White Star Coal Co. v. Pursifull

217 S.W. 1020, 186 Ky. 697, 1920 Ky. LEXIS 23
CourtCourt of Appeals of Kentucky
DecidedJanuary 30, 1920
StatusPublished
Cited by10 cases

This text of 217 S.W. 1020 (White Star Coal Co. v. Pursifull) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
White Star Coal Co. v. Pursifull, 217 S.W. 1020, 186 Ky. 697, 1920 Ky. LEXIS 23 (Ky. Ct. App. 1920).

Opinion

Opinion of the Court by

Judge Thomas —

Affirming.

The appellant and defendant below, White Star Coal Company, is a corporation, engaged in mining coal. About November 1, 1915, it orally contracted with the appellee, Edward Pursifull (plaintiff below), to do certain work pertaining to its mines at Wilhoit, Kentucky, and about the 15th of that month he began work. On December 13, following, an officer of the defendant reduced the contract to writing, which was duly executed by both parties. Thé material parts of the contract out of which this litigation grew says:

“This contract, made and entered into this the 13th day of December, 1915, by and between the White Star Coal Company, incorporated, of Pineville, Bell county, Kentucky, hereinafter designated as the company, party of the first part, and Edward Pursifull, of Pineville, Bell county, Kentucky, hereinafter designated as. the contractor, party of the second part.
‘/Witnesseth: 1. That the company is desirous of making certain improvements at Wilhoit, ITarlan county, Kentucky, such as the building of tramroads, inclines, miners’ houses, repairs to tipple, etc., and the contractor is desirous of doing this, work for the company.
“2. Therefore it is mutually agreed that the contractor will do all of the necessary grading of the tram roads, including whatever trestles or culverts are agreed upon as necessary, inclines or whatever other grading is desired by the company, at actual cost.
“3. The contractor agrees to superintend all of the work done for the company, personally, in so far as he is able, but he is to be allowed such necessary foremen as are necessary to carry on the work energetically and economically. The contractor is to receive for his compensation or profit, for said grade work or superintendence, fifteen per cent (15%) of the gross amount actually [699]*699spent in the grading and other work mentioned above, and the profit of fifteen per cent (15%) above mentioned is to be paid by the company in shares of stock of the company at par value.
“4. The contractor also agrees to construct not less than ten miners’ houses, or as many more as the company may desire, of such design and size as the eompanv may select, and at such places on its lease as the company may select, and is to make such repairs or additions to the tipple, or erect new tipple, for the company at actual cost, and the contractor- is to receive for his supervision and personal work a profit of ten per cent (10%) of the gross amount spent in the construction mentioned above, and the said ten per cent (10%) is to be payable in stock of the company at par value.
“The stock mentioned above, that is, as to the grading and the houses, is to be issued when the job or jobs arc completed.”

In other parts of the contract plaintiff agreed to keep the time of the laborers engaged in performing the work, and to turn in to the company’s office reports thereof, and agreed to furnish as much as three teams with drivers, for which he was to receive at the rate of four dollars ($4.00) per day, one-half of which was to be paid in cash and the other one-half in stock of the company. He also agreed to furnish the necessary equipment and tools for carrying on the work and to prosecute it energetically until it was completed.

Sometime in June, 1916, and after the completion of the greater part of the work, a settlement was had between the parties covering plaintiff’s percentage on the amount spent for labor, and there was found to be due him for his percentages and for one-half of the services of his teams the sum of $1,250.00, and the defendant thereupon issued to him stock in the company of the par value of that amount. All of the work specified in the contract was not completed until August or September of that year, but plaintiff, according to his testimony, after receiving the above stock (and perhaps after the work was completed), demanded a final settlement with defendant, and failing to obtain one he procured an attorney who made a similar demand, and he was met with the contention by the defendant that there was nothing due the plaintiff under the contract, since it insisted that he was entitled to the percentages mentioned in the con[700]*700tract only upon the amount spent by defendant for labor in the constructions mentioned therein. Plaintiff claimed, and is contending .on this appeal, that he was not only entitled to such percentages upon the item of labor, but that he was also entitled to his agreed rate of compensation upon the amount spent by the company for the material and supplies which went into the work, and he brought this suit asking the court to require defendant to issue to him additional stock to the amount of $2,000.00, which be claimed represented the amount still due him under the contract.

An answer was filed in which the material allegations of the petition were traversed, and a counterclaim for $2,500.00 damages was asserted because of the alleged failure of plaintiff to perform his contract. An amended answer alleged a settlement between the parties at the time plaintiff received from defendant the $1,250.00 stock, which settlement, as alleged, was agreed to in full payment and satisfaction of all of plaintiff’s services under the contract. Subsequent pleadings put in issue all those defenses, and the court on motion of the defendant transfeired the cause to the common law docket “for the trial of the common law issues raised by the pleadings.” The jury, upon the trial of those issues (the record not disclosing what they were) returned a verdict in favor of defendant against the plaintiff for the sum of $190.00, upon which judgment was rendered. The cause thereafter proceeded as an equity case, and upon final submission the court found that plaintiff under the contract was not entitled to any percentage for the value of materials and supplies used in the construction of the tipple, incline or screens, but that he was entitled to his percentage of such material and supplies used in the construction of the miners’ houses, and in the grading as well as culverts and trestles therein; that upon this basis there was a balance due him of $1,235.65, which it was adjudged should be paid in stock of the defendant company at its par value. Complaining of that judgment the defendant prosecutes this appeal.

The chief ground insisted upon as error grows out of the construction which the court placed on the contract, the defendant challenging the correctness of that construction. For convenience of reference we have separated the contract into clauses, designating them 1, 2, 3 and 4, which figures' do not appear in the original.

[701]*701The law is, without exception, that it is the duty of the court having before it the construction of a contract to ascertain the intention of the parties from the language employed in the entire contract, and to give the construction which conforms to that intention. Owens v. Georgia Life Insurance Company, 165 Ky. 507, and Keen v. Ross, 186 Ky. 256. Other rules are subsidiary to the one mentioned, their office being only to assist the court in arriving at the intention of the parties.

Guided by the above rule, we find that in clause 1 of the contract all of the different character of work contemplated by the defendant is referred to.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First National Bank v. Stoyanoff
349 P.2d 1016 (Montana Supreme Court, 1960)
Veech v. Deposit Bank of Shelbyville
128 S.W.2d 907 (Court of Appeals of Kentucky (pre-1976), 1939)
Fry v. Weyen
70 P.2d 359 (Idaho Supreme Court, 1937)
Belknap v. Bank of Prospect
82 S.W.2d 504 (Court of Appeals of Kentucky (pre-1976), 1935)
Bank of Blaine v. Hanshaw
75 S.W.2d 529 (Court of Appeals of Kentucky (pre-1976), 1934)
Bullock v. Young
67 S.W.2d 941 (Court of Appeals of Kentucky (pre-1976), 1933)
Ex Parte Walker's
68 S.W.2d 745 (Court of Appeals of Kentucky (pre-1976), 1933)
G. F. Vanzant Lumber Co. v. Hopkins
37 S.W.2d 37 (Court of Appeals of Kentucky (pre-1976), 1931)
Hudson, House & Cogar v. Clarke Plumbing Co.
248 S.W. 206 (Court of Appeals of Kentucky, 1922)
White Star Coal Co. v. Pursifull
224 S.W. 858 (Court of Appeals of Kentucky, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
217 S.W. 1020, 186 Ky. 697, 1920 Ky. LEXIS 23, Counsel Stack Legal Research, https://law.counselstack.com/opinion/white-star-coal-co-v-pursifull-kyctapp-1920.