W.G. Barr Management, LLC v. ContekPro LLC

CourtDistrict Court, N.D. California
DecidedJune 5, 2024
Docket3:23-cv-02257
StatusUnknown

This text of W.G. Barr Management, LLC v. ContekPro LLC (W.G. Barr Management, LLC v. ContekPro LLC) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W.G. Barr Management, LLC v. ContekPro LLC, (N.D. Cal. 2024).

Opinion

1 2 3 4 UNITED STATES DISTRICT COURT 5 NORTHERN DISTRICT OF CALIFORNIA 6 7 W.G. BARR MANAGEMENT, LLC, Case No. 23-cv-02257-TSH

8 Plaintiff, ORDER RE: CROSS-MOTIONS FOR 9 v. SUMMARY JUDGMENT

10 CONTEKPRO LLC, Re: Dkt. Nos. 47, 48 11 Defendant.

12 13 I. INTRODUCTION 14 Plaintiff W.G. Barr Beverage Co. (d/b/a Two Pitchers Brewing Co., “Two Pitchers”) 15 alleges Defendant ContekPro, LLC breached their agreement for ContekPro to build and deliver a 16 pre-inspected, finished Kitchen Container to Two Pitchers’ taproom in Oakland. Pending before 17 the Court are the parties’ cross-motions for summary judgment. ECF Nos. 47 (Pl.’s Mot.), 48 18 (Def.’s Mot.). The Court finds the motions suitable for disposition without oral argument and 19 VACATES the June 13, 2024 hearing. See Civ. L.R. 7-1(b). For the reasons stated below, the 20 Court DENIES Two Pitchers’ motion and GRANTS ContekPro’s cross-motion.1 21 II. BACKGROUND 22 Two Pitchers, located in Oakland, California, is a start-up company that brews and 23 distributes craft shandies, which are lagers mixed with natural fruit and fruit juices. First Am. 24 Compl. ¶ 8, 13, ECF No. 11. ContekPro, located in Tigard, Oregon, manufactures and delivers 25 commercial kitchen units built within shipping containers. Attahri Decl. ¶ 3, ECF No. 48-2. 26 On May 18, 2020, Two Pitchers entered into a contract with ContekPro for the 27 1 manufacture and delivery of a commercial Kitchen Container to a taproom Two Pitchers would be 2 opening in Oakland. First Am. Compl. ¶ 13; Arghavani Decl., Ex. 1 (Contract), ECF No. 47-3. 3 The contract provided for a delivery date of approximately September 1, 2020, and the parties 4 subsequently agreed to a delivery date of March 1, 2021. Contract at 3; Arghavani Decl., Ex. 2 5 (Attahri Dep.) at 15:12-16:7, ECF No. 47-4. Two Pitchers made full payment to ContekPro under 6 the contract. Attahri Dep. at 15:6-11. 7 Two Pitchers alleges there were four breaches of the contract, as summarized below. 8 A. California Manufactured Building Sticker 9 The contract specified that ContekPro “certifies that it will construct the buildings exactly 10 as detailed in the approved plans,” and “guarantees the buildings will receive a State of California 11 manufactured building sticker.” Contract at 4. A California manufactured building sticker 12 signifies that a building is pre-inspected and meets all California requirements for using the 13 building. Attahri Dep. at 19:7-10; Arghavani Decl., Ex. 5 (Hester Dep.) at 19:10-17, ECF No. 47- 14 7. 15 ContekPro scheduled an inspection for the container to receive a California manufactured 16 building sticker on March 24, 2021. Arghavani Decl., Ex. 6 (Email re: Container Shipment 17 Timeline); id., Ex. 24 (Email re: Two Pitchers) at 3-8. However, the inspection never took place. 18 Attahri Dep. at 33:21-34:15; id., Ex. 3 at 3 (ContekPro Response to Interrogatories, 1); id., Ex. 7 at 19 3 (ContekPro Requests for Admission, 1). ContekPro never told Two Pitchers what happened 20 with the scheduled March 24 inspection, nor did it explain why it had not obtained the sticker. 21 Hester Dep. at 150:11-151:16. The container never received a California manufactured building 22 sticker. Attahri Dep. at 33:21-34:11; 74:3-5; id., Ex. 7 at 3 (ContekPro Requests for Admission, 23 1); Hester Dep. at 246:12-24. 24 B. Timing of Completion and Inspection 25 The container was shipped unfinished from ContekPro’s facility in Oregon to Two 26 Pitchers’ taproom site on or about April 6, 2021. Arghavani Decl., Ex. 8 (Email re: Two Pitchers 27 Container Shipment); Attahri Dep. at 46:20-22. The parties dispute the reasons why the container 1 undisputed that the container was not pre-inspected, and because it was not finished when 2 delivered, the container was not ready for final inspections. Hester Dep. at 210:13-211:2; Attahri 3 Dep. at 38:4-5; 57:1-58:11; 74:3-5. In July, Attahri acknowledged the container was still 4 unfinished. Arghavani Decl., Ex. 16 (text messages from Yassine Attahri); id., Ex. 17 (same); 5 Attahri Dep. at 40:24-41:4; 62:8-19; 64:12-65:12. As of July 28, 2021, ContekPro’s work on the 6 container was not complete and it was not ready for final inspection. Attahri Dep. at 65:8-12; 7 Hester Dep. at 212:12-24. Two Pitchers subsequently hired other contractors to finish the work on 8 the container and to secure all final inspections. Arghavani Decl., Ex. 18 (email re: Recap Email); 9 id., Ex. 9 (Tallon Dep.) at 169:9-171:1. The container did not pass final inspections until 10 September 1, 2021. Id., Ex. 19 (email re: Container Delay Timeline). 11 C. Code Requirements 12 The contract provides that “ContekPro tests all electrical, water, and gas components of the 13 product and ensures all components work and meet appropriate codes.” Contract at 5. Two 14 Pitchers contends ContekPro’s work did not meet appropriate codes and that the Container could 15 not pass Oakland city code inspections even by the end of July, four months after it was delivered. 16 Pl.’s Mot. at 6 (citing Attahri Dep. at 64:12-21; Hester Dep. at 83:7-85:6; 90:4-9; 245:18-246:11). 17 D. Costs of Rectifying Deficiencies 18 The contract provides that “[i]f the buildings are not constructed as planned, buyer/end 19 user may enter a claim for the cost of rectifying any issues.” Contract at 4. On September 9, 20 2021, Two Pitchers’ counsel sent a letter to ContekPro alleging that ContekPro had breached the 21 contract by failing to deliver a finished, pre-inspected container. Arghavani Decl., Ex. 20 at 2 22 (Email re: Breach of Contract Claim); Attahri Decl., Ex. B (same), ECF No. 48-4. That letter did 23 not include a claim for the cost of rectifying issues with the container. Arghavani Decl., Ex. 20; 24 Answer ¶ 24, ECF No. 16; Attahri Decl., Ex. B. 25 On April 25, 2023, Two Pitchers emailed ContekPro with an accounting for $98,622.70, 26 representing the costs that Two Pitchers alleges it incurred due to the deficiencies in the container. 27 Arghavani Decl., Ex. 20 (Email re: Breach of Contract Claim); id., Ex. 21 (Pl.’s Third Amended 1 E. Procedural Background 2 Two Pitchers filed its original complaint on May 9, 2023 and filed its First Amended 3 Complaint on June 26, 2023. It alleges three causes of action: (1) Breach of Contract; (2) 4 Promissory Estoppel; and (3) Breach of Implied Duty of Good Faith and Fair Dealing. It seeks 5 $98,622.70 in damages, as well as attorneys’ fees and costs. First Am. Compl. at 8-9. 6 As to its breach of contract claim, Two Pitchers alleges ContekPro breached the contract 7 because it failed to deliver a complete, finished Kitchen Container with all necessary approvals 8 and inspections required by applicable law. Id. ¶¶ 26-28. 9 As to its promissory estoppel claim, Two Pitchers alleges it repeatedly conveyed to 10 ContekPro that it could not operate its newly constructed taproom without a functioning kitchen 11 and that, because ContekPro had not completed the container, it would need to pay other 12 contractors to complete it and to secure all necessary approvals and inspections. Id. ¶ 30. Two 13 Pitchers alleges it accepted delivery of the container in April 2021 “in express reliance on 14 ContekPro’s oral assurance that the Container would be fully inspected and approved shortly after 15 delivery of the Container,” and “relied to its detriment on the statement by ContekPro that it would 16 have the Container inspected and approved shortly after its delivery,” when “[i]n fact, ContekPro 17 never completed the work necessary for the Container to pass inspections; the Container was not 18 fully inspected and approved until August 2021, after Two Pitchers paid other contracts to engage 19 in extensive additional work to finish the Container and to secure the necessary approvals and 20 inspections.” Id. ¶ 31.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wright v. Denn Ex Rel. Page
23 U.S. 204 (Supreme Court, 1825)
Klaxon Co. v. Stentor Electric Manufacturing Co.
313 U.S. 487 (Supreme Court, 1941)
Norse v. City of Santa Cruz
629 F.3d 966 (Ninth Circuit, 2010)
Cafasso v. General Dynamics C4 Systems, Inc.
637 F.3d 1047 (Ninth Circuit, 2011)
United States v. Michael A. Respress
9 F.3d 483 (Sixth Circuit, 1993)
Norwest Bank Billings v. Murnion
684 P.2d 1067 (Montana Supreme Court, 1984)
Reed v. Jackson County
803 P.2d 1194 (Court of Appeals of Oregon, 1990)
Schafer v. Fraser Et Ux
294 P.2d 609 (Oregon Supreme Court, 1956)
Ristau v. Wescold, Inc.
868 P.2d 1331 (Oregon Supreme Court, 1994)
Heinzel v. Backstrom
794 P.2d 775 (Oregon Supreme Court, 1990)
City of Ashland v. Hoffarth
733 P.2d 925 (Court of Appeals of Oregon, 1987)
Natkin & Co. v. H.D. Fowler Co.
876 P.2d 319 (Court of Appeals of Oregon, 1994)
Hill v. Mayers
802 P.2d 694 (Court of Appeals of Oregon, 1990)
Neiss v. Ehlers
899 P.2d 700 (Court of Appeals of Oregon, 1995)
Windsor Mills, Inc. v. Collins & Aikman Corp.
25 Cal. App. 3d 987 (California Court of Appeal, 1972)
Simmons v. Wolff
594 F. Supp. 2d 6 (District of Columbia, 2009)
Communication Management Services, LLC v. Qwest Corp.
67 F. Supp. 3d 1159 (D. Oregon, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
W.G. Barr Management, LLC v. ContekPro LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wg-barr-management-llc-v-contekpro-llc-cand-2024.