Nitekman v.Fifield Construction and Realty, LLC
Opinion
2023 IL App (1st) 211319-U No. 1-21-1319
Order filed March 31, 2023 FIFTH DIVISION
NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1).
IN THE
APPELLATE COURT OF ILLINOIS FIRST JUDICIAL DISTRICT
MICHAEL NITEKMAN, ) Appeal from the ) Circuit Court of
Plaintiff-Appellee, ) Cook County.
)
v. ) No. 2017 L 2557 )
FIFIELD CONSTRUCTION AND REALTY, ) Honorable LLC, and CHRISTOPHER FIFIELD, ) Margaret A. Brennan, ) Judge presiding.
Defendants-Appellants. )
JUSTICE MITCHELL delivered the judgment of the court.
Presiding Justice Delort and Justice Lyle concurred in the judgment.
ORDER
¶1 Held: We reverse the trial court’s award of damages and remand with directions to reduce the compensatory damages on the breach of contract claim and to vacate the judgment on the consumer fraud claim, including the award of punitive damages and attorney fees.
¶2 Defendants Fifield Construction and Realty, LLC and Christopher Fifield appeal the trial court’s judgment order awarding plaintiff Michael Nitekman $334,551.38 after a bench trial in this home remodeling case. Fifield raises two issues: (1) is the trial court’s award of $133,750.53 in compensatory damages against the manifest weight of the evidence; and (2) did the trial court err in finding a violation of the Illinois Consumer Fraud and Deceptive Business Practices Act because
that claim was duplicative of the breach of contract? For the following reasons, we reverse and remand with directions.
¶3 BACKGROUND
¶4 Plaintiff Michael Nitekman, along with his wife, Phoebe Nitekman, made plans to build a third-floor addition to their two-story house and a “breezeway” connecting the house to a detached garage. After months of discussions, Christopher Fifield—the sole member, manager, and employee of Fifield Construction and Realty, LLC—entered into an agreement with the Nitekmans to complete the construction for $344,285. During the time that Fifield worked on the project, the Nitekmans submitted periodic payments to Fifield and, at times, paid Fifield’s subcontractors directly at Fifield’s direction.
¶5 During the construction, the Nitekmans discovered water leaking into their bedrooms. The leak continued for several weeks without much reprieve. After a lengthy dispute over the leak and other defects with the construction, Fifield emailed Nitekman announcing that he was walking away from the project. By this time, the Nitekmans had paid $97,622.12 to Fifield directly and $84,823.86 to various subcontractors and material suppliers. Subsequently, the Nitekmans hired two replacement contractors: Wickright, to complete the breezeway portion of the project, and NewLook Construction LLC, for an “emergency” repair of the water leak and masonry defects with the third-floor addition and other work.
¶6 Nitekman filed a lawsuit against Fifield alleging breach of contract and violation of the Illinois Consumer Fraud and Deceptive Business Practices Act (815 ILCS 505/1 et seq. (West 2016)), among other claims. After bench trial, the trial court entered judgment in favor of Nitekman on both the breach of contract and the Consumer Fraud Act claims, awarding $334,551.38. The
award consisted of $133,750.53 in compensatory damages for the breach of contract claim, $50,000 in punitive damages for the Consumer Fraud Act violation, and $150,800.85 in attorney fees under the Consumer Fraud Act. The trial court denied Nitekman’s motion to reconsider and Fifield’s motion to vacate the judgment. Fifield timely appealed. Ill. S. Ct. R. 303 (eff. July 1, 2017).
¶7 ANALYSIS
¶8 A. Breach of Contract Damages
¶9 Fifield argues that the trial court’s award of $133,750.53 in compensatory damages is against the manifest weight of the evidence because the trial court did not offset the award by the amount unpaid on the original $344,285 contract, thus resulting in a windfall for Nitekman. The issue of damages is a question of fact, and a trial court’s finding on damages will not be disturbed on appeal unless it is against the manifest weight of the evidence. Fieldcrest Builders. Inc. v. Antonucci, 311 Ill. App. 3d 597, 607 (1999). A damages award is against the manifest weight of the evidence only where it is apparent that the trial court ignored the evidence or that its measure of damages was erroneous as a matter of law. Id.
¶ 10 In the context of a construction contract, when a builder has provided less than full performance or has provided defective performance, the measure of damages is “the cost of repairing the defects and/or completing the project.” Kirkpatrick v. Strosberg, 385 Ill. App. 3d 119, 137 (2008); Meyers v. Woods, 374 Ill. App. 3d 440, 453-54 (2007). The general rule in contract actions is that damages should place the injured party in the position he would have been had the contract been performed, but not in a better position. Walker v. Ridgeview Construction Co., Inc., 316 Ill. App. 3d 592, 596 (2000). Thus, predicated on this general rule, the proper
calculation of damages is the cost of repair or the cost of completion minus the original contract price. Castricone v. Michaud, 223 Ill. App. 3d 138, 140 (1991) (quoting Ross v. Danter Associates, Inc., 102 Ill. App. 2d 354, 370 (1968)) (“the measure of damages in this type of case is the ‘difference between the cost of constructing, by contract, the building the contractor agreed to put up, and the fair cost market price of erecting such building’”).
¶ 11 Castricone is illustrative of this “contract price limitation” rule, which applies squarely to “cases in which the purchaser’s damages are measured using the cost of completion/repairs standard”. 223 Ill. App. 3d at 141-42. In Castricone, the trial court awarded the homeowners the entire cost incurred in completing and repairing the house: $27,407.88. Id. at 139. The appellate court subsequently reduced this award, applying the rule that “the total cost of completing the home must be netted against the original contract price.” Id. at 141. Because the homeowners contracted for an $89,000 project, their damages were the amount in excess of the $89,000 contract price, not the entire amount they expended in completing and repairing the home. Id. at 142.
¶ 12 Here, Fifield contends that Nitekman has paid a total of $363,894.98 for the construction project, including the costs to repair defects and to complete the work after Fifield’s breach. Because Nitekman had contracted for a $344,285 project 1, the damages he is entitled to would be the amount in excess of $344,285, which Fifield argues is $19,609.98 ($363,894.98 – $344,285). This sum of $363,894.98 is, however, not inclusive of all costs Nitekman expended in connection with this construction project. Fifield breaks down the sum into $182,446.98 (payments Nitekman
1 Nitekman disputes the actual contract price. However, the trial court found that “a valid and enforceable oral agreement existed” between the parties for the project price of $344,285, and this finding was not challenged on appeal.
made to Fifield and subcontractors); $96,000 (cost of completion of the breezeway); and $85,449 (various costs of repair that the trial court awarded).
Free access — add to your briefcase to read the full text and ask questions with AI
2023 IL App (1st) 211319-U (Nitekman v.Fifield Construction and Realty, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.