Goldstein v. Barak Construction

164 Cal. App. 4th 845, 79 Cal. Rptr. 3d 603, 2008 Cal. App. LEXIS 998
CourtCalifornia Court of Appeal
DecidedJuly 8, 2008
DocketB196551
StatusPublished
Cited by22 cases

This text of 164 Cal. App. 4th 845 (Goldstein v. Barak Construction) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Goldstein v. Barak Construction, 164 Cal. App. 4th 845, 79 Cal. Rptr. 3d 603, 2008 Cal. App. LEXIS 998 (Cal. Ct. App. 2008).

Opinion

Opinion

FLIER, J.

Barak Construction (Barak) and Ami Weisz (sometimes hereafter appellants) appeal from (1) the trial court’s order granting the application of respondents Anita Goldstein and Eric Mizrahi for a right to attach order and order for issuance of writ of attachment against Barak and (2) its order *849 directing Weisz not to “sell, encumber, or diminish the value of his residence” until the action is adjudicated or upon further order of the court. We affirm.

FACTS 1

Respondents own a residence in Los Angeles, California. In June 2004, Weisz represented to respondents that he was personally engaged in the business of residential construction and remodeling and that Barak was “his” company. Weisz also stated that both he and Barak were licensed California building contractors. In reliance on these statements, respondents entered into a contract with Barak for an addition to, and a remodeling of, their home. The work to be performed under the contract included demolition and disposal of an existing garage, excavation and pouring of concrete foundations for a new structure, furnishing structural steel for the new construction, erecting the framing and roof of the new structure and plumbing, electrical, heating, air conditioning, interior finishing, painting and other work. The total cost for all material and labor was $363,000.

Neither Barak nor Weisz was a licensed contractor at the time the contract was signed on June 18, 2004. After the contract was executed, Barak commenced working on the project. Three months later, on September 17, 2004, Barak obtained a contractor’s license for the first time.

Respondents allegedly paid Barak the sum of $362,660.50 under the contract. However, Barak allegedly abandoned the job before the work was completed, leaving respondents with a home that was unfinished and riddled with construction defects.

Respondents filed the present action against Barak, Weisz and others in March 2005. As against both appellants, the verified complaint sought *850 recovery for fraud, negligent misrepresentation, concealment, negligence, breach of implied warranties, breach of contract and unfair business practices. The complaint also sought recovery of money paid to an unlicensed contractor as against Barak.

Appellants filed a verified answer to the complaint. Appellants admitted that Barak entered into a contract “relating to the construction of an addition to, and remodeling of, [respondents’] residence.” The answer admitted that a general building contractor license was not issued to Barak until September 17, 2004, and neither Barak nor Weisz held a California building contractor’s license at the time the contract with respondents was executed. Appellants also admitted in their answer that Weisz was an officer, director and majority shareholder of Barak and alleged that respondents made payments to Barak totaling $362,629.50. They further admitted that Barak never held a contractor’s license prior to entering into the contract with respondents.

After appellants filed their verified answer, respondents filed applications for a right to attach order and order for issuance of a writ of attachment against Barak and Weisz. Respondents asked for an attachment in the amount of $385,388, which included $362,660.50 respondents allegedly paid Barak, estimated costs of $643 and allowable attorney fees of $22,084.50. Respondents proffered a declaration testifying to the basic facts as related, ante. The declaration further averred that respondents were obliged to retain attorneys to seek recovery of the amounts they paid under the contract, and they incurred attorney fees of $22,084.50 and costs of $643 in prosecuting the case.

Appellants filed a written opposition to the applications. The opposition raised four contentions: (1) respondents’ claim was not based on a contract; (2) the amount was not fixed or readily ascertainable; (3) respondents had not proved the probable validity of their claim by a preponderance of evidence; and (4) there was no legal or factual basis for allowing an attachment against Weisz individually. Appellants further took issue with the amount sought to be secured by the attachment, arguing that (1) over $80,000 of the funds paid Barak was for “extras” separate from the subject contract; (2) $34,800 of the contract was for allowances paid directly by respondents to third parties; (3) Barak was seeking an offset for work performed and materials provided but not paid for; and (4) respondents had not apportioned fees and costs among multiple defendants. The opposition specifically did not include notice of any intention to claim any exemption of property from attachment.

Weisz filed a declaration stating that he had incorporated Barak on April 17, 2003, and Barak has been an active corporation in good standing since then. Weisz asserted Barak had been adequately capitalized and had maintained a separate corporate existence. He admitted the facts of the contract *851 but asserted the contract price included $34,800 in allowances that respondents paid third parties. He stated that respondents had an unpaid balance on the contract of $56,470. Weisz admitted that Barak had not completed respondents’ project, but he claimed it was due to the “wrongful conduct” of respondents. Also, he contended, the project included “extras” agreed to by respondents in the amount of $93,150.60, of which respondents paid $90,899.50, leaving the sum of $2,251.10 of “extras” unpaid. According to Weisz, $81,470.13 of the “extras” paid for by respondents was requested and performed after Barak obtained its contractor’s license.

Weisz declared that Barak had submitted an application for a contractor’s license in mid-2003, and Aharon Vaknin, then a shareholder of Barak, had taken the contractor’s license examination in March or April 2004. Vaknin failed to pass all the portions of the examination. It was not until August 2004 that Vaknin was able to retake and pass the examination, after which a license was issued to Barak on September 17, 2004. 2

Weisz claimed Barak performed “very little” work on respondents’ project, primarily site preparation and demolition, prior to issuance of the license. He stated the “majority” of the work under the contract occurred after Barak had its license. He denied ever telling respondents he or Barak had a contractor’s license and asserted the subject of licensing never came up in his discussions with respondents. Weisz contended on information and belief that respondents “knew” Barak did not have a contractor’s license when they entered into the contract. He stated he advised respondents at the time of contracting that he would engage a licensed onsite project supervisor or manager, and Barak did in fact engage a bonded and licensed general building contractor other than Vaknin to oversee the project, both before and after Barak had secured its own license.

After a hearing, the trial court granted respondents’ application for a right to attach order and order for issuance of a writ of attachment solely against Barak in the amount of $385,388 upon the filing of a $10,000 undertaking.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

REV Capital v. ALO CA2/3
California Court of Appeal, 2025
Northeast Securities Co. v. Que CA6
California Court of Appeal, 2025
Conservatorship of the Person of C.O. CA1/4
California Court of Appeal, 2025
West Casitas v. Swing House Stages CA2/5
California Court of Appeal, 2023
Park v. NMSI, Inc.
California Court of Appeal, 2023
Royals v. Lu
California Court of Appeal, 2022
Hawkins v. Zoegall
N.D. California, 2022
Gluck v. Sarkissian CA2/2
California Court of Appeal, 2021
Kivel v. McInerney CA4/1
California Court of Appeal, 2021
E.J. Franks Construction v. Sahota
California Court of Appeal, 2014
E. J. Franks Construction Inc. v. Sahota
226 Cal. App. 4th 1123 (California Court of Appeal, 2014)
Consolidated Irrigation District v. City of Selma
204 Cal. App. 4th 187 (California Court of Appeal, 2012)
Alatriste v. Cesar's Exterior Designs, Inc.
183 Cal. App. 4th 656 (California Court of Appeal, 2010)
White v. Cridlebaugh
175 Cal. App. 4th 1535 (California Court of Appeal, 2009)
Vfs Financing, Inc. v. Chf Express, LLC
620 F. Supp. 2d 1092 (C.D. California, 2009)
Hamilton Beach Brands, Inc. v. Metric & Inch Tools, Inc.
614 F. Supp. 2d 1056 (C.D. California, 2009)
The Fifth Day, LLC v. Bolotin
172 Cal. App. 4th 939 (California Court of Appeal, 2009)
Oceguera v. Cohen
172 Cal. App. 4th 783 (California Court of Appeal, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
164 Cal. App. 4th 845, 79 Cal. Rptr. 3d 603, 2008 Cal. App. LEXIS 998, Counsel Stack Legal Research, https://law.counselstack.com/opinion/goldstein-v-barak-construction-calctapp-2008.