White Oak Realty, L.L.C. v. U.S. Army Corps

CourtCourt of Appeals for the Fifth Circuit
DecidedJuly 11, 2018
Docket17-30438
StatusUnpublished

This text of White Oak Realty, L.L.C. v. U.S. Army Corps (White Oak Realty, L.L.C. v. U.S. Army Corps) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
White Oak Realty, L.L.C. v. U.S. Army Corps, (5th Cir. 2018).

Opinion

Case: 17-30438 Document: 00514550755 Page: 1 Date Filed: 07/11/2018

IN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT United States Court of Appeals Fifth Circuit

FILED No. 17-30438 July 11, 2018 Lyle W. Cayce WHITE OAK REALTY, L.L.C.; CITRUS REALTY, L.L.C., Clerk

Plaintiffs - Appellants

v.

UNITED STATES ARMY CORPS OF ENGINEERS; THOMAS P. BOSTICK, Lieutenant General, United States Army Chief of Engineers, in his official capacity; JOHN W. PEABODY, Major General, Commander, Mississippi Valley Division, United States Army Corps of Engineers, in his official capacity; RICHARD L. HANSEN, Colonel, Commander, New Orleans District, United States Army Corps of Engineers, in his official capacity,

Defendants - Appellees

Appeal from the United States District Court for the Eastern District of Louisiana USDC No. 2:13-CV-4761

Before WIENER, GRAVES, and HO, Circuit Judges. 1 PER CURIAM:* This dispute involves a challenge to environmental mitigation requirements imposed by the U.S. Army Corps of Engineers (the “Corps”) as a prerequisite to excavate and sell soil from private property for use in the

1 Judge Ho concurs in the judgment only.

* Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in 5TH CIR. R. 47.5.4. Case: 17-30438 Document: 00514550755 Page: 2 Date Filed: 07/11/2018

No. 17-30438 Corps’s projects. Appellant claims the mitigation requirements are contrary to federal law and unconstitutional. The district court granted the Corps summary judgment on all claims. We affirm. BACKGROUND In the wake of Hurricanes Rita and Katrina, Congress tasked the Corps with a series of projects collectively known as the Greater New Orleans Hurricane and Storm Damage Risk Reduction System (“HSDRRS”). The HSDRRS required construction, on an “emergency schedule,” of numerous levees, floodwalls, gates, and pumps within Southeastern Louisiana. Corps engineers estimated that completion of the HSDRRS would require 31,000,000 cubic yards of suitable “borrow material.” 2 In order to acquire the needed material, the Corps considered three options: (1) “government-furnished” borrow material, (2) “contractor- furnished” borrow material, and (3) supply contracts. Only the government- furnished and contractor-furnished options are relevant to this appeal. Under the government-furnished option, the Corps would seek to directly obtain the property rights to extract borrow material from an identified piece of land. Under the contractor-furnished option, the Corps would require construction contractors to work “in partnership with a landowner to provide suitable borrow material from the landowner’s property.” In 2008, the Corps considered acquiring the rights to mine government- furnished borrow material on Idlewild, a tract of land owned by White Oak Realty, LLC (“White Oak”). In response, White Oak, fearing a potential eminent domain action against its property, sent the Corps letters informing the Corps that it was “pursuing the property for contractor supply borrow material,” and requesting that the Corps “cease and desist any and all activity

2 “Borrow material” refers to soil “dug in one location for use at another.” 2 Case: 17-30438 Document: 00514550755 Page: 3 Date Filed: 07/11/2018

No. 17-30438 pertaining to government supplied borrow at Idlewild.” The Corps declined to cease consideration of Idlewild as a source of government-furnished borrow material. Nonetheless, the Corps informed White Oak that it remained “free to utilize [its] property in any manner” pending further notification on the Corps’s intentions. The Corps never pursued an eminent domain action. In 2009, White Oak applied for a permit to excavate clay on Idlewild as a source for contractor-supplied borrow material. The Corps pre-approved 3 the permit in October 2010 — with a caveat. As part of its review, the Corps had determined that clay excavation on Idlewild would cause adverse environmental impact on bottomland hardwood forests (“BLH”). To offset that impact, the Corps required mitigation of those environmental impacts “through the purchase of mitigation bank credits.” Purchase of bank credits was only required, however, if Idlewild’s resources were excavated “for use in building the HSDRRS.” “[I]f borrow excavated at [Idlewild] [was] not used in the construction of a [Corps] water resources project, there [was] no [Corps] requirement that impacts to non-wetland bottomland hardwoods be mitigated.” Upset by the cost of available mitigation bank credits, White Oak proposed to fulfill its mitigation requirements by placing 158.36 acres of “wetland and jurisdictionally determined non-wetland” forest in a conservation servitude. The Land Trust for Southeast Louisiana would then work to ensure that the land remained pristine.

3Pre-approval did not guarantee that the Corps’s contractors would select Idlewild as a source of borrow material. It merely meant that the Corps would list Idlewild as a pre- approved site. Contractors were “not obligated to select a site from the contractor-furnished clay source list.” “Agreements for use of a contractor-furnished site would solely be between a construction contractor and the landowner, and at no point in time would the landowner have an agreement with the [Corps].”

3 Case: 17-30438 Document: 00514550755 Page: 4 Date Filed: 07/11/2018

No. 17-30438 The Corps rejected White Oak’s proposal on the grounds that mitigation bank credits were “preferred by both statute and regulation” and were “the most efficient, timely and effective means to achieve the required compensatory mitigation for impacts to contractor-furnished borrow area.” The Corps further explained that the “creation and approval of a mitigation plan is a lengthy and detailed process that can take a year or more.” “Not only [did] the [Corps] not have the manpower to devote to this process for every contractor-furnished borrow site, but it would significantly delay the approval and use of those sites.” The parties then exchanged correspondence for a number of years discussing whether a non-mitigation bank alternative would suit the Corps. Eventually, on February 20, 2013, District Commander Edward Fleming sent a final notice to White Oak reiterating the bank credit mitigation requirement. In response, White Oak filed the instant suit against the Corps on June 10, 2013, alleging that: (1) the Water Resources Development Act (“WRDA”) does not authorize the Corps to require private parties to pay for the mitigation costs, (2) the WRDA does not authorize the Corps to require purchase of mitigation bank credits in this instance, and (3) a taking under the Corps=s mitigation plan would be unconstitutional under the Fifth Amendment. Shortly thereafter, the Corps filed a motion to dismiss the complaint for lack of Article III standing, which the district court denied. The parties then filed cross motions for summary judgment. After summary judgment briefing had concluded, White Oak moved to supplement the administrative record. On May 4, 2016, the district court denied White Oak’s motion to supplement as untimely and unnecessary. The court subsequently granted summary judgment in favor of the Corps on all claims. This appeal timely followed.

4 Case: 17-30438 Document: 00514550755 Page: 5 Date Filed: 07/11/2018

No. 17-30438 STANDARD OF REVIEW “This court reviews a grant of summary judgment de novo, applying the same standard to review the agency’s decision that the district court used.” Baylor Cty. Hosp. Dist. v. Price, 850 F.3d 257, 261 (5th Cir. 2017).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Omnia Commercial Co. v. United States
261 U.S. 502 (Supreme Court, 1923)
Skidmore v. Swift & Co.
323 U.S. 134 (Supreme Court, 1944)
United States v. Grand River Dam Authority
363 U.S. 229 (Supreme Court, 1960)
United States v. Mead Corp.
533 U.S. 218 (Supreme Court, 2001)
American Wildlands v. Kempthorne
530 F.3d 991 (D.C. Circuit, 2008)
Hearts Bluff Game Ranch, Inc. v. United States
669 F.3d 1326 (Federal Circuit, 2012)
Mitchell Arms, Inc. v. United States
7 F.3d 212 (Federal Circuit, 1993)
Dennis Melancon v. City of New Orleans, et
703 F.3d 262 (Fifth Circuit, 2012)
Danvers Motor Co. v. Ford Motor Co.
432 F.3d 286 (Third Circuit, 2005)
Baylor County Hospital Dist v. Thomas Price
850 F.3d 257 (Fifth Circuit, 2017)
Leonard Cottrell v. Alcon Laboratories
874 F.3d 154 (Third Circuit, 2017)
Knapp v. United States Department of Agriculture
796 F.3d 445 (Fifth Circuit, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
White Oak Realty, L.L.C. v. U.S. Army Corps, Counsel Stack Legal Research, https://law.counselstack.com/opinion/white-oak-realty-llc-v-us-army-corps-ca5-2018.