W.G. Barr Management, LLC v. ContekPro LLC

District Court, N.D. California·Decided June 5, 2024·No. 3:23-cv-02257·Unknown

Opinion

W.G. BARR MANAGEMENT, LLC, Case No. 23-cv-02257-TSH

Plaintiff, ORDER RE: CROSS-MOTIONS FOR v. SUMMARY JUDGMENT

CONTEKPRO LLC, Re: Dkt. Nos. 47, 48 Defendant.

Plaintiff W.G. Barr Beverage Co. (d/b/a Two Pitchers Brewing Co., “Two Pitchers”) alleges Defendant ContekPro, LLC breached their agreement for ContekPro to build and deliver a pre-inspected, finished Kitchen Container to Two Pitchers’ taproom in Oakland. Pending before the Court are the parties’ cross-motions for summary judgment. ECF Nos. 47 (Pl.’s Mot.), 48 (Def.’s Mot.). The Court finds the motions suitable for disposition without oral argument and VACATES the June 13, 2024 hearing. See Civ. L.R. 7-1(b). For the reasons stated below, the Court DENIES Two Pitchers’ motion and GRANTS ContekPro’s cross-motion.1 Two Pitchers, located in Oakland, California, is a start-up company that brews and distributes craft shandies, which are lagers mixed with natural fruit and fruit juices. First Am. Compl. ¶ 8, 13, ECF No. 11. ContekPro, located in Tigard, Oregon, manufactures and delivers commercial kitchen units built within shipping containers. Attahri Decl. ¶ 3, ECF No. 48-2. On May 18, 2020, Two Pitchers entered into a contract with ContekPro for the manufacture and delivery of a commercial Kitchen Container to a taproom Two Pitchers would be opening in Oakland. First Am. Compl. ¶ 13; Arghavani Decl., Ex. 1 (Contract), ECF No. 47-3. The contract provided for a delivery date of approximately September 1, 2020, and the parties subsequently agreed to a delivery date of March 1, 2021. Contract at 3; Arghavani Decl., Ex. 2 (Attahri Dep.) at 15:12-16:7, ECF No. 47-4. Two Pitchers made full payment to ContekPro under the contract. Attahri Dep. at 15:6-11. Two Pitchers alleges there were four breaches of the contract, as summarized below. A. California Manufactured Building Sticker The contract specified that ContekPro “certifies that it will construct the buildings exactly as detailed in the approved plans,” and “guarantees the buildings will receive a State of California manufactured building sticker.” Contract at 4. A California manufactured building sticker signifies that a building is pre-inspected and meets all California requirements for using the building. Attahri Dep. at 19:7-10; Arghavani Decl., Ex. 5 (Hester Dep.) at 19:10-17, ECF No. 47- 7. ContekPro scheduled an inspection for the container to receive a California manufactured building sticker on March 24, 2021. Arghavani Decl., Ex. 6 (Email re: Container Shipment Timeline); id., Ex. 24 (Email re: Two Pitchers) at 3-8. However, the inspection never took place. Attahri Dep. at 33:21-34:15; id., Ex. 3 at 3 (ContekPro Response to Interrogatories, 1); id., Ex. 7 at 3 (ContekPro Requests for Admission, 1). ContekPro never told Two Pitchers what happened with the scheduled March 24 inspection, nor did it explain why it had not obtained the sticker. Hester Dep. at 150:11-151:16. The container never received a California manufactured building sticker. Attahri Dep. at 33:21-34:11; 74:3-5; id., Ex. 7 at 3 (ContekPro Requests for Admission, 1); Hester Dep. at 246:12-24. B. Timing of Completion and Inspection The container was shipped unfinished from ContekPro’s facility in Oregon to Two Pitchers’ taproom site on or about April 6, 2021. Arghavani Decl., Ex. 8 (Email re: Two Pitchers Container Shipment); Attahri Dep. at 46:20-22. The parties dispute the reasons why the container undisputed that the container was not pre-inspected, and because it was not finished when delivered, the container was not ready for final inspections. Hester Dep. at 210:13-211:2; Attahri Dep. at 38:4-5; 57:1-58:11; 74:3-5. In July, Attahri acknowledged the container was still unfinished. Arghavani Decl., Ex. 16 (text messages from Yassine Attahri); id., Ex. 17 (same); Attahri Dep. at 40:24-41:4; 62:8-19; 64:12-65:12. As of July 28, 2021, ContekPro’s work on the container was not complete and it was not ready for final inspection. Attahri Dep. at 65:8-12; Hester Dep. at 212:12-24. Two Pitchers subsequently hired other contractors to finish the work on the container and to secure all final inspections. Arghavani Decl., Ex. 18 (email re: Recap Email); id., Ex. 9 (Tallon Dep.) at 169:9-171:1. The container did not pass final inspections until September 1, 2021. Id., Ex. 19 (email re: Container Delay Timeline). C. Code Requirements The contract provides that “ContekPro tests all electrical, water, and gas components of the product and ensures all components work and meet appropriate codes.” Contract at 5. Two Pitchers contends ContekPro’s work did not meet appropriate codes and that the Container could not pass Oakland city code inspections even by the end of July, four months after it was delivered. Pl.’s Mot. at 6 (citing Attahri Dep. at 64:12-21; Hester Dep. at 83:7-85:6; 90:4-9; 245:18-246:11). D. Costs of Rectifying Deficiencies The contract provides that “[i]f the buildings are not constructed as planned, buyer/end user may enter a claim for the cost of rectifying any issues.” Contract at 4. On September 9, 2021, Two Pitchers’ counsel sent a letter to ContekPro alleging that ContekPro had breached the contract by failing to deliver a finished, pre-inspected container. Arghavani Decl., Ex. 20 at 2 (Email re: Breach of Contract Claim); Attahri Decl., Ex. B (same), ECF No. 48-4. That letter did not include a claim for the cost of rectifying issues with the container. Arghavani Decl., Ex. 20; Answer ¶ 24, ECF No. 16; Attahri Decl., Ex. B. On April 25, 2023, Two Pitchers emailed ContekPro with an accounting for $98,622.70, representing the costs that Two Pitchers alleges it incurred due to the deficiencies in the container. Arghavani Decl., Ex. 20 (Email re: Breach of Contract Claim); id., Ex. 21 (Pl.’s Third Amended E. Procedural Background Two Pitchers filed its original complaint on May 9, 2023 and filed its First Amended Complaint on June 26, 2023. It alleges three causes of action: (1) Breach of Contract; (2) Promissory Estoppel; and (3) Breach of Implied Duty of Good Faith and Fair Dealing. It seeks $98,622.70 in damages, as well as attorneys’ fees and costs. First Am. Compl. at 8-9. As to its breach of contract claim, Two Pitchers alleges ContekPro breached the contract because it failed to deliver a complete, finished Kitchen Container with all necessary approvals and inspections required by applicable law. Id. ¶¶ 26-28. As to its promissory estoppel claim, Two Pitchers alleges it repeatedly conveyed to ContekPro that it could not operate its newly constructed taproom without a functioning kitchen and that, because ContekPro had not completed the container, it would need to pay other contractors to complete it and to secure all necessary approvals and inspections. Id. ¶ 30. Two Pitchers alleges it accepted delivery of the container in April 2021 “in express reliance on ContekPro’s oral assurance that the Container would be fully inspected and approved shortly after delivery of the Container,” and “relied to its detriment on the statement by ContekPro that it would have the Container inspected and approved shortly after its delivery,” when “[i]n fact, ContekPro never completed the work necessary for the Container to pass inspections; the Container was not fully inspected and approved until August 2021, after Two Pitchers paid other contracts to engage in extensive additional work to finish the Container and to secure the necessary approvals and inspections.” Id. ¶ 31. It alleges that “[w]hen it became clear that ContekPro was not willing to complete the work in a timely fashion, Two Pitchers acted in further reliance on ContekPro’s position, including the terms of the written contract that it could ‘enter a claim for the cost of rectifying any issues’ with the Container, and engaged other contractors to complete the work on the Kitchen Container.” Id. Because Two Pitchers “acted in reliance on the position of ContekPro and incurred the costs needed to c

Free access — add to your briefcase to read the full text and ask questions with AI

W.G. Barr Management, LLC v. ContekPro LLC, (N.D. Cal. 2024).

W.G. Barr Management, LLC v. ContekPro LLC (W.G. Barr Management, LLC v. ContekPro LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Wright v. Denn Ex Rel. Page
23 U.S. 204 (Supreme Court, 1825)
Klaxon Co. v. Stentor Electric Manufacturing Co.
313 U.S. 487 (Supreme Court, 1941)
Norse v. City of Santa Cruz
629 F.3d 966 (Ninth Circuit, 2010)
Cafasso v. General Dynamics C4 Systems, Inc.
637 F.3d 1047 (Ninth Circuit, 2011)
United States v. Michael A. Respress
9 F.3d 483 (Sixth Circuit, 1993)
Norwest Bank Billings v. Murnion
684 P.2d 1067 (Montana Supreme Court, 1984)
Reed v. Jackson County
803 P.2d 1194 (Court of Appeals of Oregon, 1990)
Schafer v. Fraser Et Ux
294 P.2d 609 (Oregon Supreme Court, 1956)
Ristau v. Wescold, Inc.
868 P.2d 1331 (Oregon Supreme Court, 1994)
Heinzel v. Backstrom
794 P.2d 775 (Oregon Supreme Court, 1990)
City of Ashland v. Hoffarth
733 P.2d 925 (Court of Appeals of Oregon, 1987)
Natkin & Co. v. H.D. Fowler Co.
876 P.2d 319 (Court of Appeals of Oregon, 1994)
Hill v. Mayers
802 P.2d 694 (Court of Appeals of Oregon, 1990)
Neiss v. Ehlers
899 P.2d 700 (Court of Appeals of Oregon, 1995)
Windsor Mills, Inc. v. Collins & Aikman Corp.
25 Cal. App. 3d 987 (California Court of Appeal, 1972)
Simmons v. Wolff
594 F. Supp. 2d 6 (District of Columbia, 2009)
Communication Management Services, LLC v. Qwest Corp.
67 F. Supp. 3d 1159 (D. Oregon, 2014)