Hudson, House & Cogar v. Clarke Plumbing Co.

248 S.W. 206, 197 Ky. 653, 1922 Ky. LEXIS 652
CourtCourt of Appeals of Kentucky
DecidedDecember 8, 1922
StatusPublished
Cited by1 cases

This text of 248 S.W. 206 (Hudson, House & Cogar v. Clarke Plumbing Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hudson, House & Cogar v. Clarke Plumbing Co., 248 S.W. 206, 197 Ky. 653, 1922 Ky. LEXIS 652 (Ky. Ct. App. 1922).

Opinion

Opinion op the Court by

Judge Thomas

Reversing.

In the summer and fall of 1917, appellants and plaintiffs below, composing the firm of Hudson, House & Co-gar, were engaged in the hemp growing business in Boyle county and they had rented for three years a farm suitable for the purpose and containing about three hundred acres. Appellees and defendants below, composing the firm of Clarke Plumbing Company, were and had been for a long time engaged in the plumbing business, including fitting together of machinery. Along in the summer of that year plaintiffs conceived the idea of constructing a hemp dryer and procured one or more firms to make figures and perhaps draw plans for the construction of one, which plans they submitted to defendants ’ for estimates on the cost of construction, but they were not accepted because of the excessively high cost. Some time thereafter one of the defendants was in Cincinnati, Ohio, and met the defendant, F. E. Siebenmann, who was a professional designing engineer of heating plants, power plants and other similar structures. Defendants had theretofore worked in connection with Siebenmann in the installation of plants of which he was the engineer and he was induced to undertake the making of the plans and specifications for a hemp dryer to be installed by plaintiffs. Subsequently Siebenmann sent to defendants plans and specifications for the dryer, which was estimated to cost without carriage the sum of $7,158.42, which was presented to Hudson, a member of the firm, and he objected, because it did not include the entire cost of carriage, etc., whereupon the senior member of the defendant firm, who carried the specifications to Hudson, estimated the cost of the omitted items to be $337.00, or a total cost of $7,495.42. Following that and ■on November 23, 1917, there was presented to plaintiffs for signature a writing prepared by Siebenmann, the first part of which says:

“Specifications for the installation of hemp dryer as per plans and specifications prepared and furnished by [655]*655F. E. Siebenmann, engineer, Cincinnati, 0., and contractor for Hudson, House & Cogar, Danville. Kentucky.

“ Tbe contractor agrees to furnish material and labor to complete hemp dryer exclusive of carpenter work and fuel to operate and test out plant, as described herein for the net sum of seventy-four hundred and ninety-five dollars and 42/100. $7,495.42. Payments as follows: Eighty-five per cent to be paid on material dólivered on the premises and work installed where dryer is located, remaining fifteen per cent to be paid when plant is tested out and contract complied with.

“The different materials used, also workmanship, fully guaranteed free from defects of any kind. Should any defects occur within one year from date, same will be made good and replaced without cost to the owners. The guarantee also covers the efficiency and capacity of the plant as specified. ’ ’

Then followed a minute description of the material to be used in the construction of the dryer and it is then stated: “The dryer in its entirety is guaranteed to dry from fifteen to twenty thousand pounds of hemp containing ten per cent saturation in eight (8) hours variable speed. Any failure on the part of said drying plant to do-as above specified will be reconstructed by said F. E. Siebenmann without cost to the owners.”

The stipulation is then added by which the contractors agree to build the dryer by the 26th day of December, 1917, excepting named contingencies which are not necessary to mention. That paper is signed by “Hudson, House & Cogar, owners by Hudson,” and by “F. E. Siebenmann, engineer,” and there is a blank line followed by the word ‘ ‘ contractors, ’ ’ but no name is written thereon. Hudson testified, and he was corroborated by a witness named Davis, that both Clarke and Seibenmann came to Hudson’s office on that day with the prepared writing and that both he and Seibenmann signed it at the. time,- while Clarke testified that Siebenmann was not", present and that the writing had already been signed by him when received by Clarke and was signed by Hudson! in the latter’s office when Clarke alone presented it. If will be'observed that the fixed cost included both material and labor minus carpenter work and fuel to test the plant.

Within a few days thereafter defendants were shown by plaintiffs the site upon which to construct the dryer and they immediately began work thereon, some of the materials for which were shipped to defendants before [656]*656the writing was signed by Hudson. The building was not finished because of weather conditions and other interfering causes until some time in March, 1918, bul no test of it was made at that time because plaintiffs say that in the meantime they had broken their entire crop of hemp and had none left with which to make the test. The building enclosing the machinery was locked by plaintiffs, but the roof was blown off and the machinery became more or less damaged, and in the late fall of 1918, after repairing the damage, a test was made, but as to the extent of it the testimony is contradictory. However, it was found that the dryer, though constructed according' to the plans, would not perform the work and was without value for the purposes intended.

This action was filed by plaintiffs against Siebenmann and the Clarke Plumbing Company to recover damages for the failure to construct the plant within the time agreed upon, and for its failure to perform the work, the total amount of which, as alleged in the petition, was $11,251.10. Siebenmann tendered an answer but the court, on objections by plaintiffs to its being filed, sustained their objections, and a jury, empanelled to assess the damages against him, returned a verdict in favor of plaintiffs for $6,731.10, upon which judgment was rendered and from which no appeal is prosecuted. The Clarke Plumbing Company denied that they were either contractors or subcontractors in the construction of the plant but that plaintiffs contracted with Siebenmann for plans and specifications for the construction of the plant and that plaintiffs, through Siebenmann, their engineer, employed appellees to construct the plant according to the plans and specifications and they were to receive therefor ten per cent of the estimated cost according to the plans, or a sum of $749.55, plus all extra material and labor used in the construction and not contained in the specifications. They alleged that they had paid for all the material specified in the plans and specifications as well as extras, and that such payments plus their percentage amounted to $9,902.18, only $6,371.11 of which plaintiffs had paid and by counterclaim asked judgment against plaintiffs for $3,531.07. Before trial plaintiffs filed, over the objections of defendants, an amended petition in which they withdrew the averments in their petition-that the Clarke Plumbing Company was a co-contractor with Siebenmann and alleged that they were subcontractors under him and withdrew their prayer for any [657]*657judgment against appellees. Appropriate pleadings made the issues and upon- a jury trial under the instructions of the court, a verdict was returned in favor of appellees against appellants for the sum of $2,458.20, upon which judgment was rendered and the court declining to set it aside on a motion for a new trial plaintiffs prosecute this appeal.

The grounds urged for a reversal are, that the court erred in giving to the jury instruction number 1, and erred in refusing to give instruction “Z,” offered by plaintiffs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clarke Plumbing Company v. Hudson, House Cogar
270 S.W. 748 (Court of Appeals of Kentucky (pre-1976), 1925)

Cite This Page — Counsel Stack

Bluebook (online)
248 S.W. 206, 197 Ky. 653, 1922 Ky. LEXIS 652, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hudson-house-cogar-v-clarke-plumbing-co-kyctapp-1922.