Westlake View Condominium Ass'n v. Sixth Avenue View Partners, LLC

193 P.3d 161, 146 Wash. App. 760
Court of Appeals of Washington·Decided August 11, 2008·No. No. 60167-9-I·Published·Cited by 7 cases

Opinion

Becker, J.

¶1 A condominium homeowners’ association sued the builder of the condos for breaching the implied warranty of habitability. The builder moved for summary judgment. The association presented evidence of regular water intrusion into the units, inadequately sloped decks, loose railings on decks, improperly installed windows, and other structural problems. Such evidence is sufficient to create a question of fact for the jury to determine whether the builder breached the implied warranty of habitability. Summary judgment for the builder is reversed.

¶2 Sixth Avenue View Partners built Westlake View Condominiums near Lake Union in 1999. Westlake has six units, two units on each of three floors. The two units on the top floor of the condominium have large decks that extend over the living areas of the units on the second floor.

¶3 The city of Seattle issued a certificate of occupancy on June 10, 1999. The six condos sold between June and September 1999.

¶4 Right away, the homeowners’ association began notifying the builder, Rick Hunter, about construction problems with the condos. For example, the door leading to the deck had not been installed properly on unit 101, so the lock did not line up with the bolt and the owner was unable to lock the door. The deck on unit 201 did not have sufficient drainage, and as a result there were huge puddles on the deck after every rainfall. Hunter wrote back to the owner of unit 201 saying that he would ask his superintendent to look into the deck problems. The record contains no information as to any further communication that might have taken place between the homeowners’ association and Hunter in the next few years.

¶5 The homeowners’ association filed suit against Sixth Avenue in February 2004 for breach of contract, express warranties, and the implied warranty of habitability.

[763] ¶6 Several of the homeowners experienced ongoing water intrusion problems in their units. In March 2004, the association hired contractor McBride Construction to investigate how water was getting into the units. Following a two-day inspection, McBride prepared a report stating that water damage was evident in the interior wallboards of two units and in the structural framing of the deck surface and the deck handrail attachments on unit 301. The metal deck railing moved about 6 inches in and out when grasped. The report identified the visibly bowed and damaged window frames in all other units as another area of concern.

¶7 McBride identified several areas of poor workmanship that likely contributed to the water intrusion: poor installation of weather resistant barrier paper, poor installation of metal coping on the deck railing, and the failure to seal or properly shim the windows. The association sent Hunter a copy of the McBride report in April 2004. Hunter responded that he would have his construction superintendent review the report and make recommendations, but he believed that the condos were “out of warranty” and that “any repairs should be made through an insurance claim.”

¶8 The association hired Bridge Planning Architecture to investigate the conditions of the building and develop a repair plan that was submitted in March 2005. Bridge was familiar with some of the building’s water intrusion problems as it had responded to emergency leak conditions in units 201 and 301 on two separate occasions. Bridge sampled for mold in the units and did a selective destructive investigation in February 2005. Bridge reviewed and incorporated the McBride report into its findings and recommendations.

¶9 The Bridge report stated that the decks on the units were inadequately sloped to drain. The inadequate slope was said to be a factor contributing to the “persistent leaking condition into unit 201.” Bridge recommended that the upper decks be rebuilt to provide the appropriate slope for drainage. The report noted that the deck columns were showing signs of excessive water intrusion. Bridge recommended stripping the siding and paper from the columns, [764] repairing the decay, and then applying weather resistant barrier. The deck railings on all units were “poorly set and sealed,” a condition that contributed to the leaking in unit 201. Additionally, the railing was loose at the upper decks due to poor anchorage. Bridge recommended that the railings be removed and reset with proper materials to prevent water intrusion and further decay.

¶10 The Bridge report stated that the windows in most units “are experiencing deformation of the vinyl frame to a degree where failure of the window to perform is anticipated.” Further, “[virtually every unit owner complains of excessive and recurring mold at the window sills and bottom sash of the glazed units themselves. The pervasive nature of this condition and the frequent recurrence of every 3-4 months (anecdotal) indicate a failure at the windows and a potentially pervasive life safety concern.”

¶11 Bridge recommended that all windows be replaced, with proper flashing and seals. The report pointed out that the siding installed at the windows without sealant creates “a direct pathway for water to the window” and that there was evidence that water had been leaching from behind the siding. Mold was found on exposed sheathing and framing at exterior conditions, interior wall and ceiling cavities coincident with areas of water intrusion, interior gypsum behind base and door casing conditions where water intrusion was noted, and windows at every unit.

¶12 The report identified the building’s seismic system as a potential area of concern. Bridge noted that there is a large crack running across the floor at the garage/basement level and that there is “noticeable cracking directly above the floor crack in the ceiling the full width span of the garage.” There are cracks above the doors and nail heads popping through the ceiling in almost every unit. The report states, “If the seismic system is defectively installed it may represent a life safety hazard to the occupants.” Completing the repairs recommended in the Bridge Report would cost approximately $341,000.

[765] ¶13 Sixth Avenue moved for summary judgment in September 2005 on the grounds that the plaintiff had failed to provide Sixth Avenue with the mandatory preclaim notice of 45 days prior to filing suit in violation of RCW 64.50.020. The trial court granted summary judgment. The plaintiff appealed. In July 2006, the Court of Appeals remanded the case back to the superior court based on a stipulated order in light of the Supreme Court’s recent decision, Lakemont Ridge Homeowners Ass’n v. Lakemont Ridge Ltd. Partnership, 156 Wn.2d 696, 131 P.3d 905 (2006).

¶14 Sixth Avenue filed a second summary judgment motion to dismiss all of the plaintiff’s claims on March 9, 2007. Sixth Avenue argued that it was entitled to judgment because the statute of limitations barred the plaintiff’s claims. Additionally, Sixth Avenue claimed that the implied warranty of habitability claim was factually unsupported because the alleged defects did not involve fundamental foundation or support problems.

Free access — add to your briefcase to read the full text and ask questions with AI

Westlake View Condominium Ass'n v. Sixth Avenue View Partners, LLC, 193 P.3d 161, 146 Wash. App. 760 (Wash. Ct. App. 2008).

193 P.3d 161 (Westlake View Condominium Ass'n v. Sixth Avenue View Partners, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Kaylynn Lareau v. Thomas Greene, et ux
Court of Appeals of Washington, 2025
Pham v. Corbett
351 P.3d 214 (Court of Appeals of Washington, 2015)
Lang Pham v. Shawn Corbett
Court of Appeals of Washington, 2015
Eric & Susie Kim v. Shelly & John Doe Forest
Court of Appeals of Washington, 2014
Landis & Landis Construction, LLC v. Nation
286 P.3d 979 (Court of Appeals of Washington, 2012)
Westlake View Condo. Ass'n v. Sixth Ave. View Partners, LLC
193 P.3d 161 (Court of Appeals of Washington, 2008)
Westlake View Condominium Ass'n v. Sixth Avenue View Partners, LLC
146 Wash. App. 1030 (Court of Appeals of Washington, 2008)