

Free access — add to your briefcase to read the full text and ask questions with AI

White v. Cridlebaugh, 178 Cal. App. 4th 506, 100 Cal. Rptr. 3d 434, 2009 Cal. App. LEXIS 1693 (Cal. Ct. App. 2009).

178 Cal. App. 4th 506 (White v. Cridlebaugh) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Shiralian v. Concord Development CA5
California Court of Appeal, 2025
Powell v. Idleman CA2/7
California Court of Appeal, 2021
Crown Financial LLC v.
Third Circuit, 2021
Manela v. Stone
California Court of Appeal, 2021
Kivel v. McInerney CA4/1
California Court of Appeal, 2021
Rossetta v. CitiMortgage, Inc.
California Court of Appeal, 2017
Jeff Tracy, Inc. v. City of Pico Rivera
California Court of Appeal, 2015
Jeff Tracy, Inc. v. City of Pico Rivera CA2/2
240 Cal. App. 4th 510 (California Court of Appeal, 2015)
Womack v. Lovell
237 Cal. App. 4th 772 (California Court of Appeal, 2015)
Turkmen v. Katz CA2/4
California Court of Appeal, 2015
Alborzian v. JPMorgan Chase Bank, N.A.
235 Cal. App. 4th 29 (California Court of Appeal, 2015)
Bertoli v. Dennis CA1/5
California Court of Appeal, 2015
E.J. Franks Construction v. Sahota
California Court of Appeal, 2014
E. J. Franks Construction Inc. v. Sahota
226 Cal. App. 4th 1123 (California Court of Appeal, 2014)
Adelman v. Adelman CA2/4
California Court of Appeal, 2014
Qu v. Univ. of So. Cal. CA2/3
California Court of Appeal, 2013