Natkin & Co. v. H.D. Fowler Co.

876 P.2d 319, 128 Or. App. 311, 24 U.C.C. Rep. Serv. 2d (West) 801, 1994 Ore. App. LEXIS 921
CourtCourt of Appeals of Oregon
DecidedJune 8, 1994
DocketC92-0393CV; CA A78899
StatusPublished
Cited by11 cases

This text of 876 P.2d 319 (Natkin & Co. v. H.D. Fowler Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Natkin & Co. v. H.D. Fowler Co., 876 P.2d 319, 128 Or. App. 311, 24 U.C.C. Rep. Serv. 2d (West) 801, 1994 Ore. App. LEXIS 921 (Or. Ct. App. 1994).

Opinions

[313]*313WARREN, P. J.

Plaintiff appeals from a judgment dismissing its complaint for failure to state a claim. ORCP 21A(8). We reverse in part and affirm in part.

In reviewing the granting of a motion to dismiss, we assume the truth of all allegations, as well as any inferences that may be drawn from them, and view them in the light most favorable to the nonmoving party. Oksenholt v. Lederle Laboratories, 294 Or 213, 215, 656 P2d 293 (1982). We determine whether the complaint states a claim as a matter of law. Hansen v. Anderson, 113 Or App 216, 218, 831 P2d 717 (1992).

Plaintiff is a subcontractor. Defendant H.D. Fowler Company (Fowler) is a manufacturer’s agent. Defendant Couch Pump Company (Couch) is a manufacturer of heavy-duty pumps. Plaintiff solicited bids for pumps it needed for a construction project. Fowler, as agent for Couch, submitted a written offer to provide those pumps. The offer, which is incorporated by reference into the complaint, contained two variations from the contract specifications plaintiff provided to Couch. Plaintiff contacted Fowler about those variations. Fowler told plaintiff that the pumps “would meet all of the contract specifications.” Plaintiff incorporated Couch’s offer into a bid that it submitted to a general contractor, who awarded plaintiff a subcontract. Plaintiff then told Fowler that it was accepting Couch’s offer. Couch supplied plaintiff with shop drawings to submit to the general contractor for approval. The general contractor did not approve the drawings, and Couch refused to supply different drawings or pumps that would comply with contract specifications.1

Plaintiff brought this action, asserting three claims for relief. Defendants successfully moved to dismiss each of the claims. Plaintiffs first assignment is that the court erred in dismissing its first claim for relief, denominated “Promissory Estoppel,” arguing that it has pleaded all of the elements of promissory estoppel. Defendants argue that promissory estoppel does not apply to the facts in this case [314]*314and, even if it does, plaintiff did not plead the required elements.

Promissory estoppel is not an independent cause of action. It is a substitute for consideration, and provides a basis for enforcing a promise as a contract despite a lack of consideration, when the promisee has relied on a promise to his or her detriment. City of Ashland v. Hoffarth, 84 Or App 265, 270, 733 P2d 925, rev den 303 Or 483 (1987). A promise is enforceable by reason of promissory estoppel if there is: (1) a promise; (2) the promisor could reasonably foresee the promise would induce conduct of the kind that occurred; (3) actual reliance on the promise; and (4) a substantial change in position by the party seeking to enforce the promise. Schafer et al v. Fraser et ux, 206 Or 446, 472, 290 P2d 190 (1956); Bixler v. First National Bank, 49 Or App 195, 199, 619 P2d 895 (1980). The doctrinéis applied if “injustice canbe avoided only by enforcement of the promise.” Restatement of Contracts § 90 (1932); quoted with approval in Schafer et al v. Fraser et ux, supra, 206 Or at 468.

Plaintiff first alleges that Couch made a written offer to supply pumps. That offer contained two “exceptions” to the contract specifications. Next, plaintiff alleges:

“On or about July 2, 1992, [plaintiff] contacted Defendant Fowler, as agent for Couch, regarding the exceptions noted on the quote * * * whereupon, Fowler, as agent for Couch, informed [plaintiff] that the [pumps] it was offering, as agent for Couch, would meet all of the contract specifications * * * required for the DWWTP project, notwithstanding the exceptions noted on the written offer to [plaintiff].”

That allegation is susceptible to different interpretations. Defendants contend that plaintiff alleges Fowler promised the pumps would meet all “product specifications,” that is, although nonconforming, they would meet the performance requirements of the contract. Plaintiff argues that it has alleged that Fowler modified the offer by withdrawing the exceptions contained in the written offer. Defendants assert that, if the allegation is interpreted as an allegation that Fowler modified the bid, “there are no allegations that the bid as ‘modified’ was sufficiently specific to constitute a firm ‘promise.’ ”

[315]*315Assuming the truth of plaintiffs allegations and viewing them in the light most favorable to plaintiff, Couch first made an offer to supply pumps that varied from contract specifications. Fowler, as agent for Couch, then modified the offer by withdrawing the “exceptions” that it contained. Because Fowler did not change any other term of the written offer, the modified offer was sufficiently specific to be a “firm promise.” Plaintiff relies on promissory estoppel as abasis for enforcing Fowler’s promise that allegedly modified the written offer. It alleges:

“8.
“By submitting an offer to [plaintiff] to provide the [pumps] for the Project, which would meet all contract specifications, Couch expected that if its bid was deemed the most advantageous bid by [plaintiff], its bid would be used by [plaintiff] in its proposal for the work.
“9.
“[Plaintiff] relied upon the bid of Couch and the promise that its pumps would meet all of the contract specifications, which reliance resulted in [plaintiffs] incorporation of Couch’s offer for the pumps in its own subcontract bid. Such reliance was reasonable and was expected by Couch when it submitted its offer to [plaintiff] and when it promised, through its agent Fowler, that its [pumps] would meet all of the contract specifications.
‡ *
“11.
“[Plaintiffs] subcontract bid, which included Couch’s offer for [pumps], was accepted by the general contractor * * *. Upon [the general contractor’s] acceptance of [plaintiffs] bid, [plaintiff] informed Couch, through its agent, Fowler, that its bid was being accepted and submitted a purchase order to Couch through Fowler.
“15.
“Despite [plaintiffs] demand that Couch perform according to its offer, Couch * * * has failed to supply plaintiff with [pumps] which complied with the contract specifications.
“16.
“As a result of * * * Couch’s failure and refusal to perform, despite demands by [plaintiff], plaintiff has been damaged in [316]*316that it was required to purchase [pumps], which would meet the contract specifications, from another supplier * * *.”

We need not consider whether plaintiff has stated a claim for breach of contract based on a theory of promissory estoppel, because we conclude that plaintiff has sufficiently alleged breach of an express contract. See Chaney v. Shell Oil Co., 111 Or App 556, 827 P2d 196, rev den 313 Or 299 (1992). Assumingthe truth of plaintiffs allegations, Couch offered to supply plaintiff conforming pumps. Plaintiff accepted. Couch breached the parties’ agreement by failing to supply those pumps and plaintiff was damaged.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
D. Oregon, 2026
Jurj v. Andersen
D. Oregon, 2024
Barinaga v. JP Morgan Chase & Co.
749 F. Supp. 2d 1164 (D. Oregon, 2010)
Franke v. Oregon Department of Fish & Wildlife
2 P.3d 921 (Court of Appeals of Oregon, 2000)
Duncan v. Office Depot
973 F. Supp. 1171 (D. Oregon, 1997)
Mittleman Properties v. Bank of California
886 P.2d 1061 (Court of Appeals of Oregon, 1994)
Loewen v. Galligan
882 P.2d 104 (Court of Appeals of Oregon, 1994)
Natkin & Co. v. H.D. Fowler Co.
876 P.2d 319 (Court of Appeals of Oregon, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
876 P.2d 319, 128 Or. App. 311, 24 U.C.C. Rep. Serv. 2d (West) 801, 1994 Ore. App. LEXIS 921, Counsel Stack Legal Research, https://law.counselstack.com/opinion/natkin-co-v-hd-fowler-co-orctapp-1994.