Westlake Financial Group, Inc. v. CDH-Delnor Health System

2015 IL App (2d) 140589
CourtAppellate Court of Illinois
DecidedMarch 5, 2015
Docket2-14-0589
StatusPublished
Cited by19 cases

This text of 2015 IL App (2d) 140589 (Westlake Financial Group, Inc. v. CDH-Delnor Health System) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Westlake Financial Group, Inc. v. CDH-Delnor Health System, 2015 IL App (2d) 140589 (Ill. Ct. App. 2015).

Opinion

Illinois Official Reports

Appellate Court

Westlake Financial Group, Inc. v. CDH-Delnor Health System, 2015 IL App (2d) 140589

Appellate Court WESTLAKE FINANCIAL GROUP, INC., Plaintiff-Appellant, v. Caption CDH-DELNOR HEALTH SYSTEM, f/k/a Delnor Community Health System, Defendant-Appellee.

District & No. Second District Docket No. 2-14-0589

Filed January 6, 2015

Held The trial court’s dismissal of plaintiff’s complaint for breach of (Note: This syllabus contract arising from a brokerage agreement under which defendant constitutes no part of the hired plaintiff to act as defendant’s insurance broker to procure opinion of the court but benefits for defendant’s employees was reversed, since the trial court has been prepared by the erred in determining that a termination clause in a separate contract Reporter of Decisions between the parties permitted defendant to terminate the contract at for the convenience of issue without cause and that plaintiff’s damages were barred by a the reader.) limitation-of-liability clause, especially when the two contracts dealt with different subject matter and the termination clauses did not equally apply to both contracts, and the limitation-of-liability clause barred only consequential damages from lost profits, not direct damages from lost profits.

Decision Under Appeal from the Circuit Court of Lake County, No. 13-L-747; the Review Hon. Diane E. Winter, Judge, presiding.

Judgment Reversed and remanded. Counsel on Robert S. Reda and Kristina A. McClure, both of Reda & Des Jardins, Appeal Ltd., of Lake Forest, for appellant.

Alison C. Conlon and Colleen J. Balek, both of Barnes & Thornburg LLP, of Chicago, for appellee.

Panel JUSTICE SPENCE delivered the judgment of the court, with opinion. Justices McLaren and Hudson concurred in the judgment and opinion.

OPINION

¶1 Plaintiff, Westlake Financial Group, Inc. (Westlake), appeals from the trial court’s dismissal of its amended breach-of-contract complaint against defendant, CDH-Delnor Health System, f/k/a Delnor Community Health System (Delnor). Westlake argues that the trial court erred in ruling that: (1) a termination clause in a separate contract allowed Delnor to terminate the agreement at issue without cause; and (2) all of Westlake’s damages were barred under a limitation-of-liability clause. We conclude that, while the contracts should be construed together, their termination clauses do not equally apply to both contracts, which cover different subject matter. We also conclude that the limitation-of-liability clause bars only consequential damages from lost profits and not direct damages from lost profits. We therefore reverse and remand.

¶2 I. BACKGROUND ¶3 Westlake filed its initial complaint on October 2, 2013. The trial court granted Delnor’s motion to dismiss the complaint, and Westlake was given leave to amend its complaint. Westlake filed an amended complaint on March 18, 2014, alleging as follows in relevant part. On January 1, 2008, Westlake and Delnor entered into a brokerage agreement (General Service Agreement or GSA) whereby Delnor hired Westlake to, inter alia, act as its insurance broker and procure benefits for its employees. Westlake agreed to create and/or provide the following: a confidential and secure website branded and coded for Delnor’s employees to manage their healthcare and benefits; use of Westlake’s “Online Enrollment System” software through the Delnor website; confidential and secure administration of benefits; a benefit call center; and confidential and secure access to and use of Westlake’s “WITS Program,” subject to a “WITS Program Service Agreement” (WITS Agreement), through which Delnor employees could track the resolution of issues concerning their individual benefits and claims. In exchange for its services, Westlake would be paid certain

-2- fees and receive certain commissions. The terms of the agreement were to begin on January 1, 2010, and terminate on December 31, 2014.1 ¶4 Westlake further alleged as follows. It performed all of its duties under the General Service Agreement and the WITS Agreement, as well as a “Non-Disclosure Agreement,” excepting only performance prevented by Delnor’s actions. The termination clause in paragraph 3.2 of the GSA stated: “Termination by Delnor. Delnor may terminate this Agreement at any time upon sixty (60) days prior written notice if (i) WestLake[ 2 ] is unable to fulfill its responsibilities under this Agreement, or WestLake is otherwise in material breach of any provision of this Agreement, and (ii) Delnor has given WestLake written notice of such failure or breach and WestLake has not cured such deficiency during such sixty (60) day period.” The WITS Agreement also had a termination clause, but its integration clause stated that the termination clause was limited to the WITS Agreement only. On about March 31, 2011, Delnor breached the GSA’s termination clause by one or more of the following acts: (1) notifying Westlake in a letter dated April 18, 2011, that it had replaced Westlake as its insurance broker effective March 31, 2011; (2) merging into CDH-Delnor Health System and ceasing to exist as a separate corporate entity; and (3) hiring another company to provide it brokerage services. Delnor confirmed the March breach on December 30, 2011, by discontinuing use of Westlake’s brokerage services, switching to another broker, and refusing to make any further payments under the GSA. As a direct result, Westlake suffered the loss of at least 24 months of commissions on benefits as guaranteed by the GSA, leading to damages exceeding $350,000. The costs saved by Westlake in not having to perform the remainder of the agreement were nominal because it had already completed the Delnor website and because Westlake’s support center and WITS program were already staffed as fixed costs of Westlake’s operations. Alternatively, Westlake lost “the value of creating and providing the Delnor Website and the WITS Service,” which Westlake believed exceeded $100,000. ¶5 On April 15, 2014, Delnor filed a motion to dismiss the amended complaint under section 2-615 of the Code of Civil Procedure (Code) (735 ILCS 5/2-615 (West 2012)). It argued that, based on the GSA’s integration clause and the fact that the parties contemporaneously executed both the GSA and the WITS Agreement, the agreements should be read together and thus Delnor properly terminated the GSA by giving Westlake more than 60 days’ written notice under the WITS Agreement’s termination clause, which stated: “Term: Termination. This Agreement will commence on January 1, 2008, and continue for a five year period until December 31, 2012, unless terminated earlier in accordance with this Section 5 of the Agreement [(the same paragraph)]. Either party may terminate this Agreement by written notice if the other party materially defaults in the performance of any of its material duties or obligations hereunder, and such default is not substantially cured within sixty (60) days after written notice from the

1 The GSA actually stated that it was effective through December 31, 2012, as Westlake acknowledges in its brief’s statement of facts. 2 The contract refers to Westlake as “WestLake,” but we use the spelling Westlake applies to itself in its briefs.

-3- other party describing the material default. Either party may terminate this Agreement for any reason by providing sixty (60) days prior written notice to the other party.” (Emphasis added.) Delnor alternatively argued that Westlake could not recover for breach of contract because its damages claim was uncertain, speculative, and limited by the GSA’s clear language. ¶6 The trial court granted Delnor’s motion to dismiss on May 21, 2014. The trial court found as follows.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

High Concept Holdings, Inc. v. Precision Body Works, Inc.
2025 IL App (1st) 250338-U (Appellate Court of Illinois, 2025)
Nitekman v.Fifield Construction and Realty, LLC
2023 IL App (1st) 211319-U (Appellate Court of Illinois, 2023)
Ivey v. Transunion Rental Screening Solutions, Inc.
2021 IL App (1st) 200894 (Appellate Court of Illinois, 2021)
Willow Electrical Supply Co., Inc. v. Fleites
2020 IL App (1st) 181329-U (Appellate Court of Illinois, 2020)
Solargenix Energy, LLC v. Acciona Solar Energy, LLC
2020 IL App (1st) 180176-U (Appellate Court of Illinois, 2020)
Union Tank Car Co. v. NuDevco Partners Holdings, LLC
2019 IL App (1st) 172858 (Appellate Court of Illinois, 2019)
AMA Realty Group of Illinois v. Melvin M. Kaplan Realty, Inc.
2015 IL App (1st) 143600 (Appellate Court of Illinois, 2015)
Maglio v. Advocate Health and Hospitals Corporation
2015 IL App (2d) 140782 (Appellate Court of Illinois, 2015)
AMA Realty Group of Illinois v. Melvin M. Kaplan Realty, Inc.
2015 IL App (1st) 143600 (Appellate Court of Illinois, 2015)
Fiala v. Bickford Senior Living Group, LLC
2015 IL App (2d) 141160 (Appellate Court of Illinois, 2015)
Medfusion, Inc. v. Allscripts Healthcare Solutions, Inc.
2015 NCBC 31 (North Carolina Business Court, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
2015 IL App (2d) 140589, Counsel Stack Legal Research, https://law.counselstack.com/opinion/westlake-financial-group-inc-v-cdh-delnor-health-s-illappct-2015.